stakeholder meeting
play

Stakeholder Meeting April 15, 2019 CURRENT DESIGN STATUS OVERALL - PowerPoint PPT Presentation

Stakeholder Meeting April 15, 2019 CURRENT DESIGN STATUS OVERALL DESIGN STATUS Structures 40% Maintenance of Traffic (MOT) 45% Roadway - 75% MAJOR DESIGN SUBMITTALS TO DATE: Master Plans for Roadway - Traffic


  1. Stakeholder Meeting April 15, 2019

  2. CURRENT DESIGN STATUS OVERALL DESIGN STATUS • • Structures – 40% • Maintenance of Traffic (MOT) – 45% Roadway - 75% MAJOR DESIGN SUBMITTALS TO DATE: • Master Plans for Roadway - Traffic Control Plans (TCP), Signing and ITS • 90% roadway plans for SR 836, I-395 • Final roadway plans for I-95 and SR 836 • Final Phase I MOT plans for SR 836, I-395 and I-95 • 60% signature bridge foundation plans • TCP detour routes and generic details 2

  3. UPCOMING CONSTRUCTION THREE MONTH LOOK ACTIVITIES AHEAD * This schedule does not reflect days added to the contract for holidays, weather days or special events • Nighttime eastbound lane closures for soil boring operations (Ongoing) • Installation of ITS devices for the Smart Workzone Management System (Ongoing) • Nighttime single and double lane closures on SR 836 (Ongoing) • Traffic shift on SR 836 between NW 27 Avenue to NW 12 Avenue – Travel lanes shifted to the outside (Week of April 15)) 3

  4. SR 836 PHASE 1 Meidan Work Zone LEGEND N Eastbound and westbound SR 836 travel lanes will be shifted to the right approximately six feet to set up a work zone in the median area from east of the toll gantry to west of the Miami River 4

  5. SR 836 – NW 17 AVENUE CRANE PAD CONSTRUCTION * This schedule does not reflect days added to the contract for holidays, weather days or special events 5

  6. SR 836 PHASE 1 – STEP 1A Remove existing barrier wall TBW TBW • Install temporary barrier wall from approximately NW 18 Avenue to west of the Miami River to set up a work zone in the middle (mid-April) • Install temporary barrier wall (TBW) from east of the toll gantry to west of the Miami River to set up a work zone in the middle (mid-April) • Remove existing median barrier wall for the first eight spans • Nighttime closures of NW 17 Avenue will be required when there are demolition activities overhead 6

  7. SR 836 PHASE 1 – STEP 1A Closure Pour TBW TBW • After median concrete barrier wall is removed the contractor will perform a concrete closure pour to join the two bridges. 7

  8. SR 836 PHASE 1 – STEP 1 Widening of SR 836 to the Future widening for south to create future westbound SR 836 eastbound lanes 8

  9. UPCOMING CONSTRUCTION THREE MONTH LOOK ACTIVITIES AHEAD SR 836 UPCOMING CONSTRUCTION ACTIVITIES • Utility relocations (ongoing) • Removal of pavers on sidewalks at NW 13 Street and Biscayne Boulevard (Ongoing) • Temporary widening of NE 1 Avenue (May) • Permanent closure of NE 12 Street between Biscayne Boulevard and NE 2 Avenue; Traffic to be routed to NE 13 Street (June) • Widening activity on NE 13 Street between Biscayne Boulevard and NE 2 Avenue (May/June) • Bridge foundation work for I-395 collector-distributor bridges (June/July) 9

  10. UPCOMING CONSTRUCTION THREE MONTH LOOK ACTIVITIES AHEAD SR 836 UPCOMING CONSTRUCTION ACTIVITIES Bridge foundation work for westbound Signature Bridge (August/September) 10

  11. UPCOMING CONSTRUCTION THREE MONTH LOOK ACTIVITIES AHEAD * This schedule does not reflect days added to the contract for holidays, weather days or special events • Installation of new drainage (ongoing) • Construction of foundations for new overhead sign structures (late- April). This work will require continuous weekend lane closures starting at 11 p.m. on Friday until 5:30 a.m. on Monday • Construct median barrier wall (April/May) • Begin concrete pavement replacement (May) 11

  12. * This schedule does not reflect days added to the contract for holidays, weather days or special events 12

  13. * This schedule does not reflect days added to the contract for holidays, weather days or special events Begin foundation work on northbound I-95 bridge approaching ramp to I-195 (late April) 13

  14. MAINTENANCE OF TRAFFIC (MOT)/HOURS SR 836 SPECIFIC I-395 SPECIFIC Mainline Nightly Closures Mainline Nightly Closures • 8 pm to 5:30 am Sunday thru Thursday • 10 pm to 5:30 am Sunday thru Thursday • 8:30 pm to 9 am Friday • 1 am to 7 am Saturday and Sunday • 8:30 pm to 11 am Saturday I-95 SPECIFIC RAMPS • 10 pm to 6:30 am Sunday thru Thursday​ Mainline Nightly Closures • 9 pm to 5:30 am Sunday thru Thursday • 11 pm to 7 am Friday and Saturday​ SPECIAL NOTES: • Special events will be taken into account when scheduling closures • Hours noted above are for single lane closures, multi-lane closures will occur later • Weekend lane closures will be permitted on I-95 from 11 p.m. on Friday to 5:30 a.m. on Monday • The contract documents allows for weekend closures on certain ramps 14

  15. TRAFFIC MANAGEMENT SYSTEM Smart Work Zone Management System (SWZMS) - The project will implement a SWZMS that will utilize Intelligent Transportation System (ITS) Devices such as traffic cameras, data collection devices and portable message signs to: • Provide drivers with real-time travel information; • Encourage motorists to take alternate routes; • Clear incidents more quickly, thereby reducing secondary incidents; and • Make work zones safer for highway workers and motorists. 15

  16. COMMUNITY OUTREACH PROJECT WEBSITE • www.i-395miami.com • Sign-up for project alerts/updates Lane Closure information Upcoming construction activities Presentations • Calendar of events OUTREACH OFFICE IN THE OVERTOWN COMMUNITY • 1035 NW 3 Avenue, Miami, Florida 33136 STAKEHOLDER MEETINGS • Ongoing individual stakeholder meetings and presentations • Next stakeholder meeting – May 20 16

  17. THANK YOU! www.i-395miami.com Contact: Oscar Gonzalez 786-280-0983 OGonzalez@mrgmiami.com 17

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend