Status of Greenhead Base, Lerwick, Shetland Background Experience - - PowerPoint PPT Presentation

status of greenhead base lerwick shetland
SMART_READER_LITE
LIVE PREVIEW

Status of Greenhead Base, Lerwick, Shetland Background Experience - - PowerPoint PPT Presentation

Status of Greenhead Base, Lerwick, Shetland Background Experience Future Presented by James Johnson Decommissioning Manager for PetersonSBS Background - Decommissioning Interest began in 1999 Market Development Established in 1999 to


slide-1
SLIDE 1

Background Experience Future

Status of Greenhead Base, Lerwick, Shetland

Presented by James Johnson Decommissioning Manager for PetersonSBS

slide-2
SLIDE 2
  • Market Development

Established in 1999 to market and develop Decommissioning opportunity for Shetland Contract award in 2005 from Aker Solutions and Total for the Frigg Cessation Project Currently working on FEED and feasibility studies for Topsides, Jackets, Subsea and Single Lift

  • Operational Philosophy

to build on Best Industry practice to develop Shetland into a

“centre of excellence”

for Decommissioning

Background - Decommissioning Interest began in 1999

slide-3
SLIDE 3
  • Shetland Decommissioning

The trading name for a joint venture / cooperation agreement between PetersonSBS [PSBS]

and Veolia Environmental Services [Veolia] with support from Lerwick Port Authority [LPA]

  • Stakeholders Today

PetersonSBS Develop & Operate the Facility Providing Marine & Quayside Services

(formerly SBS Logistics)

Veolia provide the Scrap Handling, Waste Management & Environmental Services Lerwick Port Authority Operate the Harbour

Background - Company Stakeholders

slide-4
SLIDE 4

Background - Geography

slide-5
SLIDE 5
  • All Weather Port
  • Open 24/7
  • Over 3,000m of Quayside
  • Excellent Freight

Links with the UK Mainland

  • Local Support Services

with 30 years of Oil & Gas Experience

Background - Lerwick Harbour

Greenhead Base

Drill Cuttings Plant New Landfill Site Decommissioning Facility Energy Recovery Incinerator Fabrication Facility

slide-6
SLIDE 6
  • Decommissioning Facility

Concrete Pad with impermeable membrane - covering an area of ~20,000 sq. m.

  • Includes Wash Bay, Bunded Storage, Quarantine Area & Emergency Stations

The Pad is Fully Enclosed - all drainage leads to Class 1 Interceptor

  • Fully Licensed with PPC permit issued by SEPA
  • RSA authorisation approved for receipt, handling and temp storage of LSA/NORM

Background - Decommissioning Facility

slide-7
SLIDE 7
  • Piece Small Operations

Piece Small Decommissioning of platform MCP-01 started in 2006 The 1st Campaign ran from Aug-Dec 2006 This was completed in 2008 with the 2nd Campaign running through Jan-Dec 2008 The Greenhead Base acted as the forwarding supply for all of MCP-01 Logistics requirements and

all piece-small Waste materials were processed through Greenhead

Experience - Piece Small

slide-8
SLIDE 8
  • Piece Small Operations

Primary processing carried out offshore; Materials were packed into skips and delivered onshore via PSV Scrap Handling, Waste Segregation, Processing and Environmental Accounting managed Onshore

  • This included all Hazardous Wastes; e.g: Asbestos, WEEE, Batteries etc
  • All materials were packaged and shipped to Licensed and Approved Disposal routes

Experience - Piece Small

slide-9
SLIDE 9

Experience - Single Piece - TCP2 - MSF

(~11,100 Te across the Quay) (one of the largest structures loaded into the UK)

  • TCP2 Module support Frame ~ 8730Te

The MSF was lifted offshore by Saipem UK using the S7000 Crane Vessel Landed onto a bespoke Grillage on the S600 Launch Barge it was towed to shore in July 2007 Many months of Preparatory Engineering & Construction works were required Onshore Also the presence of the skid rails on the barge required the MSF to be loaded-in over the Bow of

the barge, this required significant barge works and barge manoeuvring

slide-10
SLIDE 10

Experience – MSF - Barge Manoeuvring - Video

slide-11
SLIDE 11

Experience - Single Piece - TCP2 - MSF

  • Load-in Logistics and Planning

Load-in Operations were all planned to specific date and tide; 358 axle lines mobilised from Europe, America and Asia Tailored Ballasting & Mooring systems Mobilised & Installed 3 Weeks of tightly programmed Preparations & Fabrications Onshore and On Barge

(All works completed on schedule and without significant incident)

slide-12
SLIDE 12

Experience – MSF - Load-in Operations - Video

(~11,100 Te across the Quay) (one of the largest structures loaded into the UK)

slide-13
SLIDE 13

Experience - Single Piece - TCP2 - MSF

  • Handover for Decontamination

Decontamination Operations took approximately 12 weeks Access (7m height), Safety Inspections, Make Safe

(Install Emergency Equipment, Emergency Exits, Lights, First Aid and Fire etc)

Inventory & Mapping Decontamination - Draining & Cleaning Asbestos Removal W.E.E.E Removal (Waste Electrical and Electronic Equipment Regulations)

slide-14
SLIDE 14

Experience - Single Piece - TCP2 - MSF

  • Demolition Methods

Reduction by Machine was maximised - Leibherr 984 + 19Te LaBounty shear However Hot-work & Pre-cutting was required due to extreme steel thickness (Up to 100mm) Exclusion zones set-up for the Cutting Operations Positive Pressure masks for Hot-work (Minimise risks from Iso-cyanate paint fumes)

slide-15
SLIDE 15
slide-16
SLIDE 16
slide-17
SLIDE 17
slide-18
SLIDE 18
slide-19
SLIDE 19
slide-20
SLIDE 20
slide-21
SLIDE 21
slide-22
SLIDE 22
slide-23
SLIDE 23
slide-24
SLIDE 24
slide-25
SLIDE 25

Experience - Single Piece - TCP2 - MSF

  • Summary and Conclusion

The TCP2 MSF is one of the largest “single piece” structures to be transported and

decommissioned from the North Sea to date

The success of this project has proven Shetland’s capability for handling Large Scale projects The Onshore Operations were completed on schedule, and without significant incident or LTI We are now looking to the future for further works, alliances and development opportunities

slide-26
SLIDE 26

The Future - Study works & Development Options - Animation

slide-27
SLIDE 27

The Future - Study works & Development Options - Animation

slide-28
SLIDE 28

The Future - Study works & Development Options - Animation

Existing

slide-29
SLIDE 29

The Future - Study works & Development Options - Animation

Development option - South

slide-30
SLIDE 30

The Future - Study works & Development Options - Animation

Development option - North

slide-31
SLIDE 31

The Future - Study works & Development Options - Animation

Development option – North Phase 2 – extend to -20m

slide-32
SLIDE 32

The Future - Study works & Development Options - Animation

slide-33
SLIDE 33

The Future - Study works & Development Options - Animation

slide-34
SLIDE 34

The Future - Study works & Development Options - Animation

slide-35
SLIDE 35

Thank you - Any Questions?

Email jjohnson@petersonsbs.com Telephone +44(0) 1595 743 413