Building Retro Commissioning Program (RCP) Building Retro - - PowerPoint PPT Presentation

building retro commissioning program rcp building retro
SMART_READER_LITE
LIVE PREVIEW

Building Retro Commissioning Program (RCP) Building Retro - - PowerPoint PPT Presentation

Building Retro Commissioning Program (RCP) Building Retro Commissioning Program (RCP) EAP 2015 Initiative 5 Building Energy System Retro Commissioning EAP 2015 Initiative 5 Building Energy System Retro Commissioning Strategy


slide-1
SLIDE 1

1

Building Retro‐Commissioning Program (RCP)

EAP 2015 Initiative 5 – Building Energy System Retro‐Commissioning

Building Retro‐Commissioning Program (RCP)

EAP 2015 Initiative 5 – Building Energy System Retro‐Commissioning

Strategy Optimize efficiency of building automation, heating ventilation and air conditioning (HVAC), mechanical, and electrical systems. The primary focus is to

  • ptimize building energy consuming systems and ensure efficient operation of

both building systems and campus distribution/delivery systems, while effectively and efficiently meeting customer needs. Tactic Objective 5.1: Test and optimize building chillers, boilers, and HVAC system reliability and operating efficiencies. Objective 5.2: Raise awareness of retro‐commissioning and system optimization process and educate others about the benefits, while obtaining input and support to identify needs and ensure needs are met. Objective 5.3: Report on building energy consumption and cost, before, during, and after retro‐ commissioning process to raise awareness of opportunities and results achieved.

slide-2
SLIDE 2

2

Building Retro‐Commissioning Program (RCP) Building Retro‐Commissioning Program (RCP)

  • 99 buildings since 2002
  • 13.8 Million Square Feet
  • 1992 Campus EUI was 364mBtu/gsf
  • 2012 at 214 mBtu/gsf
  • 2015 goal is 190 mBtu/gsf
  • Integral component of EAP 2015
  • Focus on:
  • Safety
  • Comfort
  • Meeting customer needs
  • Energy consumption and cost reduction
slide-3
SLIDE 3

3

Building Retro‐Commissioning Program (RCP) Building Retro‐Commissioning Program (RCP)

500000 1000000 1500000 2000000 2500000 3000000 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 Square Feet

RC Annual Square Footage

slide-4
SLIDE 4

4

Building Retro‐Commissioning Program (RCP) Building Retro‐Commissioning Program (RCP)

Retro‐Commissioning Square Feet per Year

2002 943,849 2003 1,664,814 2004 919,784 2005 401,340 2006 2,481,077 2007 795,429 2008 1,997,701 2009 1,689,246 2010 115,797 2011 0 (Energy Steward Pilot) 2012 2,821,088

Total 13,830,125 sq.ft. Average 1,257,284 sq.ft./yr

slide-5
SLIDE 5

5

Building Retro‐Commissioning Program (RCP) Building Retro‐Commissioning Program (RCP)

Retro‐Commission building selection based on input from several areas:

  • Data Analysis Team
  • Building Automation Team
  • Facilities Services
  • Energy Stewards
  • Historical Work Orders
slide-6
SLIDE 6

6

Building Retro‐Commissioning Program (RCP) Building Retro‐Commissioning Program (RCP)

Prior to Retro‐Commissioning a building or group of buildings, we compare the Energy Use Index (EUI) – measured in mBtu/GSF ‐ and the Energy Cost Index (ECI) – measured in $/GSF ‐ of each building with prior year consumption and peer buildings, to identify potential opportunities. This analysis requires access to metered energy consumption and cost data for prior 12 to 36 months. Once this “benchmarking” analysis is complete, buildings to be commissioned are selected and prioritized on Retro‐Commissioning Priority List (RCPL).

slide-7
SLIDE 7

7

Building Retro‐Commissioning Program (RCP) Building Retro‐Commissioning Program (RCP)

Identify specific, itemized Energy Consumption Reduction Measures (ECRM) recommendations (including payback calculations) in a document called the Retro‐Commissioning Plan (RCP) Recommendations are derived using both the original building specifications (design intent) together with changes in building use with latest design standards. Standard operational items are quickly corrected, such as:

  • Over‐Ridden Points
  • Systems in Hand, rather than Auto
  • Unnecessary preheat‐cooling‐reheat
  • Valves & Dampers not controlling
  • Over‐Ridden Schedules
slide-8
SLIDE 8

8

Building Retro‐Commissioning Program (RCP) Building Retro‐Commissioning Program (RCP)

The RCP records occupant requirements for the building and any recommended change to the building design intent. Improvements and enhancement recommendations are reviewed and approved before implementation. The RCP includes a list of action items recommended for implementation with a proposed schedule, estimated cost and simple payback calculations. Operations and Maintenance (O&M) improvements are identified in the RCP and work orders are sent to Facilities Services (FS) for correction. Metered building consumption data and cost, both before and after the RC process, is documented.

