SHAILESH MODI, ASST. MANAGER, ERDA (INDIA) ONSITE ACCURACY - - PowerPoint PPT Presentation

shailesh modi asst manager erda india onsite accuracy
SMART_READER_LITE
LIVE PREVIEW

SHAILESH MODI, ASST. MANAGER, ERDA (INDIA) ONSITE ACCURACY - - PowerPoint PPT Presentation

SHAILESH MODI, ASST. MANAGER, ERDA (INDIA) ONSITE ACCURACY VERFICATION OF ENERGY METER WITHOUT DISCONNECTING CTs AND PTs ABSTRACT ONSITE CALIBRATION OF ENERGY METER WITHOUT REMOVAL OF CT AND PT CONNECTIONS. REGULATION BY


slide-1
SLIDE 1

SHAILESH MODI,

  • ASST. MANAGER,

ERDA (INDIA)

slide-2
SLIDE 2

ONSITE ACCURACY VERFICATION OF ENERGY METER WITHOUT DISCONNECTING CTs AND PTs

slide-3
SLIDE 3

ABSTRACT

ONSITE CALIBRATION OF ENERGY METER WITHOUT REMOVAL OF CT AND PT CONNECTIONS. REGULATION BY CENTRAL ELECTRICITY AUTHORITY

slide-4
SLIDE 4

INTRODUCTION

Energy meters: One of the important element of an electrical system Energy Meter used in: Every electrical installation From small houses to huge industries. All exchange points Transmission, distribution and supply network Generation and power stations Distribution transformers It acts as a link between consumer and utility.

slide-5
SLIDE 5

Need of calibration

It relates to the revenue of the utility The accuracy shall not exceed the permissible limits (as per standard) Required to have periodic calibration/accuracy check. If accuracy goes beyond the limits, replaced by calibrated meter having accuracy within prescribed limits.

slide-6
SLIDE 6

Methods for calibration

Energy Meter: Onsite Meter is calibrated on actual load. Reference standard meter is connected in line with the test meter Accuracy is checked.

slide-7
SLIDE 7

Methods for calibration

Energy Meter: Using phantom load: Meter is removed from the site Accuracy is checked using phantom load generator. The voltage of the test meter is connected in parallel The current circuit of test meter and reference meter is connected in series. Check the accuracy of meter from lower load to maximum load at required power factor as per the requirement of standard.

slide-8
SLIDE 8

Methods for calibration

Current Transformer (CT): The primary of the test CT and standard CT are connected through a high current source Secondary of both the CT’s are compared and accuracy obtained.

slide-9
SLIDE 9

Methods for calibration

Potential Transformer(PT): The primary of the test PT and standard PT are connected to a voltage source Secondary of both the PT’s are compared and accuracy obtained.

slide-10
SLIDE 10

DISADVANTAGES

Energy meter to be disconnected from site for calibration. CT’s and PT’s are required to be disconnected. All three are calibrated separately Effect of lead from CT and PT to meter is accounted against rated burden After measurement of accuracy of CT, PT and energy meter separately, one need to compute the overall compensation factor.

slide-11
SLIDE 11

OBJECTIVE

Gazette notification no. 502/70/CEA/ DP&D

Calibration & periodical testing of meters carried out at least once in five years Consumer Meter: Meter above 650Volts should cover the entire metering system including CT and PT Energy accounting and audit meters: The testing/ calibration must be carried out without removing CT’s and PT’s

slide-12
SLIDE 12

OBJECTIVE

Calibration/testing is to be done for the whole system which includes Energy Meter, CT and PT in actual loading condition. The main objective is to carry out the calibration of the Energy Meter with CT and PT with the actual burden connected to CT & PT.

slide-13
SLIDE 13

METHODOLOGY

LABORATORY EXPERIMENT The details of reference instruments used for calibration is: Energy Meter: 63.5V, 1A Class : 0.2 PT: 11kV/63.5V Class : 1.0 CT: 200/5A Class : 0.2

slide-14
SLIDE 14

METHODOLOGY

LABORATORY EXPERIMENT The details of Instrument under test used for calibration is: Energy Meter: 63.5V, 1A Class :0.5 PT: 11kV/63.5V Class :3.0 CT: 200/1A Class :0.5

slide-15
SLIDE 15

METHODOLOGY

The PT’s (standard as well as object) were energized with high voltage source. CT’s were energized with high current source. Secondary of the test CT and PT were connected to the test meter Secondary of standard CT and PT were connected to the reference standard meter. Phase shifter is connected in the set up to change the power factor, when required.

slide-16
SLIDE 16

METHODOLOGY

Then both the energy meters are run for certain duration The % error of the test meter was taken. The pulses coming out from the test meter is sensed by the sensor of reference meter The % error of the test meter was displayed on standard meter.

slide-17
SLIDE 17

TEST CIRCUIT FOR CALIBRATION OF ENERGY METER WITHOUT REMOVAL OF CT, PT CONNECTION AT RATED CONDITIONS

slide-18
SLIDE 18

RESULTS:

Calibration results separately for test objects: Energy Meter: Sr. No. Voltage Current Power Factor %error 1 63.5V 1A UPF 0.06

slide-19
SLIDE 19

RESULTS

Calibration results separately for test objects: Current Transformer: Rating: 200/1A Sr. No. % of Current Ratio Error (%) Phase error 1 100.5% 0.18 10.66min

slide-20
SLIDE 20

RESULTS

Calibration results separately for test objects: Potential Transformer: Rating: 11kV/63.5V Sr. No. % of Voltage Ratio Error (%) Phase error 1 101.2% 1.053 1.99min

slide-21
SLIDE 21

RESULTS

Combine result for the setup (Energy Meter, CT, PT): Sr. No. Voltage Current Power Factor %error 1 63.5V 1A UPF 1.28

slide-22
SLIDE 22

CONCLUSION

Our present method satisfies Gazette Notification (de-energised condition) The problem of the calibration of energy meter with CT and PT online (or on actual load) is still an issue which is not yet resolved. No standard defines the procedure for the calibration of the same.

slide-23
SLIDE 23

CONCLUSION

In this paper the problems related with the aforesaid consideration were presented and discussed by mean of several experimental tests. Presently we have different methods for calibration of energy meter. But method suggested in this paper will be more reliable as compared to the earlier methods of

  • nsite calibration of individual components.
slide-24
SLIDE 24

THANK YOU