schedule plans for commissioning run
play

Schedule & Plans for Commissioning Run K.T.Knpfle K.T.Knpfle - PowerPoint PPT Presentation

Schedule & Plans for Commissioning Run K.T.Knpfle K.T.Knpfle MPI Kernphysik, Heidelberg ktkno@mpi-hd.mpg.de GERDA Collaboration Meeting at LNGS 1 3 March 2010 Outline update weekly schedule options for technical /


  1. Schedule & Plans for Commissioning Run K.T.Knöpfle K.T.Knöpfle MPI Kernphysik, Heidelberg ktkno@mpi-hd.mpg.de GERDA Collaboration Meeting at LNGS 1 – 3 March 2010

  2. Outline • update weekly schedule • options for technical / commissioning run • run team 2010 Mar 2 Schedule, plans - K.T.Knöpfle 2

  3. 2010 month jan february march apr 5 6 7 8 9 10 11 12 13 14 15 16 17 18 calendar week 4 2010 28 30 1 3 5 8 10 12 15 17 19 22 24 26 1 8 15 22 29 6 12 19 26 3 task / day b / 1 mar 2 lock ship to LNGS X ! install it in cleanroom ? ? isolating flange delivery isolating flange delivery e of 24 feb ✔ / SMA feedthru flange del/rdy install ext. gas system @ cleanroom update ✔ ✔ clean it ✔ including He leak test mount cluster flange/shutters ✔ mount clean bench ✔ ✔ mount 2nd c lock support mount 2nd c-lock support install int gas system install int vacuum system ✔ / ✔ X mini UHV shutters del/inst X ( ✔) ✔ install 1/3 source mechanics ✔ 1 of 2: replace blue support bars tests ✔ ✔ source mechanics in HdM source mechanics in HdM X He leak test lock ? lock mechanics ✔ test running Rn emanation monitor ? ? Rn emanation lock !! ?? insert dummy detector 1/2

  4. 2010 month jan february march apr 5 6 7 8 9 10 11 12 13 14 15 16 17 18 calendar week 4 2010 27 29 1 3 5 8 10 12 15 17 19 22 24 26 1 8 15 22 29 6 12 19 26 3 task / day b / 1 mar 2 @ e-cabinet ✔ Install racks ✔ install cooling & power X ✔ ✔ fix cable length fix cable length e of 24 feb route cables lock - e-cabinet X install / test electronics install/ test DAQ update slow control demand driven PRIORITIES! complete hardware integration WT drainage WT drainage ✔ pneumatic actuators delivery X dto installation / test ✔ 3 rd flow rate test, w Ø110 diaphragma ? ? 8m flow rate test w Ø110 diaphragma new flow regulator delivery X X DN65 flow regulator deliveries !! !! test of DN65 regulators test of DN65 regulators pipes/flow meter re-installed/tested misc control room furnitures/PC roots pump electrical inst X c-lock PLC installation ? 2/2

  5. Outline Open issues: immediate immediate filling of WT – linked to WT drainage delivery of c-lock arm for 1x 3-diode string delivery of c-lock arm for 1x 3-diode string muon veto commissioning close to immediate close to immediate delivery of 2 nd arm of c-lock for 3 x 3-diode string operation 2010 Mar 2 Schedule, plans - K.T.Knöpfle 5

  6. plan / options Goal of commissioning run: Goal of commissioning run: set up and test c-lock for single string - do muon veto commissioning in parallel install diode(s), test electronics, DAQ, and calibration procedures, get first information about background gain experience for operation of 3x3-diode string with enriched Ge diodes How to proceed in detail – various options: obvious steps mechanical test with weight – ist-soll comparison electrical test with capacitor He leak test cleaning of glove box ( & LAr surface? ) tests with prototype & cap to be optimized Rn assay of c-lock arm - when and how long? R f l k h d h l ? How many Genius TF diodes to be immersed? Any enriched diode? 2010 Mar 2 Schedule, plans - K.T.Knöpfle 6

  7. develop / produce 3x3-diode string c-lock arm schedule v0 muon veto commissioning 8m WT run week 6 run week 6 drainage test NOW run week 2 basic electric t tests t write LAr paper? surface run week 3 run week 3 clean? continue? 2m WT drainage test? non-enriched? test w prototype c-lock delivery 1 + cap run week 4 install & connect install x Genius TF clean y enriched glove box l b run week 5 WT filled basic run week 1 mechanic diodes & c-lock delivery 2 l k d li 2 tests install Rn monitor 2010 Mar 2 insert Schedule, plans - K.T.Knöpfle 7 commission! run week 6 dummy load

  8. paper? PAPER: realistic goal? - Would be nice support for funding requests…. 1) RESULT ON BACKGROUND INDEX (BI) ABOVE 1900 keV: Assume BI of 0.1 resp 0.01 cts per (kg keV y) in RoI of ~2000 – 2600+ keV, exposure m x t = 6 kg x 0.1 y (non-enriched) t 6 k 0 1 ( i h d) ► expect 36 resp 3.6 counts in RoI (a bit too optimistic, perhaps rather 25 and 2.5)! 2) RESULT FOR 2 ν 2 β BACKGROUND BELOW 1900 keV: If BI ~ 0 01 nice comparison of DBD spectrum of enriched & natural Ge diode! If BI ~ 0.01, nice comparison of DBD spectrum of enriched & natural Ge diode! 2 ν 2 β background will dominates – factor 10 larger in case of Ge-76! (6x10^23 x 0.1 / 10^21 = 60 per mol Ge-76 and per 0.1 year). 3) LIMITS FOR KNOWN LINES i.e. LIMITS on CONTAMINATIONS: 2010 Mar 2 Schedule, plans - K.T.Knöpfle 8

  9. measured spectra spectra measured at LNGS with Ge diode unshielded unshielded Tl-208 x nd Index ackgrou Ba shielded predominantly external γ -rays p y γ y GERDA phase I goal 2010 Mar 2 Schedule, plans - K.T.Knöpfle 9

  10. 3x3 string test setup with strings of rather different weights ► no strong deflections 2010 Mar 2 Schedule, plans - K.T.Knöpfle 10

  11. 3x3 string first design study isolated rotatable 2010 Mar 2 Schedule, plans - K.T.Knöpfle 11

  12. 3x3 string To Do List provide 2 nd DN250 shutter - done replace motor & safety clutch replace cable drum provide feed thrus, isolation flange, cables run 30+ cables in energy chain provide DN150-DN250 interface provide two DN250 tubes, one with bellow to modify length design mounting sequence - design mounting sequence started started design & provide mount/support for 3 strings incl. front end - started GOAL: get it delivered by end of June! 2010 Mar 2 Schedule, plans - K.T.Knöpfle 12

  13. run team We need to establish a run team* within a few weeks! * difference shifter – run team: •shifter: changing •shifter: changing - sometimes present sometimes present • run team: fixed - always present 2010 Mar 2 Schedule, plans - K.T.Knöpfle 13

  14. the end 2010 Mar 2 Schedule, plans - K.T.Knöpfle 14

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend