Stakeholder Meeting April 15, 2019 CURRENT DESIGN STATUS OVERALL DESIGN STATUS Structures 40% Maintenance of Traffic (MOT) 45% Roadway - 75% MAJOR DESIGN SUBMITTALS TO DATE: Master Plans for Roadway - Traffic


slide-1
SLIDE 1

Stakeholder Meeting April 15, 2019

slide-2
SLIDE 2

2

CURRENT DESIGN STATUS

  • Master Plans for Roadway - Traffic Control Plans (TCP), Signing and ITS
  • 90% roadway plans for SR 836, I-395
  • Final roadway plans for I-95 and SR 836
  • Final Phase I MOT plans for SR 836, I-395 and I-95
  • 60% signature bridge foundation plans
  • TCP detour routes and generic details

OVERALL DESIGN STATUS

  • Roadway - 75%
  • Structures – 40%
  • Maintenance of Traffic (MOT) – 45%

MAJOR DESIGN SUBMITTALS TO DATE:

slide-3
SLIDE 3

* This schedule does not reflect days added to the contract for holidays, weather days or special events

3

  • Nighttime eastbound lane closures for soil boring operations (Ongoing)
  • Installation of ITS devices for the Smart Workzone Management System (Ongoing)
  • Nighttime single and double lane closures on SR 836 (Ongoing)
  • Traffic shift on SR 836 between NW 27 Avenue to NW 12 Avenue – Travel lanes shifted to

the outside (Week of April 15)) UPCOMING CONSTRUCTION ACTIVITIES THREE MONTH LOOK AHEAD

slide-4
SLIDE 4

4

SR 836 PHASE 1

N

LEGEND

Meidan Work Zone

Eastbound and westbound SR 836 travel lanes will be shifted to the right approximately six feet to set up a work zone in the median area from east of the toll gantry to west of the Miami River

slide-5
SLIDE 5

* This schedule does not reflect days added to the contract for holidays, weather days or special events

5

SR 836 – NW 17 AVENUE CRANE PAD CONSTRUCTION

slide-6
SLIDE 6
  • Install temporary barrier wall from approximately NW 18 Avenue to west of the Miami

River to set up a work zone in the middle (mid-April)

6 TBW TBW Remove existing barrier wall

SR 836 PHASE 1 – STEP 1A

  • Install temporary barrier wall (TBW) from east of the toll gantry to west of the Miami

River to set up a work zone in the middle (mid-April)

  • Remove existing median barrier wall for the first eight spans
  • Nighttime closures of NW 17 Avenue will be required when there are demolition

activities overhead

slide-7
SLIDE 7

7 TBW TBW Closure Pour

SR 836 PHASE 1 – STEP 1A

  • After median concrete barrier wall is removed the contractor will perform a concrete

closure pour to join the two bridges.

slide-8
SLIDE 8

8

SR 836 PHASE 1 – STEP 1

Widening of SR 836 to the south to create future eastbound lanes Future widening for westbound SR 836

slide-9
SLIDE 9

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

9

  • Utility relocations (ongoing)
  • Removal of pavers on sidewalks at NW 13 Street and Biscayne Boulevard (Ongoing)
  • Temporary widening of NE 1 Avenue (May)
  • Permanent closure of NE 12 Street between Biscayne Boulevard and NE 2 Avenue;

Traffic to be routed to NE 13 Street (June)

  • Widening activity on NE 13 Street between Biscayne Boulevard and NE 2 Avenue

(May/June)

  • Bridge foundation work for I-395 collector-distributor bridges (June/July)

UPCOMING CONSTRUCTION ACTIVITIES THREE MONTH LOOK AHEAD

slide-10
SLIDE 10

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

10

Bridge foundation work for westbound Signature Bridge (August/September)

UPCOMING CONSTRUCTION ACTIVITIES THREE MONTH LOOK AHEAD

slide-11
SLIDE 11

* This schedule does not reflect days added to the contract for holidays, weather days or special events

11

  • Installation of new drainage (ongoing)
  • Construction of foundations for new overhead sign structures (late- April). This work

will require continuous weekend lane closures starting at 11 p.m. on Friday until 5:30 a.m. on Monday

  • Construct median barrier wall (April/May)
  • Begin concrete pavement replacement (May)

UPCOMING CONSTRUCTION ACTIVITIES THREE MONTH LOOK AHEAD

slide-12
SLIDE 12

* This schedule does not reflect days added to the contract for holidays, weather days or special events

12

slide-13
SLIDE 13

* This schedule does not reflect days added to the contract for holidays, weather days or special events

13

Begin foundation work on northbound I-95 bridge approaching ramp to I-195 (late April)

slide-14
SLIDE 14

MAINTENANCE OF TRAFFIC (MOT)/HOURS

I-395 SPECIFIC

Mainline Nightly Closures

  • 10 pm to 5:30 am Sunday thru Thursday
  • 1 am to 7 am Saturday and Sunday

SR 836 SPECIFIC

Mainline Nightly Closures

  • 8 pm to 5:30 am Sunday thru Thursday
  • 8:30 pm to 9 am Friday
  • 8:30 pm to 11 am Saturday

I-95 SPECIFIC

Mainline Nightly Closures

  • 9 pm to 5:30 am Sunday thru Thursday

RAMPS

  • 10 pm to 6:30 am Sunday thru Thursday​
  • 11 pm to 7 am Friday and Saturday​

SPECIAL NOTES:

  • Special events will be taken into account when scheduling closures
  • Hours noted above are for single lane closures, multi-lane closures will occur later
  • Weekend lane closures will be permitted on I-95 from 11 p.m. on Friday to 5:30 a.m. on Monday
  • The contract documents allows for weekend closures on certain ramps

14

slide-15
SLIDE 15
  • Provide drivers with real-time

travel information;

  • Encourage motorists to take

alternate routes;

  • Clear incidents more quickly,

thereby reducing secondary incidents; and

  • Make work zones safer for

highway workers and motorists. Smart Work Zone Management System (SWZMS) - The project will implement a SWZMS that will utilize Intelligent Transportation System (ITS) Devices such as traffic cameras, data collection devices and portable message signs to:

TRAFFIC MANAGEMENT SYSTEM

15

slide-16
SLIDE 16

16

COMMUNITY OUTREACH

PROJECT WEBSITE

  • www.i-395miami.com
  • Sign-up for project alerts/updates

Lane Closure information Upcoming construction activities Presentations

  • Calendar of events

OUTREACH OFFICE IN THE OVERTOWN COMMUNITY

  • 1035 NW 3 Avenue, Miami, Florida 33136

STAKEHOLDER MEETINGS

  • Ongoing individual stakeholder meetings and presentations
  • Next stakeholder meeting – May 20