Spectrometer Solenoid Design and Test Results Spectrometer Solenoid - - PowerPoint PPT Presentation

spectrometer solenoid design and test results
SMART_READER_LITE
LIVE PREVIEW

Spectrometer Solenoid Design and Test Results Spectrometer Solenoid - - PowerPoint PPT Presentation

Spectrometer Solenoid Design and Test Results Spectrometer Solenoid Review November 18, 2009 Steve Virostek Lawrence Berkeley National Lab MICE Cooling Channel Layout Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18,


slide-1
SLIDE 1

Spectrometer Solenoid Design and Test Results

Steve Virostek

Lawrence Berkeley National Lab

Spectrometer Solenoid Review November 18, 2009

slide-2
SLIDE 2

MICE Spectrometer Solenoid Design and Test Results Page 2 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

MICE Cooling Channel Layout

slide-3
SLIDE 3

MICE Spectrometer Solenoid Design and Test Results Page 3 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

  • Magnet 1 design features
  • Magnet 1 testing results
  • Modifications for Magnet 2
  • Magnet 2 test results
  • Photos for discussion

Topics

slide-4
SLIDE 4

MICE Spectrometer Solenoid Design and Test Results Page 4 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

Magnet 1 Original Design

LHe lines Radiation shield Cold mass Vapor return lines Cold head 2nd stage Cold head 1st stage

slide-5
SLIDE 5

MICE Spectrometer Solenoid Design and Test Results Page 5 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

Temperature Sensor Locations

TPR: platinum resistor TRX: Cernox HTR: heater TSD: silicon diode VTM: voltage tap

slide-6
SLIDE 6
  • Magnet cold mass was successfully cooled down to <5K

using a combination of LN and LHe

  • Cool down of the shield was very slow as there was no

direct connection to the LN (i.e. shield cooling by radiation and conduction thru cold mass suppts only)

  • LHe was boiling off from cold mass at a high rate
  • Helium was not being condensed at all by the coolers
  • Since the magnet was cold, an attempt was made to

train the coils

MICE Spectrometer Solenoid Design and Test Results Page 6 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

Magnet 1 Testing Results

slide-7
SLIDE 7
  • The training reached 196 A in all coils (270 A needed to

reach 4 T in the central coil)

  • Magnet training was discontinued when the available

cryogens ran out and so modifications could begin

  • Based on measurements and observations, the coolers

were not maintaining the LHe level, and the shield temperature was ~120 K rather than the specified 80 K

  • These two issues were due to the thermal siphon line

being plugged by frozen N2 and an inadequate thermal connection between the cooler 1st stages and the shield

MICE Spectrometer Solenoid Design and Test Results Page 7 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

Magnet 1 Testing Results (cont’d)

slide-8
SLIDE 8
  • The blocked helium lines was mainly a procedural and

partially a design issue

  • Also, the pressure rise observed within the cold mass

during quench was too high

  • It was determined that the venting of the cold mass

during quench was not sufficient due to crowding of the single vent line with instrumentation wires

  • Several mechanical issues also arose: magnet alignment

in vacuum vessel, support stand height, iron shield support pads, support stand offset

MICE Spectrometer Solenoid Design and Test Results Page 8 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

Magnet 1 Testing Results (cont’d)

slide-9
SLIDE 9
  • Based on the results of the Magnet 1 testing, several

design modifications were proposed

  • Work proceeded to complete the Magnet 2 assembly

with design changes while starting Magnet 1 disassembly

  • A new cold mass cooling scheme was devised as well as

an improved cooldown procedure

  • The 1st stage radiation shield connection was modified

an an attempt to increase the thermal conduction

  • An additional vent line was added to the cold mass
  • An LN reservoir was added for direct cooldown of shield

MICE Spectrometer Solenoid Design and Test Results Page 9 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

Magnet Design Modifications

slide-10
SLIDE 10

Magnet Cooling Configurations

Original Design Design Option A

Cold head Condenser Cold mass shell Coils LHe line Trap Larger diameter No trap

(Magnet 1)

Design Option B

Direct connection LHe

(not adopted) (Magnet 2)

