status of greenhead base lerwick shetland
play

Status of Greenhead Base, Lerwick, Shetland Background Experience - PowerPoint PPT Presentation

Status of Greenhead Base, Lerwick, Shetland Background Experience Future Presented by James Johnson Decommissioning Manager for PetersonSBS Background - Decommissioning Interest began in 1999 Market Development Established in 1999 to


  1. Status of Greenhead Base, Lerwick, Shetland Background Experience Future Presented by James Johnson Decommissioning Manager for PetersonSBS

  2. Background - Decommissioning Interest began in 1999 � Market Development � Established in 1999 to market and develop Decommissioning opportunity for Shetland � Contract award in 2005 from Aker Solutions and Total for the Frigg Cessation Project � Currently working on FEED and feasibility studies for Topsides, Jackets, Subsea and Single Lift � Operational Philosophy to build on Best Industry practice to develop Shetland into a “centre of excellence” for Decommissioning

  3. Background - Company Stakeholders � Shetland Decommissioning � The trading name for a joint venture / cooperation agreement between PetersonSBS [PSBS] and Veolia Environmental Services [Veolia] with support from Lerwick Port Authority [LPA] � Stakeholders Today � PetersonSBS Develop & Operate the Facility Providing Marine & Quayside Services (formerly SBS Logistics) � Veolia provide the Scrap Handling, Waste Management & Environmental Services � Lerwick Port Authority Operate the Harbour

  4. Background - Geography

  5. Background - Lerwick Harbour • All Weather Port • Open 24/7 • Over 3,000m of Quayside • Excellent Freight Links with the UK Mainland • Local Support Services with 30 years of Oil & Greenhead Base Gas Experience Decommissioning Facility Drill Cuttings Plant Fabrication Facility New Landfill Site Energy Recovery Incinerator

  6. Background - Decommissioning Facility � Decommissioning Facility � Concrete Pad with impermeable membrane - covering an area of ~20,000 sq. m. • Includes Wash Bay, Bunded Storage, Quarantine Area & Emergency Stations � The Pad is Fully Enclosed - all drainage leads to Class 1 Interceptor • Fully Licensed with PPC permit issued by SEPA • RSA authorisation approved for receipt, handling and temp storage of LSA/NORM

  7. Experience - Piece Small � Piece Small Operations � Piece Small Decommissioning of platform MCP-01 started in 2006 � The 1 st Campaign ran from Aug-Dec 2006 � This was completed in 2008 with the 2 nd Campaign running through Jan-Dec 2008 � The Greenhead Base acted as the forwarding supply for all of MCP-01 Logistics requirements and all piece-small Waste materials were processed through Greenhead

  8. Experience - Piece Small � Piece Small Operations � Primary processing carried out offshore; � Materials were packed into skips and delivered onshore via PSV � Scrap Handling, Waste Segregation, Processing and Environmental Accounting managed Onshore • This included all Hazardous Wastes; e.g: Asbestos, WEEE, Batteries etc • All materials were packaged and shipped to Licensed and Approved Disposal routes

  9. Experience - Single Piece - TCP2 - MSF (~11,100 Te across the Quay) (one of the largest structures loaded into the UK) � TCP2 Module support Frame ~ 8730Te � The MSF was lifted offshore by Saipem UK using the S7000 Crane Vessel � Landed onto a bespoke Grillage on the S600 Launch Barge it was towed to shore in July 2007 � Many months of Preparatory Engineering & Construction works were required Onshore � Also the presence of the skid rails on the barge required the MSF to be loaded-in over the Bow of the barge, this required significant barge works and barge manoeuvring

  10. Experience – MSF - Barge Manoeuvring - Video

  11. Experience - Single Piece - TCP2 - MSF � Load-in Logistics and Planning � Load-in Operations were all planned to specific date and tide; � 358 axle lines mobilised from Europe, America and Asia � Tailored Ballasting & Mooring systems Mobilised & Installed � 3 Weeks of tightly programmed Preparations & Fabrications Onshore and On Barge (All works completed on schedule and without significant incident)

  12. Experience – MSF - Load-in Operations - Video (~11,100 Te across the Quay) (one of the largest structures loaded into the UK)

  13. Experience - Single Piece - TCP2 - MSF � Handover for Decontamination � Decontamination Operations took approximately 12 weeks � Access (7m height), Safety Inspections, Make Safe (Install Emergency Equipment, Emergency Exits, Lights, First Aid and Fire etc) � Inventory & Mapping � Decontamination - Draining & Cleaning � Asbestos Removal � W.E.E.E Removal (Waste Electrical and Electronic Equipment Regulations)

  14. Experience - Single Piece - TCP2 - MSF � Demolition Methods � Reduction by Machine was maximised - Leibherr 984 + 19Te LaBounty shear � However Hot-work & Pre-cutting was required due to extreme steel thickness (Up to 100mm) � Exclusion zones set-up for the Cutting Operations � Positive Pressure masks for Hot-work (Minimise risks from Iso-cyanate paint fumes)

  15. Experience - Single Piece - TCP2 - MSF � Summary and Conclusion � The TCP2 MSF is one of the largest “single piece” structures to be transported and decommissioned from the North Sea to date � The success of this project has proven Shetland’s capability for handling Large Scale projects � The Onshore Operations were completed on schedule, and without significant incident or LTI � We are now looking to the future for further works, alliances and development opportunities

  16. The Future - Study works & Development Options - Animation

  17. The Future - Study works & Development Options - Animation

  18. The Future - Study works & Development Options - Animation Existing

  19. The Future - Study works & Development Options - Animation Development option - South

  20. The Future - Study works & Development Options - Animation Development option - North

  21. The Future - Study works & Development Options - Animation Development option – North Phase 2 – extend to -20m

  22. The Future - Study works & Development Options - Animation

  23. The Future - Study works & Development Options - Animation

  24. The Future - Study works & Development Options - Animation

  25. Thank you - Any Questions? Email jjohnson@petersonsbs.com Telephone +44(0) 1595 743 413

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend