Scheduling Network and Anaylsis Lesson 4 FE 302 Introduction - - PowerPoint PPT Presentation

scheduling network and anaylsis
SMART_READER_LITE
LIVE PREVIEW

Scheduling Network and Anaylsis Lesson 4 FE 302 Introduction - - PowerPoint PPT Presentation

Scheduling Network and Anaylsis Lesson 4 FE 302 Introduction Terminal Learning Objectives Given a scenario, create a detailed integrated master schedule. Enabling Learning Objectives Build a construction schedule using the Critical


slide-1
SLIDE 1

Lesson 4 FE 302

Scheduling Network and Anaylsis

slide-2
SLIDE 2

Introduction

Terminal Learning Objectives

  • Given a scenario, create a detailed integrated master schedule.

Enabling Learning Objectives

  • Build a construction schedule using the Critical Path Method

(CPM).

  • Analyze a baseline construction schedule for reasonableness.
  • Determine how changed conditions can affect the overall

construction schedule

slide-3
SLIDE 3

Schedules

 Policy: Fixed price contract, over SAT, with a 60-

day or more duration

 Within a time period required by KO, the  KTR must submit a practicable schedule for

approval to the KO

 Reasonable = length of tasks  Feasible = Order of tasks  Obtainable = Total duration  Dates for starting and completing salient features of

work (acquiring materials, plant and equipment)

 Progress chart of suitable scale to:  Indicate % of work scheduled for completion  By any given date during the contract

slide-4
SLIDE 4

Schedules

 Purpose

 Provides GOV with tool to measure progress  Remedies available if KTR falls behind schedule

 Case Law supports that the approved schedule

becomes part of the written record

 Question: What if a contractor submits a schedule

with early completion?

slide-5
SLIDE 5

 Two Types –

 Bar Chart UFGS 01 32 01.00  Critical Path Method (CPM) or Network Analysis

Schedule NAS) UFGS 01 32 17.00

 Factors to Consider

 Complexity of Project  Criticality of Completion  Coordination with Other Contracts  Contractor’s Expertise  Cost Benefit Ratio of Requiring Detailed Schedule

Schedules Continued…

slide-6
SLIDE 6

 Advantages:

 Simple to use  Inexpensive  Easy to understand (Less complex projects)  Able to show limited task interdependency

STR EXCAV CONCRETE ROUGH CARP FINISH CARP MECHANICAL ELECTRICAL INSTRUMENT 100 - 90 - 80 - 70 - 60 - 50 - 40 - 30 - 20 - 10 - 0 - JAN FEB MAR APR MAY $ ACCUM ACTIVITY %

  • KT AMT

LEGEND: BARS: TARGET ACTUAL ‘S’ CURVE: TARGET ACTUAL

0 70 80 100 0 25 100 0 25 100 0 100 0 20 40 100 0 40 80 100 0 44 100

Bar Chart

slide-7
SLIDE 7

Critical Path Method (CPM)

  • Used on complex projects, where the relationship and

interdependency of the individual construction activities.

  • Every CPM schedule will have at least one path

through the network, which controls the overall project duration.

slide-8
SLIDE 8
  • This path represents the route of longest combined

duration through the diagram.

  • The route is referred to as the "critical path," since any

delay in a construction activity on the path will result in an increase of the project's overall duration.

  • For those activities not on the critical path, there exists

some amount of flexibility as to when each one can start or finish without affecting the overall project duration. This flexibility is known as “float”, and can be calculated for each activity.

Critical Path Method (CPM)

slide-9
SLIDE 9

Principle One: Activities shown in boxes (node)

5-17

Critical Path Method (CPM)

slide-10
SLIDE 10

Principle Two: All future activity depends on completion of all preceding activities

5-17

Critical Path Method (CPM)

slide-11
SLIDE 11

Principle three: All activities begin and end at a desireable point in time

1040 3 10 20 13 23 Construct Driveway 2040 1 19 22 20 23 Finish Electrical 2030 2 17 20 19 22 Paint Interior 2040 3 15 15 18 18 Install Roof 2010 2 15 18 17 20 Rough Electrical 1010 7 1 1 8 8 Deliver Materials 1000 1 1 1 Mobilize 1020 6 1 2 7 8 Excavate and Form Footings 1030 2 8 8 10 10 Pour Footings 2000 5 10 10 15 15 Rough Framing 2020 1 15 19 16 20 Install Door and Window 2050 3 18 18 21 21 Install Siding 2060 2 21 21 23 23 Paint Exterior 3000 1 23 23 24 24 Cleanup

