session 1 a window to your dpv future
play

Session 1: A Window to Your DPV Future Hawaii Experience Grid - PowerPoint PPT Presentation

Session 1: A Window to Your DPV Future Hawaii Experience Grid System Technologies Advanced Research Team Marc M. Matsuura, PE Leon R. Roose, Esq. Sr. Smart Grid Program Manager, Grid START Principal & Chief Technologist, Grid START Hawaii


  1. Session 1: A Window to Your DPV Future Hawaii Experience Grid System Technologies Advanced Research Team Marc M. Matsuura, PE Leon R. Roose, Esq. Sr. Smart Grid Program Manager, Grid START Principal & Chief Technologist, Grid START Hawaii Natural Energy Institute School of Ocean & Earth Science & Technology University of Hawaii at Manoa 1680 East-West Road, POST 109 Honolulu, Hawaii 96822 Asia Edge Power Sector Learning Series A P RACTITIONER ' S G UIDE TO I MPLEMENTING S OLAR R OOFTOP P ROGRAMS AND N AVIGATING N ET -M ETERING P OLICIES July 9, 2020 9:00AM ICT (via Webinar) Session 1 - Hawaii DPV Experience | Asia EDGE Power Sector Learning Series | 1

  2. Hawaii’s isolation has long posed a serious Challenge In 2008, 8, near arly ly 90% of Hawaii’s 100% % of the energy gy was met crude de oil for the using g foss ssil il fuels ls State is importe ted Threa eat to Hawaii’s: Secu curity ty • Env nvironme nment • Econ onomy omy • Hawaii ranks #1 in U.S. electric energy costs: 47.1 cents/kWh Molokai 45.9 cents/kWh Lanai 41.9 cents/kWh Hawaii 37.8 cents/kWh Maui 35.5 cents/kWh Oahu • 2 (Avg. residential rates for 2014) 11 - 12 cents/kWh U.S. avg. Session 1 - Hawaii DPV Experience | Asia EDGE Power Sector Learning Series | 2

  3. Hawaii’s Progressive Clean Energy Policy Leadership Hawaii Clean Energy Initiative (HCEI) The State of Hawaii, US DOE, and local utility launched HCEI in January 2008 to transform Hawaii to a 70% clean energy economy by 2030: • Increasing Hawaii’s economic and energy security • Fostering and demonstrating Hawaii’s innovation • Developing Hawaii’s workforce of the future • Becoming a clean energy model for the U.S. and the world Strong Hawaii Policies Highest RPS Target in the United States 100% by 2045 (2015 - 15%; 2020 - 30%, 2030 – 40%, 2040 – 70%) Key implementing policies: • Tax incentives • Net metering • Feed in tariffs • Decoupling Session 1 - Hawaii DPV Experience | Asia EDGE Power Sector Learning Series | 3

  4. Progress Toward A Clean Energy Future Hawaiian Electric Companies Hawaii RPS Goals 2015 - 15% 2020 - 30% 2030 - 40% 2040 - 70% 2045 - 100% Loss of Geothermal Production (May 2018) Source: Hawaiian Electric Sustainability Report 2019-2020 Session 1 - Hawaii DPV Experience | Asia EDGE Power Sector Learning Series | 4

  5. Installed PV Capacity - HECO Companies (2005 to 2019) ~ 60% of total RE production ½ System Peak Load Session 1 - Hawaii DPV Experience | Asia EDGE Power Sector Learning Series | 5

  6. Hawaii Electric Systems – 4 Electric Utilities; 6 Separate Grids; % Renewable Energy Kaua ʻ i Island Utility Cooperative (2019 Yr.-end) Maui Electric (2019 Yr.-end) System Peak: 78 MW Maui System Peak: 206 MW Maui (Approved) 100 MW PV* / 7 MW Biomass / 9 MW Hydro 119 MW PV* / 72 MW Wind *60 MW PV + 240 MWh BESS Installed PV: 128% of Sys. Peak Installed PV & Wind: 1 MW PV 95% of Sys. Peak 0.735 MW PV Lana’i System Peak: 5.1 MW 3.8 MW PV (75% of Sys. Peak) Kaua’i Oʻahu Moloka’i System Peak: 5.6 MW 100% Moloka’i (Approved) 80% of state population 2.3 MW PV* (41% of Sys. Peak) *2.3 MW PV + 15 MWh BESS 60% Molokaʻi Hawaiian Electric (2019 Yr.-end) Maui System Peak: 1,216 MW 77% 674 MW PV* / 99 MW Wind* / Hawaii Electric Light (2019 Yr.-end) Lanaʻi Hawaiʻi 69 MW WTE / 168 MW Biofuel System Peak: 191 MW Installed PV & Wind: 103 MW PV* / 31 MW Wind / 64% of Sys. Peak 38 MW Geothermal* / 17 MW Hydro 67% Installed PV & Wind: *24 MW Wind (in construction) 70% of Sys. Peak 5 MW PV (Approved) 3.5 MW PV (Approved) *1 MW PV (in construction) 12.5 MW PV + 50 MWh BESS (Approved) Renewable Energy Peak 2 x 30 MW PV + 120 MWh BESS (Approved) 52 MW PV + 208 MWh BESS (Approved) Daily Production in 2019 Geothermal Plant not in operation due to 39 MW PV + 156 MWh BESS (Approved) (e.g. occurred on 11/28/19) volcanic eruption 36 MW PV + 144 MWh BESS (Approved) Session 1 - Hawaii DPV Experience | Asia EDGE Power Sector Learning Series | 6

