- Mr. Lee Yun Sang
SPM OUTSTANDING PROJECT MANAGER AWARD 2018 (CONTRACTOR CATEGORY) - - PowerPoint PPT Presentation
SPM OUTSTANDING PROJECT MANAGER AWARD 2018 (CONTRACTOR CATEGORY) - - PowerPoint PPT Presentation
SPM OUTSTANDING PROJECT MANAGER AWARD 2018 (CONTRACTOR CATEGORY) Mr. Lee Yun Sang Project Manager Civil Infra-structure Business Unit Samsung C&T Corporation Downtown Line Stage 3 Contract 922 Contract 922 comprised Expo Station, Overrun
Singapore Expo
Expo Station (EWL)
Changi City Point & Capri Hotel UE BizHub Plaza 8 DBS Asia Hub
Contract 922 comprised Expo Station, Overrun Tunnels, underground Electrical Sub-Station and Rail Facility building. (Project Period: May 2011 ~ Apr. 2017, Opened to public on 21 Oct. 2017) Downtown Line Stage 3 Contract 922
Singapore Expo
- EXPO Station is a Civil Defense Shelter station as well as an Interchange station
connected to EWL Expo Station. It also has underground connection to Changi City Point mall and UE Bizhub building.
- Electrical Substation is an underground building to supply electricity to DTL3 line.
- Rail Facility Building has Integrated Operational Control Centre rooms.
Downtown Line Stage 3 Contract 922
- A transfer-beam with 7 barrette piles was constructed prior to
excavation to support the two footings.
- 8 synchronised hydraulic jacks were installed on the transfer-
beam and provided preloading forces for compensation of the vertical displacement during excavation.
- 6 RC piles supporting each footing were cut away during
excavation.
SMRT Viaduct Transfer Beam
Barrette Pile
The station was constructed underneath two pier footings of operating MRT viaducts by an under-pinning method.
Downtown Line Stage 3 Contract 922
Station Platform
- Ent. D
- Ent. C
- Ent. E
Ventilation Tower IOCC in RF