slide-9
SLIDE 9

9

Building Retro‐Commissioning Program (RCP) Building Retro‐Commissioning Program (RCP)

A Final Retro‐Commissioning Report (FRCR) is created that documents:

  • EUI & ECI before and after Retro‐Commissioning
  • Problems found & corrected
  • Additional ECRM’s requiring additional funding or resources

along with estimated cost and pay‐back The report documents all work performed, as well as methods, criteria, and results of testing, measuring, and evaluation performed on building systems. The FRCR documents mechanical, electrical, HVAC and control systems and sequence of operations prior to RC, as compared to a post RC assessment.

slide-10
SLIDE 10

10

Building Retro‐Commissioning Program (RCP) Building Retro‐Commissioning Program (RCP)

# Type Observation Recommendation Quick Hit 1 Optimization AHUs O, S, and D serve offices, seminar rooms and dining areas, were running 24/7 Implement shutdown or setback schedule X 2 Optimization At the time of investigation, the CHW loop DP setpoint was overridden at 18 psi and AHUs’ CHW valves position was less than 50%. Determine cause for operator override and release the return the setpoint to automatic

  • control. Further Optimize the CHW loop DP

reset schedule limits using coil design data. X 3 Deficiency CHW loop DP was calculated by CHWST- CHWRT in PPCL program Fix CHW loop DP calculation formula X 4 Optimization Existing return valve control sequence will modulate return valve to maintain loop DP when two pumps were running at minimum speed Optimize return valve and pump control sequence

slide-11
SLIDE 11

11

Building Retro‐Commissioning Program (RCP) Building Retro‐Commissioning Program (RCP)

5 Deficiency HHW loop DP sensor was failed and HHW pump was 100% speed Fix HHW loop pressure sensors X 6 Optimization Preheat valve of AHUL3 was overridden at 100% open Release preheat valve control of AHUL3 X 7 Optimization Pump room temperature was 72°F Calibrate FCU thermostat and set room temperature at 80°F X 8 Optimization Preheat setpoint was fixed at 55°F Optimize the preheat setpoint for all units X 9 Optimization Energy recovery valve was modulated to maintain supply air temperature at its setpoint. Once CHW valve or preheat valve leaks by, the energy recovery valve may fully closed Optimize Energy recovery valve control sequence 10 Deficiency AHU L1 and L2 DAT sensors were out of calibration Calibrate DAT sensors for these two AHUs

slide-12
SLIDE 12

12

Building Retro‐Commissioning Program (RCP) Building Retro‐Commissioning Program (RCP)

11 Optimization Discharge static pressure setpoint was no reset Implement Static Pressure SP reset schedule for AHUs 12 Optimization Discharge air temperature setpoint was reset

  • nly according to outside air temperature

Improve discharge air temperate reset schedule 13 Optimization Economizer control sequence of non-lab AHUs were reversed Improve economizer control sequence for non- lab AHUs 14 Optimization Both preheat valve and CHW valve control loops for two AHUs (B, O) were using same discharge air temperature sensor as input to maintain setpoint. This may cause the preheat valve to open to preheat air when CHW leaks by. Use preheat temperature sensor to control preheat valve X 15 Optimization There are about 15% TECs’ minimum air flow ratio is higher than 30% Optimize TEC minimum air flow

slide-13
SLIDE 13

13

Building Retro‐Commissioning Program (RCP) Building Retro‐Commissioning Program (RCP)

16 Optimization Only 8 terminal boxes with minimum airflow setback to zero during Un-OCC mode. The majority of terminal boxes had no minimum air flow setback during Un-OCC. Reset the minimum airflow to zero during Un- OCC mode 17 Optimization Only six labs (RM221, 224, 220, 230C, 236,230) with implemented UN-OCC setbacks; the other 80 lab ventilation controllers did not have implement setback schedules Some labs’ minimum ACH was 10. Implement room temperature and ventilation setback schedule for labs 18 Deficiency Three exhaust air static pressure sensors were

  • ut of calibration.

Calibrate exhaust air static pressure sensors 19 Optimization All of the three lab exhaust fans were

  • verridden at 100% speed

Once the exhaust air static sensors are calibrated, releasing exhausts fan speed. 20 Optimization The switch station room temperature was only 69°F Change the room temperature setpoint to 80°F 21 Deficiency Occupancy sensors cannot control the lighting in classroom 107 and 108 Fix the lighting control problem X

slide-14
SLIDE 14

14

Building Retro‐Commissioning Program (RCP) Building Retro‐Commissioning Program (RCP)

Discussion