Scale Efficient Network Extensions Key design features and options - - PowerPoint PPT Presentation

scale efficient network extensions
SMART_READER_LITE
LIVE PREVIEW

Scale Efficient Network Extensions Key design features and options - - PowerPoint PPT Presentation

Scale Efficient Network Extensions Key design features and options for a SENEs framework Chris Spangaro and Elisabeth Ross Wholesale Environment and Transmission team Adelaide 20 October 2010 AEMC PAGE 1 Purpose of this presentation


slide-1
SLIDE 1

AEMC PAGE 1

Key design features and options for a SENEs framework Chris Spangaro and Elisabeth Ross Wholesale Environment and Transmission team

Adelaide 20 October 2010

Scale Efficient Network Extensions

slide-2
SLIDE 2

AEMC PAGE 2

Purpose of this presentation

  • Highlight the key issues to consider
  • Outline some of the key design features for a SENE framework
  • Discuss the five options presented in the Options Paper

– Options 1 and 2 are variations on the existing proposed SENE framework – Options 3 and 4 use the RIT-T to assess the efficiency of building incremental capacity in addition to meeting the connection requirements of a first connecting generator – Option 5 introduces a new type of prescribed service for a shared connection, paid for by generators

slide-3
SLIDE 3

AEMC PAGE 3

Key questions to consider

  • How is the investment decision made?
  • How is the SENE funded?
  • How is the SENE priced?
  • What is the nature of the transmission service on the SENE?
  • How should stranded asset risks be managed?
slide-4
SLIDE 4

AEMC PAGE 4

Summary of key design choices

  • The trigger for considering whether a SENE should be built
  • What investment test should be applied to assess the likely

efficiency of the investment

  • How the costs of the SENE should be allocated amongst relevant

parties and the structure of the charge that they face

  • What access provisions apply to the SENE
  • Regulatory oversight mechanisms
slide-5
SLIDE 5

AEMC PAGE 5

Options 1 and 2

Variations on the proposed SENE framework

slide-6
SLIDE 6

AEMC PAGE 6

Overview of Options 1 and 2

  • AEMO identifies possible “SENE zones”
  • NSPs undertake preplanning of future connection requirements

based on a forecast profile of generation entry

  • Generators pay an average cost charge based on use of SENE
  • Customers underwrite the cost of spare capacity but are rebated
  • ver time if generation materialises as expected
  • AER and AEMO have oversight roles to protect customer interests
slide-7
SLIDE 7

AEMC PAGE 7

Option 1: SENEs with a cost threshold trigger

Trigger for considering a SENE AEMO identifies possible SENE zones NSPs identify credible options, published in APR/on website Investment test Implicit in NSP planning and firm connection agreements representing 25% of capital costs

  • f SENE

Cost allocation and charging methodology Generators pay a proportional average cost

  • charge. Customers underwrite risk but face

an expected cost of zero. Access provisions Mandated compensation arrangements on the SENE Regulatory oversight AER has power of veto, AEMO reviews forecasts

slide-8
SLIDE 8

AEMC PAGE 8

Option 2: SENEs with an economic test and no capacity rights

Trigger for considering a SENE AEMO identifies possible SENE zones NSPs identify credible options, published in APR/on website Investment test Explicit assessment of net market benefits and firm connection agreements representing 25% of capital costs of SENE Cost allocation and charging methodology Generators pay a proportional average cost

  • charge. Customers underwrite risk but face

an expected cost of zero. Access provisions As per the shared network. Terms of access to be negotiated between NSP and generator Regulatory oversight AER has power of veto, AEMO reviews forecasts

slide-9
SLIDE 9

AEMC PAGE 9

Design feature Option 1 Option 2 Trigger for considering a SENE AEMO identifies possible SENE zones NSPs identify credible options, published in APR/on website As per Option 1 Investment test Implicit in NSP planning and firm connection agreements representing 25% of capital costs

  • f SENE

Explicit assessment of net market benefits and firm connection agreements representing 25% of capital costs of SENE Cost allocation and charging methodology Generators pay a proportional average cost charge. Customers underwrite risk but face an expected cost of zero. As per Option 1 Access provisions Mandated compensation arrangements As per the shared network. Terms

  • f access to be negotiated

between NSP and generator Regulatory

  • versight

AER has power of veto, AEMO reviews forecasts As per Option 1

Summary of Options 1 and 2

slide-10
SLIDE 10

AEMC PAGE 10

Options 3 and 4

Incremental approach to SENEs

slide-11
SLIDE 11

AEMC PAGE 11

Overview of Options 3 and 4

  • Generator (or group of generators) connection enquiry to NSP

triggers consideration of need for incremental capacity above first generator’s requirements

