Springs Initiative Grant Application by FGUA Projects Submitted for FY2020 Funding Applicant Priority: 1. Burkitt Road Septic to Sewer Project 2. Chatmire Septic to Sewer Project 3. Rainbow River & Rio Vista Septic to Sewer Project 2 2


slide-1
SLIDE 1

Springs Initiative Grant Application by FGUA

slide-2
SLIDE 2

2

2

Projects Submitted for FY2020 Funding

Applicant Priority:

  • 1. Burkitt Road Septic to Sewer Project
  • 2. Chatmire Septic to Sewer Project
  • 3. Rainbow River & Rio Vista Septic to Sewer Project
slide-3
SLIDE 3

3

3

Project Proximity to BMAP and PFA

slide-4
SLIDE 4

4

4

Burkitt Road Septic to Sewer

Project Description:

  • Design, Permitting and Construction of sanitary sewer system to serve

Burkitt Road Area

  • 11 OSTDS to be removed from service
  • Funding request includes connection fees and land acquisition
  • Project to benefit Rainbow Springs
  • Located within Rainbow Springs Group BMAP
  • Project Start: 2019
  • Project Completion: 2021
slide-5
SLIDE 5

5

5

Burkitt Road Septic to Sewer

GA6 KC1

slide-6
SLIDE 6

Slide 5 GA6 add a map that shows the project relative to the bmap for each project.

Garri, Alan, 11/30/2018

KC1 Please update this map as well (2400 LF), I could not see a latest version

Keller, Cara, 12/5/2018

slide-7
SLIDE 7

6

6

Burkitt Road Septic to Sewer OPC

COST ESTIMATE FOR GRANT APPLICATION CITY OF DUNNELLON BURKITT ROAD SEPTIC TO SEWER PROJECT ITEM DESCRIPTION QUANTITY UNIT PRICE AMOUNT 1 RESIDENT SEPTIC TANK ABANDONMENT, GRINDER STATION, AND CONNECTION TO SEWER 11 EA $ 30,000 $ 330,000 2 LOW PRESSURE FORCE MAIN AND CONNECTION/MINOR UPGRADE TO EXISTING COLLECTION SYSTEM 2,400 LF $ 25 $ 60,000 3 LAND ACQUISITION 1 LS $ 70,000 $ 70,000 TOTAL $ 460,000 The Engineer has no control over the cost of labor, materials, equipment, or over the Contractor's methods of determining prices or over competitive bidding or market conditions. Opinions of probable costs provided herein are based on the information known to Engineer at this time and represent only the Engineer's judgment as a design professional familiar with the construction industry. The Engineer cannot and does not guarantee that proposals, bids, or actual construction costs will not vary from its opinions of probable costs.

Seeking funding for 100% of total project cost = $460,000

slide-8
SLIDE 8

7

7

Burkett Septic to Sewer

  • Septic Tank Load to Ground Water
  • 11 Septic tanks
  • 23.7 lbs. of TN/Year/Septic Tank
  • 0.5 Attenuation Multiplier
  • 0.9 Recharge Factor
  • 117.0 lbs. of TN/Year to Ground Water
  • City’s WWTP Plant Efficiency
  • 3.9 mg/l of Nitrogen‐Discharge Concentration
  • 2,200 GPD Flow from Septic Tanks per FDEP Evaluation Method
  • 0.4 Attenuation Multiplier
  • 0.9 Recharge Factor
  • 7.0 lbs. of TN/Year to Ground Water
  • Cost Effectiveness for 30 year period
  • 111 lbs. of TN/Year removed Spring Shed
  • Project cost = $460,000
  • $138 per lb. TN removed
slide-9
SLIDE 9

8

8

Chatmire Septic to Sewer

Project Description:

  • Design, Permitting and Construction of sanitary sewer system to serve

the Chatmire Area

  • 210 OSTDS to be removed from service
  • Funding request includes connection fees and land acquisition
  • Project to benefit Rainbow Springs
  • Located within Rainbow Springs Group BMAP and PFA Boundary
  • Project Start: 2019
  • Project Completion: 2021
slide-10
SLIDE 10

9

9

Chatmire Septic to Sewer

slide-11
SLIDE 11

10

10

Chatmire Septic to Sewer OPC

COST ESTIMATE FOR GRANT APPLICATION CITY OF DUNNELLON CHATMIRE SEPTIC TO SEWER PROJECT ITEM DESCRIPTION

QUANTITY UNIT PRICE AMOUNT

1 RESIDENT SEPTIC TANK ABANDONMENT AND CONNECTION TO SEWER

210 EA $ 6,000 $ 1,260,000

2 GRAVITY SEWER (INCLUDES ALL CONSTRUCTION RELATED COMPONENTS)

14,000 LF $ 120 $ 1,680,000

3 FORCE MAIN (INCLUDES ALL CONSTRUCTION RELATED COMPONENTS)

2,000 LF $ 100 $ 200,000

4 LIFT STATION UPGRADE

1 EA $ 128,000 $ 128,000

5 ROADWAY MILLING AND RESURFACING

16,000 LF $ 27 $ 432,000 TOTAL $ 3,700,000

The Engineer has no control over the cost of labor, materials, equipment, or over the Contractor's methods of determining prices or over competitive bidding or market conditions. Opinions of probable costs provided herein are based on the information known to Engineer at this time and represent only the Engineer's judgment as a design professional familiar with the construction industry. The Engineer cannot and does not guarantee that proposals, bids, or actual construction costs will not vary from its opinions of probable costs.

