Project Schedule
- Preliminary Design (Current Phase)
- Preliminary Engineering Plans
- Environmental Studies
- Right-of-Way Clearance – Spring 2019 to Summer 2020
- Final Design – Summer 2019 to Summer 2020
- Utility Relocation Work – 2019 and 2020
- Contract Award Date – Late 2020
- Construction – Spring 2021 – Fall 2023
SLIDE 4
Project Scope
East Street (Main Street to Columbia Boulevard)
SLIDE 5
Project Scope
East Street (Columbia Boulevard to 7th Street)
SLIDE 6
Project Scope
Poplar Street (7th Street to 9th Street)
SLIDE 7
Project Scope
Poplar Street/Ferry Road (9th Street to Susquehanna River)
SLIDE 8
Project Typical Section
SLIDE 9
Project Scope
Columbia Boulevard (East Street to Park Street)
SLIDE 10
Project Scope
Local Streetscape Project
SLIDE 11
Proposed Traffic Control Plan
Poplar Street-Ferry Road-East Street (6th St. to Susq. River Bridge)
- Full roadway closure of S.R. 0487
- Posted detour in both directions
- Work to be done in phases to maximize access to property
- wners and businesses
SLIDE 12
Traffic Control Plan Phase 1
SLIDE 13
Traffic Control Plan Phase 1
SLIDE 14
Traffic Control Plan Phase 2
SLIDE 15
Traffic Control Plan Phase 3
SLIDE 16
Traffic Control Plan Phase 4
SLIDE 17
Traffic Control Plan Phase 5
SLIDE 18
Proposed Traffic Control Plan
East Street (Main Street to 6th Street)
- East Street has wide 46-foot cross-section
- Roadway closure in NB direction with posted detours
- Roadway to remain open in SB direction
- Work to be done in phases to maximize access to
property owners and businesses
SLIDE 19
Traffic Control Plan Phases 6-8
SLIDE 20
Traffic Control Plan Phase 6
SLIDE 21
Traffic Control Plan Phase 7
SLIDE 22
Traffic Control Plan Phase 8
SLIDE 23
Proposed Traffic Control Plan
- Contractor will determine order of phasing
- Contractor will not be permitted to close travel lanes on
the East Street section and Poplar Street/Ferry Road section at the same time
- Contractor will hold a public meeting prior to construction
to explain schedule
SLIDE 24
Proposed Traffic Control Plan
- Signing for business access
- Emergency responder coordination
- Pedestrian Access and Detours Details
- Tree Trimming and Removal
SLIDE 25
Contact Information
Justin Gochenauer PennDOT Project Manager PennDOT Engineering District 3-0 715 Jordan Avenue P .O. Box 218 Montoursville, PA 17754 (717) 221-2010 c-jgochena@pa.gov
SLIDE 26
Thank you for Attending Tonight’s Meeting Please help us by completing a project survey form and submitting in the designated Comment Box or mailing it to the PennDOT Project Manager