South Portland-Burlingame Sewer Repair Project—Phase 2

Joe Tursi, Community Outreach City of Portland Environmental Services

September 2020

slide-2
SLIDE 2

2

Why Sewer Rehabilitation is Needed

Part of a City- Wide Sewer Repair Program

Environmental Services l South Portland-Burlingame Sewer Repair Project-Phase 2

Replaces Deteriorating 80 to 100-Year- Old Pipes Upgrades and Extends the Life of the Sewer System Protects Public Health, Property, and Our Environment

slide-3
SLIDE 3

3

  • This project is the second of two phases of sewer repair in the area.
  • Phase 1 construction was completed in July 2020.
  • Phase 2 is currently in design with construction anticipated to begin in summer of 2021.

Project Background

30% Design 60% Design 90% Design Pre-Construction Construction

Design Summer 2021 We are here

Environmental Services l South Portland-Burlingame Sewer Repair Project-Phase 2

slide-4
SLIDE 4

4

  • Over 7,000 feet of public sewer pipes will be

repaired or replaced in the South Portland- Burlingame area.

  • Three different construction methods will be used:
  • Open cut
  • Pipe Bursting
  • Pipe Lining (CIPP)
  • Night work/extended hours proposed in six

locations.

Project Facts

Environmental Services l South Portland-Burlingame Sewer Repair Project-Phase 2

slide-5
SLIDE 5

5

Project Area

Environmental Services l South Portland-Burlingame Sewer Repair Project-Phase 2

  • The project area is loosely bordered by:
  • Interstate 5 to the west
  • S Taylors Ferry Road to the south
  • S Macadam Avenue to the east
  • S Lowell Street to the north
  • The Hillsdale Sewer Repair Projects are

taking place to northwest. For more information visit: www.portlandoregon.gov/bes/hillsdale

slide-6
SLIDE 6

6

Construction Method: Open Trench

Crews deliver materials and stores them in the right-of- way.

1

Crews cut and dig a

  • trench. Material is

hauled away by trucks.

2

Crews install the new pipe and backfills the trench.

3

Crews temporarily patch the trench before returning later to restore the street.

4

Environmental Services l South Portland-Burlingame Sewer Repair Project-Phase 2

slide-7
SLIDE 7

7

Construction Method: Pipe Bursting

Crews weld a new pipe together and lay it out in the street.

1

Crews dig insertion and receiving shafts.

2

A bursting head shatters the existing pipe and pulls the new pipe in place behind it.

3

Crews connect laterals and temporarily patch the shafts before returning later to restore the street.

4

Environmental Services l South Portland-Burlingame Sewer Repair Project-Phase 2

slide-8
SLIDE 8

8

Construction Method: Cured-in-Place Pipe (CIPP) Lining

Crews access the pipe through a manhole.

1

Crews insert a flexible liner into the existing

  • pipe. Steam or UV

light is applied to cure the liner.

2

The liner hardens to seal cracks and form a new smooth pipe within the old.

3

Environmental Services l South Portland-Burlingame Sewer Repair Project-Phase 2

slide-9
SLIDE 9

9

  • Some repairs will likely require night work
  • r extended hours to complete.
  • Environmental Services will apply for a

noise variance to enable the contractor to work both days and nights in certain locations.

Night Work Proposed

Your comments regarding night work are valuable. You can submit comments to the Portland Noise Office by Friday, September 25 to: Email: noise@portlandoregon.gov Phone: 503-823-7350

Environmental Services l South Portland-Burlingame Sewer Repair Project-Phase 2

slide-10
SLIDE 10

10

Night Work Locations

Environmental Services l South Portland-Burlingame Sewer Repair Project-Phase 2

1. SW Bancroft Street between SW Macadam Avenue and SW Moody Avenue. 2. SW Macadam Avenue between SW Bancroft Street and SW Hamilton Court. 3. SW Sweeney Street between SW Kelly and SW Macadam avenues. 4. SW Vermont Street near the intersection with SW Corbett Avenue. 5. SW Macadam Avenue just south of SW Miles Street. 6. SW Terwilliger Boulevard just south of SW Troy Street.

slide-11
SLIDE 11

11

Stay Informed

Visit the project webpage at: www.portlandoregon.gov/bes/spb Sign up for email updates at: www.portlandoregon.gov/bes/70360 Fill out a business survey at: www.portlandoregon.gov/bes/70640 Read project newsletters that are mailed to you

Environmental Services l South Portland-Burlingame Sewer Repair Project-Phase 2

slide-12
SLIDE 12

Questions?

ben@loisdcohen.com zach@loisdcohen.com www.portlandoregon.gov/bes/SPB (503) 975-7073

Ben McLean Zach Johnson