building retro commissioning program rcp building retro
play

Building Retro Commissioning Program (RCP) Building Retro - PowerPoint PPT Presentation

Building Retro Commissioning Program (RCP) Building Retro Commissioning Program (RCP) EAP 2015 Initiative 5 Building Energy System Retro Commissioning EAP 2015 Initiative 5 Building Energy System Retro Commissioning Strategy


  1. Building Retro ‐ Commissioning Program (RCP) Building Retro ‐ Commissioning Program (RCP) EAP 2015 Initiative 5 – Building Energy System Retro ‐ Commissioning EAP 2015 Initiative 5 – Building Energy System Retro ‐ Commissioning Strategy Optimize efficiency of building automation, heating ventilation and air conditioning (HVAC), mechanical, and electrical systems. The primary focus is to optimize building energy consuming systems and ensure efficient operation of both building systems and campus distribution/delivery systems, while effectively and efficiently meeting customer needs. Tactic Objective 5.1: Test and optimize building chillers, boilers, and HVAC system reliability and operating efficiencies. Objective 5.2: Raise awareness of retro ‐ commissioning and system optimization process and educate others about the benefits, while obtaining input and support to identify needs and ensure needs are met. Objective 5.3: Report on building energy consumption and cost, before, during, and after retro ‐ commissioning process to raise awareness of opportunities and results achieved. 1

  2. Building Retro ‐ Commissioning Program (RCP) Building Retro ‐ Commissioning Program (RCP) 99 buildings since 2002 • 13.8 Million Square Feet • 1992 Campus EUI was 364mBtu/gsf • 2012 at 214 mBtu/gsf • 2015 goal is 190 mBtu/gsf • Integral component of EAP 2015 • Focus on: • • Safety • Comfort • Meeting customer needs • Energy consumption and cost reduction 2

  3. Building Retro ‐ Commissioning Program (RCP) Building Retro ‐ Commissioning Program (RCP) 3000000 RC Annual Square Footage 2500000 2000000 Square Feet 1500000 1000000 500000 0 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 3

  4. Building Retro ‐ Commissioning Program (RCP) Building Retro ‐ Commissioning Program (RCP) Retro ‐ Commissioning Square Feet per Year 2002 943,849 2003 1,664,814 2004 919,784 2005 401,340 2006 2,481,077 2007 795,429 2008 1,997,701 2009 1,689,246 2010 115,797 2011 0 (Energy Steward Pilot) 2012 2,821,088 Total 13,830,125 sq.ft. Average 1,257,284 sq.ft./yr 4

  5. Building Retro ‐ Commissioning Program (RCP) Building Retro ‐ Commissioning Program (RCP) Retro ‐ Commission building selection based on input from several areas: • Data Analysis Team • Building Automation Team • Facilities Services • Energy Stewards • Historical Work Orders 5

  6. Building Retro ‐ Commissioning Program (RCP) Building Retro ‐ Commissioning Program (RCP) Prior to Retro ‐ Commissioning a building or group of buildings, we compare the Energy Use Index (EUI) – measured in mBtu/GSF ‐ and the Energy Cost Index (ECI) – measured in $/GSF ‐ of each building with prior year consumption and peer buildings, to identify potential opportunities. This analysis requires access to metered energy consumption and cost data for prior 12 to 36 months. Once this “benchmarking” analysis is complete, buildings to be commissioned are selected and prioritized on Retro ‐ Commissioning Priority List (RCPL). 6

  7. Building Retro ‐ Commissioning Program (RCP) Building Retro ‐ Commissioning Program (RCP) Identify specific, itemized Energy Consumption Reduction Measures (ECRM) recommendations (including payback calculations) in a document called the Retro ‐ Commissioning Plan (RCP) Recommendations are derived using both the original building specifications (design intent) together with changes in building use with latest design standards. Standard operational items are quickly corrected, such as: • Over ‐ Ridden Points • Systems in Hand, rather than Auto • Unnecessary preheat ‐ cooling ‐ reheat • Valves & Dampers not controlling • Over ‐ Ridden Schedules 7

  8. Building Retro ‐ Commissioning Program (RCP) Building Retro ‐ Commissioning Program (RCP) The RCP records occupant requirements for the building and any recommended change to the building design intent. Improvements and enhancement recommendations are reviewed and approved before implementation. The RCP includes a list of action items recommended for implementation with a proposed schedule, estimated cost and simple payback calculations. Operations and Maintenance (O&M) improvements are identified in the RCP and work orders are sent to Facilities Services (FS) for correction. Metered building consumption data and cost, both before and after the RC process, is documented. 8

