Seymour River Rock Slide Mitigation Proje ject To restore migration - - PowerPoint PPT Presentation

seymour river rock slide mitigation proje ject
SMART_READER_LITE
LIVE PREVIEW

Seymour River Rock Slide Mitigation Proje ject To restore migration - - PowerPoint PPT Presentation

Seymour River Rock Slide Mitigation Proje ject To restore migration conditions for all species in the Seymour River that existed before the 2014 rockslide, in a safe and sustainable manner. Outline Background Project summary


slide-1
SLIDE 1

Seymour River Rock Slide Mitigation Proje ject

“To restore migration conditions for all species in the Seymour River that existed before the 2014 rockslide, in a safe and sustainable manner.”

slide-2
SLIDE 2

Outline

  • Background
  • Project summary
  • Fish fence and Trap and

truck

  • Progress to date
  • Looking ahead
slide-3
SLIDE 3

Background

  • Slide on December 7,

2014

  • 80,000 cubic meters of

debris

  • Blocked fish migration
  • Raised water levels

upstream by 10 meters

slide-4
SLIDE 4

Project Summary

  • Tagging program 2015 – no

fish migration.

  • Trap and truck 2015 -

current

  • 2015 - 3,000 volunteer

hours

  • Unsustainable
slide-5
SLIDE 5

Project Summary

  • 2015 Fundraised for

engineering report.

  • Roundtable partners

selected mitigation

  • ption.
  • Fundraising for project
  • Rock slide opening

ceremony – August 24, 2016

slide-6
SLIDE 6

Trap and Truck

Why do we need to move fish?

  • More abundant and

productive habitat above the slide.

  • Very little spawning grounds,

cover and off channel habitat below.

  • Below will not sustain wild

coho and steelhead populations.

Above Above Below

slide-7
SLIDE 7

Fish Fence

Fence construction:

  • 36 aluminum poles/panel
  • 100 ft. long bladder
  • 20 panels
  • 100 feet across
  • 15 ft. long poles
  • 25 anchors, 3 ft. deep
  • 300 sand bags
  • Hundreds of volunteer

hours

Installing anchors Building the panels Installing the fence

slide-8
SLIDE 8

Fish Fence

  • Fence fishing as of

August 6, 2016

  • Fence maintenance and

daily operations: ➢Squamish Nation ➢Tsleil-Waututh Nation ➢Seymour Salmonid Society

slide-9
SLIDE 9

Fish Fence and Trap and Truck

From fence - 2016: Fish moved above slide:

  • Summer steelhead:
  • Coho: 330

Total: 335 From fence - 2017: Fish moved above slide:

  • Summer steelhead: 36
  • Coho: 128

Total: 304

The fence made a barrier in late summer, at very low flows. Creating ideal conditions to seine the pool directly downstream. The results of 6 weeks of seining from August 30 to November 6:

Trap and Truck Seining Program 2017 Species Broodstock Release Total pink salmon 334 334 summer steelhead 25 29 54 coho salmon 276 1,777 2,053 chum salmon 67 67 Total 2,508

slide-10
SLIDE 10

Monitoring

  • Instream Fisheries Research
  • Adult program

➢Gastric tags ➢Tagged and released at fence ➢No adults detected above slide in 2017

  • Juvenile program

➢Surgically implanted ➢Coho smolts at hatchery ➢87% survival downstream of slide in 2017

slide-11
SLIDE 11

Progress in 2016

  • Rock breaking at the toe
  • f the slide
  • 5 weeks of drilling
  • 5 rock breaking events

Before After

slide-12
SLIDE 12

Before After

slide-13
SLIDE 13

Progress in 2017

  • Rock breaking through

the mid portion of slide

  • 12 weeks of drilling
  • 7 rock breaking events
slide-14
SLIDE 14

Before and after photos from 2017

slide-15
SLIDE 15

June 2015 September 2017 Prior to rock breaking work After year 2 of rock breaking work

slide-16
SLIDE 16

Before and after photos from November 2017 rain event

slide-17
SLIDE 17

Looking ahead

  • Funds raised for 12 weeks
  • f drilling and blasting in

summer of 2018.

  • Progress reassessment

after Spring freshet.

  • Adult monitoring for at

least 5 years.

slide-18
SLIDE 18

Thank you for your support!