  7. How Much DG PV can we Connect on a Feeder? A Lot! • Many lessons already learned – leverage it • PV inverters have matured • Grid Codes are key • Reverse Power Flow is the new normal Embrace it! Session 1 - Hawaii DPV Experience | Asia EDGE Power Sector Learning Series | 7

  8. Evolution of Hosting Capacity “Limits” Pre- 2013, in the early days of rooftop PV …. • 15% of circuit Peak Load – Historical utility “Rule -of- Thumb” for synchronous generation • In the past, utilities only tracked circuit peaks for planning *DML = Net min load (metered) + 75% of installed PV capacity Session 1 - Hawaii DPV Experience | Asia EDGE Power Sector Learning Series | 8

  9. Circuit Hosting “Limits” Began Quickly Rising In 2012- 13, a series of “representative studies” were conducted using detailed distribution circuit models …. • 50%, 75%, 100% of circuit Daily Minimum Load (DML) – Utility established a new feeder penetration metric: % of DML – Study results gave the utility confidence to raise (conservatively) their PV hosting limits system wide across all circuits without conducting expensive/lengthy project specific interconnection requirements studies • 120% of DML – Dynamics modeling and lab tests revealed higher than acceptable transient over voltages (TOV) may occur when PV penetration exceeds 120% of DML – A TOV solution with inverter manufacturers was sought Session 1 - Hawaii DPV Experience | Asia EDGE Power Sector Learning Series | 9

  10. PV Hosting Limit Doubled with TOV Solved In 2014, hardware-in-the-loop (HIL) lab testing of inverters determined the TOV concern was solvable …. • 250% of DML – But, inverters must disconnect from the grid within 1-cycle (16 ms) if it detects that its terminal voltage has reached 120% of its nominal voltage. – TOV inverter performance requirement added to Grid Code Session 1 - Hawaii DPV Experience | Asia EDGE Power Sector Learning Series | 10

  11. Beyond the 250% DML Hosting Limit In 2015, individual circuit by circuit modeling of the distribution grid was performed to determine feeder specific Hosting Capacity on the Hawaii power grids …. • Individual Circuit Hosting Capacity Limits – Based on steady-state power flows (equipment thermal and line voltage limits) and flicker limits. – Emergency circuit configurations are assessed. – Substation transformer load tap changer settings are reviewed. Session 1 - Hawaii DPV Experience | Asia EDGE Power Sector Learning Series | 11

  12. Circuit Level PV Hosting Capacity • Circuit level analysis is important for distributed resource integration • Proper Grid Codes are essential to achieve high penetration of distributed resources • Advanced inverter capability is critical • Distributed PV circuit penetration several times served load may be achieved Session 1 - Hawaii DPV Experience | Asia EDGE Power Sector Learning Series | 12

  13. Maui Distributed PV Circuit Penetrations Maui Electric (2019 Yr.-end) Maui System Peak: 206 MW 119 MW PV / 72 MW Wind Installed PV & Wind: 95% of Sys. Peak DG PV capacity = 58% peak load 19.7% Energy Wind capacity = 35% peak load 21% Energy Reverse power flow exists on the majority of circuits today PV penetration on some circuits exceed 300% DML Session 1 - Hawaii DPV Experience | Asia EDGE Power Sector Learning Series | 13

  14. Mahalo! For more information, contact: (Thank you) Grid System Technologies Advanced Research Team Leon R. Roose , Esq. Principal & Chief Technologist Grid START Hawaii Natural Energy Institute School of Ocean & Earth Science & Technology University of Hawaii at Manoa 1680 East-West Road, POST 109 Honolulu, Hawaii 96822 Office: (808) 956-2331 Mobile: (808) 554-9891 E-mail: lroose@hawaii.edu Website: www.hnei.hawaii.edu Session 1 - Hawaii DPV Experience | Asia EDGE Power Sector Learning Series | 14

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend