south deep finding it s feet
play

South Deep: Finding Its Feet SOUTH DEEP SITE VISIT 13 February 2015 - PowerPoint PPT Presentation

South Deep: Finding Its Feet SOUTH DEEP SITE VISIT 13 February 2015 Nick Holland, Nico Muller and South Deep Team Introduction NICK HOLLAND Chief Executive Officer South Deep Gold Mine A Gold Fields Franchise Asset One of the largest


  1. South Deep: Finding It’s Feet SOUTH DEEP SITE VISIT 13 February 2015 Nick Holland, Nico Muller and South Deep Team

  2. Introduction NICK HOLLAND Chief Executive Officer

  3. South Deep Gold Mine A Gold Fields Franchise Asset ● One of the largest undeveloped ore bodies in the world ̵ 76.2 Moz of Mineral Resources ̵ 38.2 Moz of Mineral Reserves ● A low cost long life mine ̵ +70-year LoM ● High level of confidence in the ore body ● The mine has been built ● Mechanised operations A Gold Fields Franchise Asset South Deep: Finding it's Feet | Nick Holland, Nico Muller and the South Deep Team | Friday, 13 February 2015 3

  4. South Deep Gold Mine What did Gold Fields Acquire in 2007? ● Low resolution in geological block modelling and limited surface exploration drilling ● No robust Life of Mine plan underpinning reserves ● Shaft hoisting capacity limited to 202 ktpm (Main shaft only) ● Metallurgical plant capacity limited to 220 ktpm ● No development to access the ore body below 95 Level ● Old backfill system ● No underground workshop facilities to maintain large fleet ● Tailings facility was reaching full capacity ● Eskom power supply was limited to 80 MW and no emergency power supply ● Minimal underground cooling facilities and surface fans to develop New Mine ● Mining rate was at an average 80 ktpm (Mechanised 63%, Conventional 37%) ● Hostel accommodation inadequate We Had To Build The Mine! South Deep: Finding it's Feet | Nick Holland, Nico Muller and the South Deep Team | Friday, 13 February 2015 4

  5. South Deep Gold Mine Improved Accuracy and Confidence in Ore Body Modelling • 16 Units • Re-aligned 2005 2008 2010 Subcrop • 16 Units Positions • 4 Units • April 2007 Gold • Kriging of • LIB Drilling • Shore Line Fields acquires Channel Widths • 16 Units Campaign • 16 Units Composite 100% of South & Dynamic • Singular Started • 7 Units • Palinspastically Deep Gold Mine Modelling Subcrop Point • Infill Drilling • Singular Reconstructed • Surface Drilling (GC) Campaign Subcrop Point Depositional Campaign Started Model 2000 Started 2013 2007 2009 Detailed reserve designs for Current Future mine north The entire Mineral Highly detailed Studies in Reserve updated Reserve updated Mine only. Future of the wrench fault Reserve is designed designs for 7 years mechanising the mine estimated designed in detail for the first time in with new models with new models included as part of destress commence using the Bayesian for the first time the LoM the new LOM methodology Evolution of a Fit for Purpose Geological Modelling Process South Deep: Finding it's Feet | Nick Holland, Nico Muller and the South Deep Team | Friday, 13 February 2015 5

  6. South Deep Gold Mine De-risking The Ore Body 3D Seismic Surface drilling LIB Drilling Grade Control Survey (Long Inclined Drilling (2007-2013) Boreholes) (2003) (49,536m) (13,023m) 50m x 50m grid 300m x 300m grid ~20m resolution 600m x 600m grid Covers the whole lease Used for facies Used for facies area south of the wrench determination, structural boundaries, structural Used for structural fault. Used to confirm the definition, stratigraphic definition, stratigraphic definition, stratigraphic base of lava position as modelling, assaying and modelling, assaying and modelling, assaying and well as major structures. resource estimation. resource estimation. grade indication. 0 – 2 Years Ahead of 2 – 10 Years Ahead of 10 - 70 Years Ahead of 10 - 70 Years Ahead of Current Workings. Current Workings. Current Workings. Current Workings. Now One Of The Best Understood Ore Bodies In South Africa South Deep: Finding it's Feet | Nick Holland, Nico Muller and the South Deep Team | Friday, 13 February 2015 6

  7. South Deep Gold Mine Mining Grades Versus Reserve Grades Mining Grades (g/t) 7.0 6.0 5.0 4.0 3.0 2.0 1.0 0.0 2010 2011 2012 2013 2014 Actual Mined Grade Reserve Grade Positive Grade Reconciliation South Deep: Finding it's Feet | Nick Holland, Nico Muller and the South Deep Team | Friday, 13 February 2015 7