Seeking funding for 100% of total project cost = $3,760,000

slide-12
SLIDE 12

11

11

Chatmire Septic to Sewer

  • Septic Tank Load to Ground Water
  • 210 Septic Tanks
  • 23.7 lbs. of TN/Year/Septic Tank
  • 0.5 Attenuation Multiplier
  • 0.9 Recharge Factor
  • 2,240 Total lbs. of TN/Year to Ground Water
  • City's WWTP Plant Efficiency
  • 3.9 mg/l of Nitrogen Allowed to Discharge
  • 42,000 GPD Flow from Septic Tanks per FDEP Evaluation Method
  • 0.4 Attenuation Multiplier
  • 0.9 Recharge Factor
  • 125 lbs. of TN/Year to Ground Water
  • Cost Effectiveness for a 30 year period
  • 2114 lbs. of TN/Year removed Spring Shed
  • Project cost = $3,700,000
  • $58 per lb. TN removed
slide-13
SLIDE 13

12

12

Rainbow River & Rio Vista Septic to Sewer

Project Description:

  • Design, Permitting and Construction of sanitary sewer system to serve

Rio Vista Area

  • 329 OSTDS to be removed from service
  • Funding request includes connection fees
  • Project to benefit Rainbow Springs
  • Located within Rainbow Springs Group BMAP and PFA Boundary
  • Project Start: 2019
  • Project Completion: 2021
slide-14
SLIDE 14

13

13

Rainbow River & Rio Vista Septic to Sewer

slide-15
SLIDE 15

14

14

Rainbow River & Rio Vista OPC

COST ESTIMATE FOR GRANT APPLICATION CITY OF DUNNELLON RAINBOW RIVER AND RIO VISTA SEPTIC TO SEWER PROJECT ITEM DESCRIPTION QUANTITY UNIT PRICE AMOUNT 1 RESIDENT SEPTIC TANK ABANDONMENT,GRINDER STATIONS, AND CONNECTION TO SEWER 150 EA $ 21,000 $ 3,150,000 2 RESIDENT SEPTIC TANK ABANDONMENT, AND CONNECTION TO SEWER 179 EA $ 6,000 $ 1,074,000 3 GRAVITY SEWER (INCLUDES ALL CONSTRUCTION RELATED COMPONENTS) 25,000 LF $ 120 $ 3,000,000 4 LOW PRESSURE FORCE MAIN 20,000 LF $ 10 $ 200,000 5 REGIONAL LIFT STATION 1 LS $ 726,000 $ 726,000 6 FORCE MAIN (INCLUDES ALL CONSTRUCTION RELATED COMPONENTS) 5,000 LF $ 100 $ 500,000 7 ROADWAY MILLING AND RESURFACING 50,000 LF $ 27 $ 1,350,000 TOTAL $ 10,000,000 The Engineer has no control over the cost of labor, materials, equipment, or over the Contractor's methods of determining prices or over competitive bidding or market conditions. Opinions of probable costs provided herein are based on the information known to Engineer at this time and represent only the Engineer's judgment as a design professional familiar with the construction industry. The Engineer cannot and does not guarantee that proposals, bids, or actual construction costs will not vary from its opinions of probable costs.

Seeking funding for 100% of total project cost = $10,000,000

slide-16
SLIDE 16

15

15

Rainbow River & Rio Vista Septic to Sewer

  • Septic Tank Load to Ground Water
  • 329 Septic Tanks
  • 23.7 lbs. of TN/Year/Septic Tank
  • 0.5 Attenuation Multiplier
  • 0.9 Recharge Factor
  • 3,509 Total lbs. of TN/Year to Ground Water
  • City's WWTP Plant Efficiency
  • 3.9 mg/l of Nitrogen Allowed to Discharge
  • 65,800 GPD Flow from Septic Tanks per FDEP Evaluation Method
  • 0.4 Attenuation Multiplier
  • 0.9 Recharge Factor
  • 196 lbs. of TN/Year to Ground Water
  • Cost Effectiveness for a 30 year period
  • 3312 lbs. of TN/Year removed Spring Shed
  • Project cost = $10,000,000
  • $101 per lb. TN removed
slide-17
SLIDE 17

Springs Initiative Grant Application by FGUA