  9. Building Retro ‐ Commissioning Program (RCP) Building Retro ‐ Commissioning Program (RCP) A Final Retro ‐ Commissioning Report (FRCR) is created that documents: • EUI & ECI before and after Retro ‐ Commissioning • Problems found & corrected • Additional ECRM’s requiring additional funding or resources along with estimated cost and pay ‐ back The report documents all work performed, as well as methods, criteria, and results of testing, measuring, and evaluation performed on building systems. The FRCR documents mechanical, electrical, HVAC and control systems and sequence of operations prior to RC, as compared to a post RC assessment. 9

  10. Building Retro ‐ Commissioning Program (RCP) Building Retro ‐ Commissioning Program (RCP) # Type Observation Recommendation Quick Hit AHUs O, S, and D serve offices, seminar 1 Optimization Implement shutdown or setback schedule X rooms and dining areas, were running 24/7 Determine cause for operator override and At the time of investigation, the CHW loop DP release the return the setpoint to automatic 2 Optimization setpoint was overridden at 18 psi and AHUs’ X control . Further Optimize the CHW loop DP CHW valves position was less than 50%. reset schedule limits using coil design data. CHW loop DP was calculated by CHWST- 3 Deficiency Fix CHW loop DP calculation formula X CHWRT in PPCL program Existing return valve control sequence will modulate return valve to maintain loop DP Optimize return valve and pump control 4 Optimization when two pumps were running at minimum sequence speed 10

  11. Building Retro ‐ Commissioning Program (RCP) Building Retro ‐ Commissioning Program (RCP) HHW loop DP sensor was failed and HHW 5 Deficiency Fix HHW loop pressure sensors X pump was 100% speed Preheat valve of AHUL3 was overridden at 6 Optimization Release preheat valve control of AHUL3 X 100% open Calibrate FCU thermostat and set room 7 Optimization Pump room temperature was 72°F X temperature at 80°F 8 Optimization Preheat setpoint was fixed at 55°F Optimize the preheat setpoint for all units X Energy recovery valve was modulated to maintain supply air temperature at its setpoint. Optimize Energy recovery valve control 9 Optimization Once CHW valve or preheat valve leaks by, the sequence energy recovery valve may fully closed AHU L1 and L2 DAT sensors were out of 10 Deficiency Calibrate DAT sensors for these two AHUs calibration 11

  12. Building Retro ‐ Commissioning Program (RCP) Building Retro ‐ Commissioning Program (RCP) Implement Static Pressure SP reset schedule for 11 Optimization Discharge static pressure setpoint was no reset AHUs Discharge air temperature setpoint was reset 12 Optimization Improve discharge air temperate reset schedule only according to outside air temperature Economizer control sequence of non-lab AHUs Improve economizer control sequence for non- 13 Optimization were reversed lab AHUs Both preheat valve and CHW valve control loops for two AHUs (B, O) were using same discharge air temperature sensor as input to Use preheat temperature sensor to control 14 Optimization X maintain setpoint. This may cause the preheat preheat valve valve to open to preheat air when CHW leaks by. There are about 15% TECs’ minimum air flow 15 Optimization Optimize TEC minimum air flow ratio is higher than 30% 12

  13. Building Retro ‐ Commissioning Program (RCP) Building Retro ‐ Commissioning Program (RCP) Only 8 terminal boxes with minimum airflow setback to zero during Un-OCC mode. The Reset the minimum airflow to zero during Un- 16 Optimization majority of terminal boxes had no minimum air OCC mode flow setback during Un-OCC. Only six labs (RM221, 224, 220, 230C, 236,230) with implemented UN-OCC setbacks; Implement room temperature and ventilation 17 Optimization the other 80 lab ventilation controllers did not setback schedule for labs have implement setback schedules Some labs’ minimum ACH was 10. Three exhaust air static pressure sensors were 18 Deficiency Calibrate exhaust air static pressure sensors out of calibration. All of the three lab exhaust fans were Once the exhaust air static sensors are 19 Optimization overridden at 100% speed calibrated, releasing exhausts fan speed. The switch station room temperature was only 20 Optimization Change the room temperature setpoint to 80°F 69°F Occupancy sensors cannot control the lighting 21 Deficiency Fix the lighting control problem X in classroom 107 and 108 13

  14. Building Retro ‐ Commissioning Program (RCP) Building Retro ‐ Commissioning Program (RCP) Discussion 14

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend