Schedule & Plans for Commissioning Run K.T.Knpfle K.T.Knpfle - - PowerPoint PPT Presentation
Schedule & Plans for Commissioning Run K.T.Knpfle K.T.Knpfle - - PowerPoint PPT Presentation
Schedule & Plans for Commissioning Run K.T.Knpfle K.T.Knpfle MPI Kernphysik, Heidelberg ktkno@mpi-hd.mpg.de GERDA Collaboration Meeting at LNGS 1 3 March 2010 Outline update weekly schedule options for technical /
Outline
- update weekly schedule
- options for technical / commissioning run
- run team
2010 Mar 2 Schedule, plans - K.T.Knöpfle 2
jan february march apr
28 30 1 3 5 8 10 12 15 17 19 22 24 26 1 8 15 22 29 6 12 19 26 3 task / day
2010 month
calendar week 4
5 6 7 8 9 10 11 12 13 14 15 16 17 18 2010 lock ship to LNGS install it in cleanroom isolating flange delivery
?
X
!
b / 1 mar 2 isolating flange delivery SMA feedthru flange del/rdy install ext. gas system @ cleanroom
? ✔ ✔ /
e of 24 feb clean it mount cluster flange/shutters mount clean bench mount 2nd c lock support
✔ ✔ including He leak test ✔ ✔
update mount 2nd c-lock support install int gas system install int vacuum system mini UHV shutters del/inst
X
✔ ✔ / ✔ ✔
install 1/3 source mechanics replace blue support bars tests source mechanics in HdM
✔
X ( ✔)
✔
1 of 2:
source mechanics in HdM He leak test lock lock mechanics Rn emanation monitor
✔ ?
X
? ✔ test running
!! ??
1/2
Rn emanation lock insert dummy detector
?
jan february march apr
27 29 1 3 5 8 10 12 15 17 19 22 24 26 1 8 15 22 29 6 12 19 26 3 task / day
2010 month
calendar week 4
5 6 7 8 9 10 11 12 13 14 15 16 17 18 2010 @ e-cabinet Install racks install cooling & power fix cable length
✔
b / 1 mar 2
X
✔ ✔
fix cable length route cables lock - e-cabinet install/ test electronics install/ test DAQ e of 24 feb
✔
X
slow control complete hardware integration WT drainage update
demand driven PRIORITIES!
WT drainage pneumatic actuators delivery dto installation / test 3 rd flow rate test, w Ø110 diaphragma
X
✔ ✔
?
8m flow rate test w Ø110 diaphragma new flow regulator delivery DN65 flow regulator deliveries test of DN65 regulators
X
!!
?
X
misc control room furnitures/PC test of DN65 regulators pipes/flow meter re-installed/tested
!! 2/2
roots pump electrical inst c-lock PLC installation
X ?
Outline
Open issues:
immediate immediate filling of WT – linked to WT drainage delivery of c-lock arm for 1x 3-diode string delivery of c-lock arm for 1x 3-diode string muon veto commissioning close to immediate close to immediate delivery of 2nd arm of c-lock for 3 x 3-diode string operation
2010 Mar 2 Schedule, plans - K.T.Knöpfle 5
plan / options
Goal of commissioning run: Goal of commissioning run: set up and test c-lock for single string - do muon veto commissioning in parallel install diode(s), test electronics, DAQ, and calibration procedures, get first information about background gain experience for operation of 3x3-diode string with enriched Ge diodes How to proceed in detail – various options:
- bvious steps
mechanical test with weight – ist-soll comparison electrical test with capacitor He leak test cleaning of glove box ( & LAr surface? ) tests with prototype & cap to be optimized R f l k h d h l ? Rn assay of c-lock arm - when and how long? How many Genius TF diodes to be immersed? Any enriched diode?
2010 Mar 2 Schedule, plans - K.T.Knöpfle 6
schedule v0
develop / produce 3x3-diode string c-lock arm muon veto commissioning 8m WT
run week 6 NOW basic electric t t run week 2
drainage test
run week 6 tests LAr surface run week 3 write paper? clean? test w run week 3 continue? non-enriched?
2m WT drainage test?
c-lock delivery 1 install & prototype + cap run week 4 connect clean l b install x Genius TF y enriched glove box basic mechanic run week 1 run week 5 l k d li 2 WT filled
2010 Mar 2 Schedule, plans - K.T.Knöpfle 7
tests insert dummy load run week 6 c-lock delivery 2 install commission! diodes & Rn monitor
paper?
PAPER: realistic goal? - Would be nice support for funding requests…. 1) RESULT ON BACKGROUND INDEX (BI) ABOVE 1900 keV: Assume BI of 0.1 resp 0.01 cts per (kg keV y) in RoI of ~2000 – 2600+ keV, t 6 k 0 1 ( i h d) exposure m x t = 6 kg x 0.1 y (non-enriched) ► expect 36 resp 3.6 counts in RoI (a bit too optimistic, perhaps rather 25 and 2.5)! 2) RESULT FOR 2ν2β BACKGROUND BELOW 1900 keV: If BI ~ 0 01 nice comparison of DBD spectrum of enriched & natural Ge diode! If BI ~ 0.01, nice comparison of DBD spectrum of enriched & natural Ge diode! 2ν2β background will dominates – factor 10 larger in case of Ge-76! (6x10^23 x 0.1 / 10^21 = 60 per mol Ge-76 and per 0.1 year). 3) LIMITS FOR KNOWN LINES i.e. LIMITS on CONTAMINATIONS:
2010 Mar 2 Schedule, plans - K.T.Knöpfle 8
measured spectra
spectra measured at LNGS with Ge diode
unshielded
x
unshielded
Tl-208
nd Index ackgrou
predominantly external γ-rays
shielded
Ba
p y γ y
GERDA phase I goal
2010 Mar 2 Schedule, plans - K.T.Knöpfle 9
3x3 string
test setup with strings of rather different weights ►no strong deflections
2010 Mar 2 Schedule, plans - K.T.Knöpfle 10
3x3 string
first design study isolated rotatable
2010 Mar 2 Schedule, plans - K.T.Knöpfle 11
3x3 string
To Do List provide 2nd DN250 shutter - done replace motor & safety clutch replace cable drum provide feed thrus, isolation flange, cables run 30+ cables in energy chain provide DN150-DN250 interface provide two DN250 tubes, one with bellow to modify length design mounting sequence started design mounting sequence - design & provide mount/support for 3 strings incl. front end - started started GOAL: get it delivered by end of June!
2010 Mar 2 Schedule, plans - K.T.Knöpfle 12
run team
We need to establish a run team* within a few weeks!
* difference shifter – run team:
- shifter: changing
sometimes present
- shifter: changing - sometimes present
- run team: fixed - always present
2010 Mar 2 Schedule, plans - K.T.Knöpfle 13
the end
2010 Mar 2 Schedule, plans - K.T.Knöpfle 14