SFPUC SSIP Project: THE EMBARCADERO/DRUMM & JACKSON STREETS SEWER IMPROVEMENTS Presentation to the Central Waterfront Advisory Group May 1, 2017 SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean. PROJECT OVERVIEW PROJECT PURPOSE:


  1. SFPUC SSIP Project: THE EMBARCADERO/DRUMM & JACKSON STREETS SEWER IMPROVEMENTS Presentation to the Central Waterfront Advisory Group May 1, 2017 SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

  2. PROJECT OVERVIEW PROJECT PURPOSE:  Rehabilitate aging infrastructure Washington Street  Prevent service interruption Drumm Street SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean. 2

  3. EXISTING FORCE MAIN: CORROSION SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean. 7

  4. EXISTING SEWER BOXES ON DRUMM/JACKSON SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean. 8

  5. PROJECT OVERVIEW Force Main Rehabilitation Drumm and Jackson Sewer Boxes Rehabilitation SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean. 9

  6. CONSTRUCTION APPROACH sfwater.org/ssip ssip@sfwater.org sfwater.org SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

  7. THE EMBARCADERO Pit #1 Pit #2 THE EMBARCADERO Valve Vault Pit #3 SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

  8. THE EMBARCADERO (Area 1) : Work Hours THE EMBARCADERO Allowable Work Hours: NB Lanes: 1 lane of traffic, M-F, 9:00am-4:30pm = Open Cut Excavation All Lanes of traffic will be open outside of the above work hours. = Space needed in SWL 351 = Contractor Work Space SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

  9. THE EMBARCADERO (Area 2) : Work Hours THE EMBARCADERO Allowable Work Hours: SB Lanes: 1 lane of traffic, M-F, 8:00am-3:30pm = Open Cut Excavation All Lanes of traffic will be open outside of the above work hours. = Space needed in SWL 351 = Contractor Work Space SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

  10. THE EMBARCADERO (Area 2) : Work Hours THE EMBARCADERO Allowable Work Hours: SB Lanes: 2 lanes of traffic, M-F, 8:00am-5:00pm = Open Cut Excavation All Lanes of traffic will be open outside of the above work hours. = Space needed in SWL 351 = Contractor Work Space SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

  11. THE EMBARCADERO (Area 3) : Work Hours THE EMBARCADERO Allowable Work Hours: Slipline Work: 9:00pm – 5:00am NB Lanes: 1 lane of traffic = Open Cut Excavation SB Lanes: 1 lane of traffic = Space needed in SWL 351 = Contractor Work Space SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

  12. THE EMBARCADERO: Work Hours THE EMBARCADERO Allowable Work Hours : NB Lanes: 1 lane of traffic, M-F, 9:00am-4:30pm SB Lanes: 1 lane of traffic, M-F, 8:00am-3:30pm SB Lanes: 2 lanes of traffic, M-F, 8:00am-5:00pm SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean. All Lanes of traffic will be open outside of the above work hours.

  13. TRAFFIC MITIGATION: Alternative Route SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean. 17

  14. COMMUNICATIONS sfwater.org/ssip ssip@sfwater.org sfwater.org SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

  15. COMMUNICATIONS http://www.sfwater.org/edjsewers CONTACT:  ssip@sfwater.org  415-554-3289 SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean. 19

  16. Questions? sfwater.org/edjsewers ssip@sfwater.org sfwater.org SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean. 20

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.