MICE Spectrometer Solenoid Design and Test Results Page 10 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-11
SLIDE 11

MICE Spectrometer Solenoid Design and Test Results Page 11 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

Cryostat and Cooling System Mods

1100 Al radiation shield connections Cold head 1st stage Radiation shield Additional vent line Direct cryostat connection option

slide-12
SLIDE 12

Liquid/vapor He accumulator and cryocooler sleeves

MICE Spectrometer Solenoid Design and Test Results Page 12 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-13
SLIDE 13

MICE Spectrometer Solenoid Design and Test Results Page 13 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

Liquid Nitrogen Reservoir

LN reservoir Radiation shield Thermal plate connection 1st stage cooler connection Vent/fill lines (3)

  • Reservoir provides direct

LN cooldown of shield

  • May improve thermal

connection between 1st stage of cryos and shield

  • Frozen mass of nitrogen

protects leads in event of power failure (if LN is left in reservoir and

  • temp. is low enough)
slide-14
SLIDE 14
  • After completing the described modifications earlier this

year, an attempt was made to cool Magnet 2 with cryogens

  • An ice blockage developed within the cold mass fill line
  • The fill line geometry (90° bends) prevented clearing of the

blockage, and the vendor moved the stinger to a vent line

  • Continuing the fill process led to a leak in a Conflat flange in

the 2nd vent line (the one not being used for filling), venting the vacuum space to helium and aborting the cooldown

  • The Magnet 1 fill line routing has been changed to avoid

sharp bends and thus improve the ability to clear a blockage

MICE Spectrometer Solenoid Design and Test Results Page 14 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

Magnet 2 Testing Results

slide-15
SLIDE 15
  • After warming up the magnet, the Conflat flanges were

replaced with welded joints

  • Since the fill line blockage was likely a procedural issue, a

safer and more robust technique for cooldown was devised (Bross/FNAL) and has worked well

  • The subsequent cooldown was successfully completed in
  • nly ~3 days w/o incident
  • However, the shield temperature fell slowly to only about

~115 K at the ends of the cylinder, resulting in added heat flow into the cold mass via the cold mass supports

MICE Spectrometer Solenoid Design and Test Results Page 15 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

Magnet 2 Testing Results (cont’d)

slide-16
SLIDE 16

80K (no current) 90-95K (182 to 238 A) 102K min 65K Not working 74K No other shield sensors here

Magnet 2 Measured Temperatures

MICE Spectrometer Solenoid Design and Test Results Page 16 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-17
SLIDE 17
  • The improved(?) shield thermal connections and the LN

reservoir did not solve the previous shield problems

  • The coolers are expected to maintain the LHe level after

filling; ~1% of the LHe was being lost overnight (unpowered)

  • At this point, training began and appeared to be going well
  • The magnet underwent five training quenches at currents

ranging from 182 to 238 A

  • At 238 A (w/all coils in series), one of the HTS leads burned
  • ut due to a higher than allowable temp. at the upper end

MICE Spectrometer Solenoid Design and Test Results Page 17 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

Magnet 2 Testing Results (cont’d)

slide-18
SLIDE 18
  • The upper lead temperature without current was ~80 K,

increasing to >90 K with current, eventually resulting in failure of the lead farthest from the coolers

  • The lead problem was a surprise, as it was not noticed in

the earlier Magnet 1 tests; the feedthroughs and all the leads are the same ones used before in Magnet 1

  • We are currently thermally testing the feedthroughs and

leads in an off line test to see what can be learned

MICE Spectrometer Solenoid Design and Test Results Page 18 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

Magnet 2 Testing Results (cont’d)

slide-19
SLIDE 19
  • Changing flexible connection does not appear to have had a

major impact on shield temperatures

  • New Al straps are thicker than the original Cu, but the Cu

conductivity was better and the original straps were shorter

  • Our vendor, Bert Wang, has stated that he believes the

connection to the shield is inadequate

  • There have been no indications of vacuum problems other

than the seal failure that occurred in the vent line

  • No local icing has been observed on the vacuum vessel
  • Temperature measurements using a thermal laser probe have

not revealed any irregularities

MICE Spectrometer Solenoid Design and Test Results Page 19 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

Testing Results Discussion

slide-20
SLIDE 20

MICE Spectrometer Solenoid Design and Test Results Page 20 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

Photos for Discussion

slide-21
SLIDE 21

Upper Leads and HTS Leads

MICE Spectrometer Solenoid Design and Test Results Page 21 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-22
SLIDE 22

Upper Leads and Thermal Intercepts

MICE Spectrometer Solenoid Design and Test Results Page 22 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-23
SLIDE 23

Upper Leads and 300K Feedthrough

MICE Spectrometer Solenoid Design and Test Results Page 23 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-24
SLIDE 24

Upper HTS Leads Thermal Intercept

MICE Spectrometer Solenoid Design and Test Results Page 24 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-25
SLIDE 25

SC leads at cold mass feedthrus

MICE Spectrometer Solenoid Design and Test Results Page 25 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-26
SLIDE 26

Coil Taps & Intercepts for Lower HTS Leads

MICE Spectrometer Solenoid Design and Test Results Page 26 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-27
SLIDE 27

Coil Taps & Intercepts for Lower HTS Leads

MICE Spectrometer Solenoid Design and Test Results Page 27 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-28
SLIDE 28

Magnet 2 HTS Leads (right lead burned out)

MICE Spectrometer Solenoid Design and Test Results Page 28 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-29
SLIDE 29

Radiation Shield Thermal Connection

MICE Spectrometer Solenoid Design and Test Results Page 29 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

6061 Al cylinder ~6 mm thick

slide-30
SLIDE 30

Upper Thermal Shield Connection

MICE Spectrometer Solenoid Design and Test Results Page 30 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

Cu/Al transitions (10 each) 1st stage Cu plate 6061 Al cylinder ~6 mm thick

slide-31
SLIDE 31

Magnet 1 Shield Flexible Connection

MICE Spectrometer Solenoid Design and Test Results Page 31 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

OFHC copper straps

slide-32
SLIDE 32

Magnet 2 Shield Thermal Connection

1100 series aluminum connection to thermal shield (previously thin copper)

MICE Spectrometer Solenoid Design and Test Results Page 32 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-33
SLIDE 33

Magnet 2 Shield with Flexible Connections

MICE Spectrometer Solenoid Design and Test Results Page 33 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-34
SLIDE 34

Plates Welded to Shield for LN Reservoir

MICE Spectrometer Solenoid Design and Test Results Page 34 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-35
SLIDE 35

MLI Wrapped Cold Mass and Shield

MICE Spectrometer Solenoid Design and Test Results Page 35 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-36
SLIDE 36

Partially Assembled Magnet

MICE Spectrometer Solenoid Design and Test Results Page 36 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-37
SLIDE 37

Close Up of Cold Mass End

MICE Spectrometer Solenoid Design and Test Results Page 37 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-38
SLIDE 38

MLI on Shield & Vacuum Vessel Inner Bores

MICE Spectrometer Solenoid Design and Test Results Page 38 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-39
SLIDE 39

MLI Wrapped Cooler Sleeves and Leads

MICE Spectrometer Solenoid Design and Test Results Page 39 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-40
SLIDE 40

Cold Mass Connections (Magnet 1)

MICE Spectrometer Solenoid Design and Test Results Page 40 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-41
SLIDE 41

Cold Mass Support during Fit Up

MICE Spectrometer Solenoid Design and Test Results Page 41 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-42
SLIDE 42

Cold Mass Support Connection to Shield

MICE Spectrometer Solenoid Design and Test Results Page 42 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-43
SLIDE 43

Thermal Shield Support

MICE Spectrometer Solenoid Design and Test Results Page 43 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-44
SLIDE 44

Temperature Sensor on Cold Mass Bore

MICE Spectrometer Solenoid Design and Test Results Page 44 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009

slide-45
SLIDE 45

LHe Cooldown of Magnet

MICE Spectrometer Solenoid Design and Test Results Page 45 Steve Virostek -- Lawrence Berkeley National Laboratory -- November 18, 2009