  • RIT-T used to assess efficiency of incremental capacity
  • First generator(s) pay stand alone cost of their connection –

subsequent connecting generators contribute to this cost

  • Under Option 3, customers permanently fund incremental capacity
  • Under Option 4, customer charges reduce as subsequent

generators connect

slide-12
SLIDE 12

AEMC PAGE 12

Incremental approach

Existing network

~ ~ ~

Additional capacity to allow future generation entry Conceptual connection requirements for first generator

slide-13
SLIDE 13

AEMC PAGE 13

Option 3: Incremental approach to SENEs

Trigger for considering a SENE A generator connection enquiry Investment test Signed connection agreement with first generator, RIT-T applied to incremental capacity Cost allocation and charging methodology First generator(s) pays stand alone cost, subsequent generators contribute to this, customers pay for incremental capacity Access provisions As per the shared network. Terms of access to be negotiated between NSP and generator Regulatory oversight AER reviews application of RIT-T, AEMO reviews generation forecasts

slide-14
SLIDE 14

AEMC PAGE 14

Option 4: Incremental approach with generators bearing costs

Trigger for considering a SENE A generator connection enquiry Investment test Signed connection agreement with first generator, RIT-T applied to incremental capacity Cost allocation and charging methodology First generator(s) pays stand alone cost, customers underwrite additional capacity. Both these charges reduce with additional connections Access provisions As per the shared network. Terms of access to be negotiated between NSP and generator Regulatory oversight AER reviews application of RIT-T, AEMO reviews generation forecasts

slide-15
SLIDE 15

AEMC PAGE 15

Comparison of charging arrangements for Options 3 and 4

Option 3 Option 4

Day 1 Day 1 All gens connect All gens connect NSP’s annual revenue for SENE NSP’s annual revenue for SENE

Customers Generators

slide-16
SLIDE 16

AEMC PAGE 16

Design feature Option 3 Option 4 Trigger for considering a SENE A generator connection enquiry As per Option 3 Investment test Signed connection agreement with first generator, RIT-T applied to incremental capacity As per Option 3 Cost allocation and charging methodology First generator(s) pays stand alone cost, subsequent generators contribute to this, customers pay for incremental capacity First generator(s) pays stand alone cost, customers underwrite additional capacity. Both these charges reduce with additional connections Access provisions As per the shared network. Terms

  • f access to be negotiated

between NSP and generator As per Option 3 Regulatory

  • versight

AER reviews application of RIT-T, AEMO reviews generation forecasts As per Option 3

Summary of Options 3 and 4

slide-17
SLIDE 17

AEMC PAGE 17

Option 5

SENEs as part of the shared network with a new generator charge

slide-18
SLIDE 18

AEMC PAGE 18

Overview of Options 5

  • A new type of prescribed transmission service for shared

connections, such as SENEs

  • Shared connections are defined as all elements of transmission

network spurs shared by more than one party but which are not required to support DNSP load

  • These assets would support a new type of prescribed transmission

service, paid by generators

  • The cost of the SENE would enter the regulatory asset base and

charges would form part of the maximum allowed revenue

  • Any costs not recovered from generators would automatically be

recovered from customers

slide-19
SLIDE 19

AEMC PAGE 19

Option 5: SENEs as shared network

Trigger for considering a SENE A generator connection enquiry Investment test Signed connection agreement with first generator, RIT-T applied to entire investment Cost allocation and charging methodology A charge for a new type of prescribed transmission service is introduced relating to SENEs, which generators pay. Customers pay for spare SENE capacity Access provisions As per the shared network. Terms of access to be negotiated between NSP and generator Regulatory oversight AER reviews application of RIT-T, AEMO reviews generation forecasts

slide-20
SLIDE 20

AEMC PAGE 20

Comparison of charging arrangements for Options 1 and 5

Time NSP’s annual revenue for SENE ($) Charges paid by generators Costs underwritten by customers Rebates to consumers G2 enters G3 enters G4 enters G1 enters Time NSP’s annual revenue for SENE ($) Charges paid by generators Costs borne by customers G2 enters G3 enters G4 enters G1 enters

slide-21
SLIDE 21

AEMC PAGE 21

Option 5: SENEs as shared network

Trigger for considering a SENE A generator connection enquiry Investment test Signed connection agreement with first generator, RIT-T applied to entire investment Cost allocation and charging methodology A charge for a new type of prescribed transmission service is introduced relating to SENEs, which generators pay. Customers pay for spare SENE capacity Access provisions As per the shared network. Terms of access to be negotiated between NSP and generator Regulatory oversight AER reviews application of RIT-T, AEMO reviews generation forecasts

slide-22
SLIDE 22

AEMC PAGE 22

Where to from here?

slide-23
SLIDE 23

AEMC PAGE 23

Process from here

  • Submissions to the Options Paper

due on 12 November

  • Draft Rule determination due on

17 February

  • Final Rule determination due on

12 May

slide-24
SLIDE 24

AEMC PAGE 24