SLIDE 1 SHAILESH MODI,
ERDA (INDIA)
SLIDE 2
ONSITE ACCURACY VERFICATION OF ENERGY METER WITHOUT DISCONNECTING CTs AND PTs
SLIDE 3
ABSTRACT
ONSITE CALIBRATION OF ENERGY METER WITHOUT REMOVAL OF CT AND PT CONNECTIONS. REGULATION BY CENTRAL ELECTRICITY AUTHORITY
SLIDE 4
INTRODUCTION
Energy meters: One of the important element of an electrical system Energy Meter used in: Every electrical installation From small houses to huge industries. All exchange points Transmission, distribution and supply network Generation and power stations Distribution transformers It acts as a link between consumer and utility.
SLIDE 5
Need of calibration
It relates to the revenue of the utility The accuracy shall not exceed the permissible limits (as per standard) Required to have periodic calibration/accuracy check. If accuracy goes beyond the limits, replaced by calibrated meter having accuracy within prescribed limits.
SLIDE 6
Methods for calibration
Energy Meter: Onsite Meter is calibrated on actual load. Reference standard meter is connected in line with the test meter Accuracy is checked.
SLIDE 7
Methods for calibration
Energy Meter: Using phantom load: Meter is removed from the site Accuracy is checked using phantom load generator. The voltage of the test meter is connected in parallel The current circuit of test meter and reference meter is connected in series. Check the accuracy of meter from lower load to maximum load at required power factor as per the requirement of standard.
SLIDE 8
Methods for calibration
Current Transformer (CT): The primary of the test CT and standard CT are connected through a high current source Secondary of both the CT’s are compared and accuracy obtained.
SLIDE 9
Methods for calibration
Potential Transformer(PT): The primary of the test PT and standard PT are connected to a voltage source Secondary of both the PT’s are compared and accuracy obtained.
SLIDE 10
DISADVANTAGES
Energy meter to be disconnected from site for calibration. CT’s and PT’s are required to be disconnected. All three are calibrated separately Effect of lead from CT and PT to meter is accounted against rated burden After measurement of accuracy of CT, PT and energy meter separately, one need to compute the overall compensation factor.
SLIDE 11
OBJECTIVE
Gazette notification no. 502/70/CEA/ DP&D
Calibration & periodical testing of meters carried out at least once in five years Consumer Meter: Meter above 650Volts should cover the entire metering system including CT and PT Energy accounting and audit meters: The testing/ calibration must be carried out without removing CT’s and PT’s
SLIDE 12
OBJECTIVE
Calibration/testing is to be done for the whole system which includes Energy Meter, CT and PT in actual loading condition. The main objective is to carry out the calibration of the Energy Meter with CT and PT with the actual burden connected to CT & PT.
SLIDE 13
METHODOLOGY
LABORATORY EXPERIMENT The details of reference instruments used for calibration is: Energy Meter: 63.5V, 1A Class : 0.2 PT: 11kV/63.5V Class : 1.0 CT: 200/5A Class : 0.2
SLIDE 14
METHODOLOGY
LABORATORY EXPERIMENT The details of Instrument under test used for calibration is: Energy Meter: 63.5V, 1A Class :0.5 PT: 11kV/63.5V Class :3.0 CT: 200/1A Class :0.5
SLIDE 15
METHODOLOGY
The PT’s (standard as well as object) were energized with high voltage source. CT’s were energized with high current source. Secondary of the test CT and PT were connected to the test meter Secondary of standard CT and PT were connected to the reference standard meter. Phase shifter is connected in the set up to change the power factor, when required.
SLIDE 16
METHODOLOGY
Then both the energy meters are run for certain duration The % error of the test meter was taken. The pulses coming out from the test meter is sensed by the sensor of reference meter The % error of the test meter was displayed on standard meter.
SLIDE 17 TEST CIRCUIT FOR CALIBRATION OF ENERGY METER WITHOUT REMOVAL OF CT, PT CONNECTION AT RATED CONDITIONS
SLIDE 18
RESULTS:
Calibration results separately for test objects: Energy Meter: Sr. No. Voltage Current Power Factor %error 1 63.5V 1A UPF 0.06
SLIDE 19
RESULTS
Calibration results separately for test objects: Current Transformer: Rating: 200/1A Sr. No. % of Current Ratio Error (%) Phase error 1 100.5% 0.18 10.66min
SLIDE 20
RESULTS
Calibration results separately for test objects: Potential Transformer: Rating: 11kV/63.5V Sr. No. % of Voltage Ratio Error (%) Phase error 1 101.2% 1.053 1.99min
SLIDE 21
RESULTS
Combine result for the setup (Energy Meter, CT, PT): Sr. No. Voltage Current Power Factor %error 1 63.5V 1A UPF 1.28
SLIDE 22
CONCLUSION
Our present method satisfies Gazette Notification (de-energised condition) The problem of the calibration of energy meter with CT and PT online (or on actual load) is still an issue which is not yet resolved. No standard defines the procedure for the calibration of the same.
SLIDE 23 CONCLUSION
In this paper the problems related with the aforesaid consideration were presented and discussed by mean of several experimental tests. Presently we have different methods for calibration of energy meter. But method suggested in this paper will be more reliable as compared to the earlier methods of
- nsite calibration of individual components.
SLIDE 24
THANK YOU