SEWER IMPROVEMENTS Presentation to the Central Waterfront Advisory - - PowerPoint PPT Presentation

SFPUC SSIP Project: THE EMBARCADERO/DRUMM & JACKSON STREETS SEWER IMPROVEMENTS Presentation to the Central Waterfront Advisory Group May 1, 2017 SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean. PROJECT OVERVIEW PROJECT PURPOSE:


slide-1
SLIDE 1

SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

SFPUC SSIP Project: THE EMBARCADERO/DRUMM & JACKSON STREETS SEWER IMPROVEMENTS

Presentation to the Central Waterfront Advisory Group

May 1, 2017

slide-2
SLIDE 2

SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

PROJECT OVERVIEW

2

Washington Street Drumm Street

PROJECT PURPOSE:

  • Rehabilitate aging infrastructure
  • Prevent service interruption
slide-3
SLIDE 3

SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean. 7

EXISTING FORCE MAIN: CORROSION

slide-4
SLIDE 4

SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean. 8

EXISTING SEWER BOXES ON DRUMM/JACKSON

slide-5
SLIDE 5

SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

PROJECT OVERVIEW

9

Force Main Rehabilitation Drumm and Jackson Sewer Boxes Rehabilitation

slide-6
SLIDE 6

SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

CONSTRUCTION APPROACH

sfwater.org/ssip ssip@sfwater.org sfwater.org

slide-7
SLIDE 7

SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

THE EMBARCADERO

THE EMBARCADERO Pit #1 Pit #2 Pit #3 Valve Vault

slide-8
SLIDE 8

SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

THE EMBARCADERO (Area 1) : Work Hours

THE EMBARCADERO Allowable Work Hours: NB Lanes: 1 lane of traffic, M-F, 9:00am-4:30pm All Lanes of traffic will be open outside of the above work hours. = Contractor Work Space = Open Cut Excavation = Space needed in SWL 351

slide-9
SLIDE 9

SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

THE EMBARCADERO (Area 2) : Work Hours

THE EMBARCADERO Allowable Work Hours: SB Lanes: 1 lane of traffic, M-F, 8:00am-3:30pm All Lanes of traffic will be open outside of the above work hours. = Contractor Work Space = Open Cut Excavation = Space needed in SWL 351

slide-10
SLIDE 10

SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

THE EMBARCADERO Allowable Work Hours: SB Lanes: 2 lanes of traffic, M-F, 8:00am-5:00pm All Lanes of traffic will be open outside of the above work hours.

THE EMBARCADERO (Area 2) : Work Hours

= Contractor Work Space = Open Cut Excavation = Space needed in SWL 351

slide-11
SLIDE 11

SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

THE EMBARCADERO Allowable Work Hours: Slipline Work: 9:00pm – 5:00am NB Lanes: 1 lane of traffic SB Lanes: 1 lane of traffic

THE EMBARCADERO (Area 3) : Work Hours

= Contractor Work Space = Open Cut Excavation = Space needed in SWL 351

slide-12
SLIDE 12

SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

THE EMBARCADERO: Work Hours

THE EMBARCADERO Allowable Work Hours : NB Lanes: 1 lane of traffic, M-F, 9:00am-4:30pm SB Lanes: 1 lane of traffic, M-F, 8:00am-3:30pm SB Lanes: 2 lanes of traffic, M-F, 8:00am-5:00pm All Lanes of traffic will be open outside of the above work hours.

slide-13
SLIDE 13

SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

TRAFFIC MITIGATION: Alternative Route

17

slide-14
SLIDE 14

SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

COMMUNICATIONS

sfwater.org/ssip ssip@sfwater.org sfwater.org

slide-15
SLIDE 15

SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

COMMUNICATIONS

19

http://www.sfwater.org/edjsewers CONTACT:

  • ssip@sfwater.org
  • 415-554-3289
slide-16
SLIDE 16

SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

Questions?

sfwater.org/edjsewers ssip@sfwater.org sfwater.org