Critical Path Method (CPM)

slide-12
SLIDE 12

CPM Network Calculations

  • CPM provides the ability to determine:

– Earliest date of project completion; – Latest date of project completion if there are no changes; – Impact on the project completion date of delaying a specific activity; – Critical activities for completing the project on or before the completion date;

slide-13
SLIDE 13

CPM Network Calculations

– Process:

  • Perform a Forward Pass
  • Perform a Backward Pass
  • Calculate Total Float for each activity
  • Calculate Free Float
  • Identify the Critical Path
slide-14
SLIDE 14

Forward Pass

  • Forward Pass (beginning to end; L=>R)

– Determines duration of project – Start time of the project is Day Zero (0). – Early Finish time of each task is its Early Start time plus its estimated duration. – Early Start time of tasks is the Early Finish of the immediate preceding task. – Events having more then one predecessor task occur when ALL predecessor dependencies have been met.

slide-15
SLIDE 15

Forward Pass

  • Early Finish = Early Start + Duration

– EF = ES + DUR

slide-16
SLIDE 16

Backward Pass

  • Backward Pass (end to beginning; R=>L)

– Determines critical path & float activities – Project Late Finish time is taken from the Forward Pass calculation of the project Early Finish time. – Task Late Start time is calculated by subtracting estimated task duration from Late Finish time. – The Late Finish time of each predecessor task is the Late Start of its immediate successor task. – Activities having more than one successor task must

  • ccur soon enough to meet all successor

dependencies by Project Late Finish time.

slide-17
SLIDE 17

Backward Pass

  • Late Start = Late Finish - Duration

– LS = LF - DUR

slide-18
SLIDE 18

Float

  • Float
  • FLOAT = Late Finish – Early Finish
  • Float (or slack) is the amount of time that an individual

schedule activity can be delayed without delaying the project finish date.

slide-19
SLIDE 19

Float

  • Total Float = Late Start - Early Start

– TF = LS - ES

  • Free Float = Early Start (Next Activity) - Early Finish

– FF(x) = ES(x+1) - EF(x)

slide-20
SLIDE 20

The Critical Path

  • The Critical Path:

– Identifying the Critical Path »The series of schedule activities that determines the duration of the project. »Generally, the longest path through the project. »Usually defined by the schedule activities with zero float (critical path activities).

slide-21
SLIDE 21

Example

  • Simple Fragnet Exercise for FE 302
  • Home repair fragnet. You want to replace the

landscaping, fix the sprinkler, repaint the fence and add some stones on the surface that is currently bare earth.

slide-22
SLIDE 22

What is the key to dependency?

  • Details!
slide-23
SLIDE 23

Actions to Shorten the Critical Path

  • Schedule Compression Techniques

– Fast Tracking »Planning and/or overlapping sequential activities to be performed in parallel. – Crashing »Analyzing cost and schedule trade-offs to achieve reductions in schedule activity durations »Generally requires additional resources and person-hours »Increases costs »Must produce a shorter critical path to be visible (non- critical path activities can be crashed, but may not provide an overall benefit).

slide-24
SLIDE 24

CPM Advantages

Advantages: (complex projects)

– Accepted as evidence in court – Shows high degree of task interdependence – Shows cause & effect, impact & delay – Separate float time and critical activities

slide-25
SLIDE 25

Four Methods Used by Courts

  • “Actual Schedule”

“Submittal schedule”

  • Time Window

Fragnet

  • Adjusted As Planned

Collapsed As Built

  • Courts recognize not all schedules are the

actual schedule used to build the building, hence the methods are applied as the facts of the case merit.

slide-26
SLIDE 26

 Factors to Consider

 Total duration conforms to contract duration  Identifies critical activities for contractor and

government

 “Reasonable” duration of specific activities and

sequence “logic”

 Sufficiently demonstrate activity relationships to

support delay analysis

 Permit adequate detail to allow for progress review

and payments

Schedule Initial Reviews

slide-27
SLIDE 27

Exercise

  • Using the techniques laid out in the Draw Toast

video, work through the exercise.

  • Part 1 the WBS exercise is in general better

done in silence as described in video.

  • Part 2 is assembling the CPM schedule. Since

there are no details, you need to discuss assumptions here.

  • Part 3 is analysis, it does a deeper dive into float

for the teams that finish early.