SR 0 0 3 0 Realignm ent Project SR 0 0 3 0 , Section B0 7 SR 0 0 3 - - PowerPoint PPT Presentation

sr 0 0 3 0 realignm ent project
SMART_READER_LITE
LIVE PREVIEW

SR 0 0 3 0 Realignm ent Project SR 0 0 3 0 , Section B0 7 SR 0 0 3 - - PowerPoint PPT Presentation

Public Officials Presentation PENNSYLVANI A DEPARTMENT OF TRANSPORTATI ON, DI STRI CT 1 1 -0 SR 0 0 3 0 Realignm ent Project SR 0 0 3 0 , Section B0 7 SR 0 0 3 0 , Section B2 1 Greene Township, Beaver County Hookstown Volunteer Fire


slide-1
SLIDE 1

Public Officials Presentation

PENNSYLVANI A DEPARTMENT OF TRANSPORTATI ON, DI STRI CT 1 1 -0

SR 0 0 3 0 Realignm ent Project

SR 0 0 3 0 , Section B0 7 SR 0 0 3 0 , Section B2 1 Greene Township, Beaver County Hookstown Volunteer Fire Department October 24, 2019

slide-2
SLIDE 2

Opening Remarks

slide-3
SLIDE 3

Project Team

PennDOT District 11

  • Cheryl Moon-Sirianni, P.E.
  • Doug Seeley, P.E.
  • Victor DeFazio, P.E.
  • Robert Collins, P.E.
  • Jacqueline Evans, P.E.
  • Robert Slagel, P.E.
  • Mark Young
  • Nick Krobot, P.E.

SAI Consulting Engineers, Inc.

  • William Siess, P.E.
  • Arnold Harker, P.E.

Skelly & Loy Inc.

  • Mike Zizan, P.E.
  • John Gustkey

A.G.E.S. Inc.

  • Sebastian Lobo-Guerreo, P.E.
slide-4
SLIDE 4

Agenda

  • Opening Remarks
  • Project Team
  • Project Scope of Work

– Section B07 Realignment Portion – Section B21 Repaving and Safety I mprovement Portion

  • Phases of Construction and Associated Traffic Impacts.

– Phase 1 – Offline Embankment Construction – Phase 2 – Red Dog Road I ntersection Realignment and Construction – Phase 3 – SR 0030/ Red Dog Road Reconstruction – Phase 4A/ 4B – Completion of Realignment Section and Slide Repairs – Phase 5 – Embankment Repair at WV border and safety improvements from WV border to SR 0168.

  • Anticipated Construction Schedule
  • Questions and Answer Period
slide-5
SLIDE 5

Project Scope of Work – Section B07

slide-6
SLIDE 6

Project Scope of Work – Section B21

slide-7
SLIDE 7

Phases of Construction and Traffic Impacts

slide-8
SLIDE 8

Phases of Construction and Traffic Impacts

slide-9
SLIDE 9

Red Dog Road Detour

slide-10
SLIDE 10

Phases of Construction and Traffic Impacts

slide-11
SLIDE 11

SR 0030 Detour

slide-12
SLIDE 12

Phases of Construction and Traffic Impacts

slide-13
SLIDE 13

Phases of Construction and Traffic Impacts

slide-14
SLIDE 14

Phases of Construction and Traffic Impacts

  • Phase 5
slide-15
SLIDE 15

Anticipated Construction Schedule

  • Bidding/ Award Process. Fall 2019 to Spring 2020
  • Phase 1 Construction: Spring 2020 to Summer 2020
  • Phase 2 Construction: Fall 2020 to Winter 2021
  • Phase 3 Construction: Spring 2021 to Summer 2021
  • Phase 4A/ 4B Construction: Summer 2021 to Fall 2021
  • Phase 5 Construction: Fall 2021 to end of 2021
slide-16
SLIDE 16

Questions?