  8. South Deep Gold Mine Infrastructure Status 2015 vs 2007 Project Capacity New Capacity Capital* (R’m ) (2007) (2015) New Mine Development - Development Nil 17 km 2,416 - Ore handling capacity 200 ktpm 245 ktpm 489 Twin Shaft Hoisting Capacity 202 ktpm 370 ktpm 868 New Mining Equipment - Fleet upgraded 849 Metallurgical Plant Capacity 200 ktpm 330 ktpm 645 FPT Backfill Nil Plant commissioned 396 Tailings Storage Limited LOM TSF commissioned 389 Surface Exploration Drilling Nil 9 holes completed 116 Underground Refrigeration Nil 25.5 MwR 93 4 x BAC’s 72 * Expenditure 2009 to date We Have Built The Mine - Transition To Build Up Enabled South Deep: Finding it's Feet | Nick Holland, Nico Muller and the South Deep Team | Friday, 13 February 2015 8

  9. South Deep Gold Mine Infrastructure Status 2015 vs 2007 (Continued) Project Capacity New Capacity Capital* (R’m ) (2007) (2015) 93 Level Main Workshop Nil 70 Cat 1 machines 33 Equipping Single Accommodation Upgrades Nil 922 single rooms 70 Eskom Power Supply 80 MW 160 MW 51 - Emergency Power Supply Nil 15 MW Mechanised Training Facilities Nil Technical and practical 26 capacities Mega Surface Store Nil 3,600 m² 15 Sustaining Capital 1,235 Total 7,769 * Expenditure 2009 to date We Have Built The Mine - Transition To Build Up Enabled South Deep: Finding it's Feet | Nick Holland, Nico Muller and the South Deep Team | Friday, 13 February 2015 9

  10. South Deep Gold Mine Evolution of Mining Since 2006 1998 2007 2008 2009 2013 2015 • 96% of current mine • • • Horizontal Crush Limited • Destress destressed vs 66% in 2007 destress pillars mechanised • April 2007 mining (Reserve 2.2 Moz) and introduced mining Gold Fields mechanised • 9% of Phase 1 NoW Longhole commences acquires • All destressed (Reserve 11.3 Stoping • Convention 100% of convention Moz). commences al destress South Deep al mining, • Current mine = 10 years of Gold Mine including mining @ 80 ktpm VCR, stopped TIFR 40 35 30 25 20 15 10 5 0 F2008 F2009 F2010 F2011 C2011 C2012 C2013 C2014 Increased Mechanisation = Improved Safety South Deep: Finding it's Feet | Nick Holland, Nico Muller and the South Deep Team | Friday, 13 February 2015 10

  11. South Deep Gold Mine 2014 Intervention ● People Strategy • Short term › Rightsizing of workforce through voluntary separation process • Medium term › Recruit South African Team from limited pool of skills • Long term › Grow South African skills pool through bespoke mechanised mining training ● Fleet Availability and Utilisation • Decongest the mine • Cat A equipment reduced from 126 to 75 • Fast-track Mega Workshop on 93-level • Upgrade satellite workshops • Replace key equipment ● Ore handling infrastructure • Fast-tracked additional ore passes and other key infrastructure Costs and Capital Reduced from ~R5 Billion to ~R4 Billion Despite Ground Support South Deep: Finding it's Feet | Nick Holland, Nico Muller and the South Deep Team | Friday, 13 February 2015 11

  12. South Deep Gold Mine Safety Related Ground Support Intervention ● Growing momentum in H1 2014 interrupted in May ● Four-month suspension of production for ground support in 2014 ● Knock-on effects into 2015 ̵ Destress ̵ Long-hole open stopes delayed Acceleration of Medium Term People Strategy ● Medium and long-term people strategy accelerated ̵ Recruiting South African leadership skills ̵ Growing the South African skills pool ● Introduction of new team under Nico Muller ● Australian Team downscaled – key role in skills transfer and training 70% of Production Areas Curtailed For Four Months South Deep: Finding it's Feet | Nick Holland, Nico Muller and the South Deep Team | Friday, 13 February 2015 12

  13. Observations After First 100 Days NICO MULLER Executive Vice President: South Africa Region

  14. South Deep Gold Mine Leadership: Structure Strength and Stability Required South Deep: Finding it's Feet | Nick Holland, Nico Muller and the South Deep Team | Friday, 13 February 2015 14

  15. South Deep Gold Mine Leadership: The People Adriaan De Beer Francois Van Heerden Errol Drake VP South Deep Head of Operations Head of Engineering 09 Jan 2015 09 Jan 2015 02 Feb 2015 Masala Mutangwa Andre Marais Edwin Matlapeng Technical Head Head of Projects Head of Safety & Health Building the Team South Deep: Finding it's Feet | Nick Holland, Nico Muller and the South Deep Team | Friday, 13 February 2015 15

  16. South Deep Gold Mine Leadership: The People (continued) Blessed Mazibuko Bonny Sebola Ulrich Sibilski Head of Finance Head of Sustainable Development Head of Environment 15 Sep 2014 Tumelo Nkisi Jana Strydom Manie Keyser Head of Human Resources Head of Legal & Compliance Head of Mineral Resource 09 Jan 2015 19 Nov 2014 Management Building the Team South Deep: Finding it's Feet | Nick Holland, Nico Muller and the South Deep Team | Friday, 13 February 2015 16

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend