1
DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 CANAAN/PITTSFIELD, MAINE
Keith Donington, P.E.
SIBLEY POND
October 2012
SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 - - PowerPoint PPT Presentation
SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 CANAAN/PITTSFIELD, MAINE Keith Donington, P.E. October 2012 1 Sibley Pond - Bridge Elevation 2 Bridge Open to Traffic November 2011 3 Bridge Highlights General: Design-Build
1
DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 CANAAN/PITTSFIELD, MAINE
Keith Donington, P.E.
October 2012
2
3
– Design-Build Project – Bridge designed and constructed in 15 months – Opened to traffic in November 2011 more than 10 months ahead of the owner set completion date of October 2012 – First design of PCI’s NEXT D (Northeast Extreme Double Tee Beam) with full depth integral deck – NEXT D and NEXT F were new beam sections developed by PCI New England in response to FHWA’s nationwide initiative for Accelerated Bridge Construction (ABC) – NEXT D - 8 inch full depth integral deck slab – NEXT F - 4 inch form deck w/CIP topping – NEXT D selected as faster to erect, less costly, improved durability, and perceived higher technical score for D/B
4
– Highway Bridge – Stream/Pond Crossing
– No. of Spans 10 spans arranged in two 5-span continuous units and a single expansion joint located in the center – Continuity Spans continuous for LL and SDL – Span Length 79’-0” – Overall Length 790’-0” C.L. to C.L. of end abutments – Overall Width 36’-0” curb to curb – No. of Traffic Lanes 2 – Alignment /Skew Tangent /0 skew – Longitudinal Grade ± 1.0% with crown at center of bridge
5
– Designed to AASHTO LRFD Bridge Design Specifications for HL-93 loading for all limit states except for Strength I – LL for Strength I Limit State is MaineDOT Modified Live Load consisting of the standard HL-93 Live Load with 25% increase in the design truck – Bridge designed to 100-year design life per owner’s project requirements
6
7
Subsurface Profile
8
Organic Silt Silty Sand / Silty Clay Silty/Gravely Sand Fine Sand Bedrock
north abutment were driven from the old road during the first winter
driven by leapfrogging the pile driving crane from pier to pier, supported by temporary decking and temporary intermediate steel pile bents
9
Pile Driving Operations
Elevation of several pier bents Fixed pier bent
10
11
12
13
NEXT D Beam in casting bed
NEXT D Beam with steel studs
14
NEXT D Beam lifted from casting bed Completed NEXT D Beams
15
a custom gantry crane
support beam system
transporter vehicle parked on the
beams inserted
new piers on Hillman Rollers.
crane pick
shift
span
Beam Erection Operations
16
17
18
strand projections allowed to clear legs of gantry crane
continuity over the piers, mechanical couplers were detailed to field splice the splice bars between adjacent beams
precaster to align the deck rebars from adjacent beams to tight tolerances
19
Couplers for (-) Moment continuity at intermediate diaphragms
a special detail was developed for the bottom reinforcement using a steel end plate with ASTM A706 weldable rebar
assemblies were cast into ends
the gantry rail support system, hooked rebars were field welded to the steel plates
20
Couplers for (+) Moment continuity at intermediate diaphragms
– NEXT D beams were selected by D/B team for best technical score as well as cost considerations – NEXT D has integral deck which is both precast and prestressed – Beams used a HP performance/self-consolidating concrete mix with 5.5 gals/CY calcium nitrite corrosion inhibitor (DCI) – 8,000 psi was specified by design but 10,000 psi concrete was consistently achieved by the precaster – CIP concrete construction was limited to only the curbs, longitudinal closure joints, and pier continuity diaphragms – HPC was also specified for all field-placed concrete along with 5.5 gals/CY of DCI – MMFX rebar specified in exposed bridge curbs and rail transition barriers – Deck protection: HP machine hot applied deck waterproofing with 3 inch minimum asphalt
– Only one expansion joint in 790 ft, located at high point, with semi-integral abutments at ends
– Concrete filled steel pipe piles are protected with a shop applied fusion bonded epoxy coating system, extending from the top of the pile to 10 feet (3 meters) below the mud line
21
– Maine Department of Transportation, Augusta, ME
– The Lane Construction Corp., Bangor, ME
– Parsons Brinckerhoff, Inc., Manchester, NH/Boston MA
22
23