State Highway 5 (SH 5) From: South of FM 1378 To: South of CR 275 Collin County, Texas VIRTUAL PUBLIC HEARING June 11, 2020 CSJs: 0047-05-054, 0364-04-049 & 0047-09-034 June 11, 2020 PUBLIC HEARING PURPOSE 1. Inform the public of


slide-1
SLIDE 1

CSJs: 0047-05-054, 0364-04-049 & 0047-09-034 June 11, 2020

State Highway 5 (SH 5)

From: South of FM 1378 To: South of CR 275 Collin County, Texas VIRTUAL PUBLIC HEARING

June 11, 2020

slide-2
SLIDE 2

CSJs: 0047-05-054, 0364-04-049 & 0047-09-034 June 11, 2020

PUBLIC HEARING PURPOSE

  • 1. Inform the public of project status and project recommendations
  • 2. Describe the project so the public can determine how they may

be affected

  • 3. Provide the public the opportunity to provide input
  • 4. Develop a record of public participation

2

slide-3
SLIDE 3

CSJs: 0047-05-054, 0364-04-049 & 0047-09-034 June 11, 2020

HOW TO SUBMIT PUBLIC COMMENTS

3

slide-4
SLIDE 4

CSJs: 0047-05-054, 0364-04-049 & 0047-09-034 June 11, 2020

VIEWING DESIGN SCHEMATIC AND ENVIRONMENTAL DOCUMENTATION

▪ Websites:

– www.keepitmovingdallas.com/SH5 Direct site link to the posted materials – www.txdot.gov Search “Public Meetings and Hearings” The information presented on these websites is the same information being presented in this video.

4

slide-5
SLIDE 5

CSJs: 0047-05-054, 0364-04-049 & 0047-09-034 June 11, 2020

PROJECT LOCATION, NEED AND PURPOSE

PR PROJE OJECT LIM CT LIMIT ITS: S: ▪ SH 5 from south of FM 1378 to south of CR 275 ▪ Project Length: 7.2 miles ▪ Cities of McKinney and Fairview ▪ Collin County PR PROJE OJECT NEED: CT NEED: ▪ Anticipated future traffic demand increase ▪ Highway does not meet current design and safety standards ▪ Increase in crashes within the project limits PR PROJEC OJECT T PUR PURPOSE: POSE: ▪ Improve safety and mobility ▪ Update roadway to current design and safety standards

5

slide-6
SLIDE 6

CSJs: 0047-05-054, 0364-04-049 & 0047-09-034 June 11, 2020

EXISTING HIGHWAY

6

So South uth of

  • f FM 1

FM 1378 8 to Sp

  • Spur

ur 399 9 an and d Power erhouse house St St t to sou

  • south

th of

  • f CR

CR 2 275: R 5: Rural ural Sec Secti tion,

  • n, 2-lane

lane Sp Spur ur 399 to

  • Mc

McMakin Makin St St and and US US 38 380 to P

  • Power

erhouse house St St: R : Rural ural to U

  • Urba

rban n Tran ransition sition Sec Secti tion,

  • n, 4-lane

lane Mc McMak Makin in St St t to US 3

  • US 380:

0: Urba rban n Sec Secti tion,

  • n, 4-lane

lane

slide-7
SLIDE 7

CSJs: 0047-05-054, 0364-04-049 & 0047-09-034 June 11, 2020

PROPOSED HIGHWAY

7

So South uth of

  • f FM 1

FM 1378 8 to Sp

  • Spur

ur 399 9 an and d N T N Tenn ennessee essee St St t to sou

  • south

th of

  • f CR

CR 2 275: U 5: Urba rban n Sec Secti tion,

  • n, 4-lane

lane Sp Spur ur 399 to El D

  • El Dora
  • rado

do Blv Blvd: U d: Urba rban n Sec Secti tion,

  • n, 6-lane

lane El D El Dorad

  • rado
  • Blv

Blvd t d to N T

  • N Tenn

ennessee essee St St: U : Urba rban n Sec Secti tion,

  • n, 4-lane

lane

slide-8
SLIDE 8

CSJs: 0047-05-054, 0364-04-049 & 0047-09-034 June 11, 2020

UTILITY ADJUSTMENTS ▪ Underground and overhead utilities – Adjustments and relocations may be required prior to and during construction of the proposed project – No substantial service interruptions are anticipated

8

slide-9
SLIDE 9

CSJs: 0047-05-054, 0364-04-049 & 0047-09-034 June 11, 2020

PROJECTED COST & SCHEDULE

Current Let Date Summer 2023 Construction Duration Approximately 3 years Estimated Total Project Cost $138 million

9

slide-10
SLIDE 10

CSJs: 0047-05-054, 0364-04-049 & 0047-09-034 June 11, 2020

REVIEW AND APPROVAL OF ENVIRONMENTAL DOCUMENT

The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried-out by TxDOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 9, 2019, and executed by FHWA and TxDOT.

10

slide-11
SLIDE 11

CSJs: 0047-05-054, 0364-04-049 & 0047-09-034 June 11, 2020

ENVIRONMENTAL REVIEW/IMPACTS ADDRESSED

11

▪ Air Quality ▪ Archeological Resources ▪ Biological Resources ▪ Community/Socioeconomic ▪ Historic Resources ▪ Hazardous Materials ▪ Right of Way/Displacements ▪ Traffic Noise ▪ Vegetation and Wildlife ▪ Water Resources ▪ Wetlands/Waters of the U.S. ▪ Section 4(f) Resources

slide-12
SLIDE 12

CSJs: 0047-05-054, 0364-04-049 & 0047-09-034 June 11, 2020

ENVIRONMENTAL REVIEW – RIGHT OF WAY

Proposed Right of Way (ROW)/Displacements

  • Approximately 28 acres of new right of way would be required
  • Four commercial establishments would potentially be

displaced

  • No residences would be displaced
  • All ROW acquisition would be completed in accordance with

the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970, as amended.

12

slide-13
SLIDE 13

CSJs: 0047-05-054, 0364-04-049 & 0047-09-034 June 11, 2020

ENVIRONMENTAL REVIEW – WATERS OF THE U.S.

13

Waters of the U.S., including Wetlands

  • The project would impact eight jurisdictional stream crossings,

totaling approximately 1.0 acres and one potential wetland at Wilson Creek, totaling 0.2 acres.

  • USACE Section 404 Nationwide Permit (NWP) 14 is required. A

pre-construction notification (PCN) and compensatory mitigation would be required for the Section 404 impacts at 3 of the identified stream crossings and the potential wetland area.

slide-14
SLIDE 14

CSJs: 0047-05-054, 0364-04-049 & 0047-09-034 June 11, 2020

ENVIRONMENTAL REVIEW – FLOODPLAINS

14

Floodplains

  • Portions of the project are within the 100-year floodplains

associated with Wilson Creek and East Fork Trinity River.

  • The hydraulic design for this project would be in accordance

with current FHWA, TxDOT, and local design policies, laws, regulations, and standards.

slide-15
SLIDE 15

CSJs: 0047-05-054, 0364-04-049 & 0047-09-034 June 11, 2020

ENVIRONMENTAL REVIEW – HISTORIC RESOURCES

15

Historic Resources

  • Right of way would be needed from three properties containing historic

structures:

  • 0.0014 acres of ROW from a property containing two listed historic

structures (Joseph Field Dulaney House and the Faires-Bell House)

  • 0.0003 acres of ROW from a commercial building property listed as

contributing to the McKinney Commercial Historic District (southwest corner of Anthony St. and SH 5)

  • 0.0026 acres of ROW from a commercial building property listed as

contributing to the McKinney Commercial Historic District (northwest corner of E. Louisiana St. and SH 5)

  • The proposed project would have no adverse effects on the historic properties

under Section 106 (identifies historic sites and project impacts).

  • A Section 4(f) De Minimis determination is anticipated – little to no impact to

historic sites.

slide-16
SLIDE 16

CSJs: 0047-05-054, 0364-04-049 & 0047-09-034 June 11, 2020

ENVIRONMENTAL REVIEW – HAZARDOUS MATERIALS

16

Hazardous Materials

  • One hazardous materials site poses high environmental risk to

the project, and four pose moderate environmental risk.

  • ROW acquisitions are anticipated for four of the high or

moderate risk sites.

  • Special provisions will be included in the construction plans to

handle hazardous materials and/or petroleum contamination according to applicable federal, state and local regulations.

slide-17
SLIDE 17

CSJs: 0047-05-054, 0364-04-049 & 0047-09-034 June 11, 2020

ENVIRONMENTAL REVIEW – TRAFFIC NOISE

17

Traffic Noise

  • Traffic Noise Analysis showed traffic noise impacts to

multiple receivers.

  • Mitigation was analyzed for all impacted receivers.
  • Two noise barriers are proposed to mitigate for traffic noise.
  • A noise workshop will be conducted to allow property
  • wners and residents adjacent to the proposed barriers to

vote on their construction.

slide-18
SLIDE 18

CSJs: 0047-05-054, 0364-04-049 & 0047-09-034 June 11, 2020

ENVIRONMENTAL REVIEW CONTINUED

18

Conclusion:

  • Studies, analyses and evaluation of the proposed

project indicate no significant impacts.

slide-19
SLIDE 19

CSJs: 0047-05-054, 0364-04-049 & 0047-09-034 June 11, 2020

NEXT STEPS AND TIMELINE

Public Meeting held November 2018 Schematic Approved April 2020 Public Hearing June 2020

Environmental Clearance Anticipated July 2020

ROW Acquisition Summer 2020 Utility Relocations Fall 2021

Construction Letting Summer 2023

19

  • Public Comment Period (ends June 26, 2020)
  • Anticipated Environmental Clearance – July 2020
  • ROW Acquisition Begins – Summer 2020
  • Utility Relocation Begins – Fall 2021
  • Construction Letting – Summer 2023

PROJECT TIMELINE

“Dates subject to Change”

slide-20
SLIDE 20

CSJs: 0047-05-054, 0364-04-049 & 0047-09-034 June 11, 2020

HOW TO SUBMIT PUBLIC COMMENTS

20

www.keepitmovingdallas.com/SH5

slide-21
SLIDE 21

CSJs: 0047-05-054, 0364-04-049 & 0047-09-034 June 11, 2020

Thank you for your interest in the STATE HIGHWAY 5 (SH 5) IMPROVEMENTS PROJECT