scale efficient network extensions
play

Scale Efficient Network Extensions Key design features and options - PowerPoint PPT Presentation

Scale Efficient Network Extensions Key design features and options for a SENEs framework Chris Spangaro and Elisabeth Ross Wholesale Environment and Transmission team Adelaide 20 October 2010 AEMC PAGE 1 Purpose of this presentation


  1. Scale Efficient Network Extensions Key design features and options for a SENEs framework Chris Spangaro and Elisabeth Ross Wholesale Environment and Transmission team Adelaide 20 October 2010 AEMC PAGE 1

  2. Purpose of this presentation • Highlight the key issues to consider • Outline some of the key design features for a SENE framework • Discuss the five options presented in the Options Paper – Options 1 and 2 are variations on the existing proposed SENE framework – Options 3 and 4 use the RIT-T to assess the efficiency of building incremental capacity in addition to meeting the connection requirements of a first connecting generator – Option 5 introduces a new type of prescribed service for a shared connection, paid for by generators AEMC PAGE 2

  3. Key questions to consider • How is the investment decision made? • How is the SENE funded? • How is the SENE priced? • What is the nature of the transmission service on the SENE? • How should stranded asset risks be managed? AEMC PAGE 3

  4. Summary of key design choices • The trigger for considering whether a SENE should be built • What investment test should be applied to assess the likely efficiency of the investment • How the costs of the SENE should be allocated amongst relevant parties and the structure of the charge that they face • What access provisions apply to the SENE • Regulatory oversight mechanisms AEMC PAGE 4

  5. Options 1 and 2 Variations on the proposed SENE framework AEMC PAGE 5

  6. Overview of Options 1 and 2 • AEMO identifies possible “SENE zones” • NSPs undertake preplanning of future connection requirements based on a forecast profile of generation entry • Generators pay an average cost charge based on use of SENE • Customers underwrite the cost of spare capacity but are rebated over time if generation materialises as expected • AER and AEMO have oversight roles to protect customer interests AEMC PAGE 6

  7. Option 1: SENEs with a cost threshold trigger Trigger for considering a SENE AEMO identifies possible SENE zones NSPs identify credible options, published in APR/on website Investment test Implicit in NSP planning and firm connection agreements representing 25% of capital costs of SENE Cost allocation and charging Generators pay a proportional average cost methodology charge. Customers underwrite risk but face an expected cost of zero. Access provisions Mandated compensation arrangements on the SENE Regulatory oversight AER has power of veto, AEMO reviews forecasts AEMC PAGE 7

  8. Option 2: SENEs with an economic test and no capacity rights Trigger for considering a SENE AEMO identifies possible SENE zones NSPs identify credible options, published in APR/on website Investment test Explicit assessment of net market benefits and firm connection agreements representing 25% of capital costs of SENE Cost allocation and charging Generators pay a proportional average cost methodology charge. Customers underwrite risk but face an expected cost of zero. Access provisions As per the shared network. Terms of access to be negotiated between NSP and generator Regulatory oversight AER has power of veto, AEMO reviews forecasts AEMC PAGE 8

  9. Summary of Options 1 and 2 Design feature Option 1 Option 2 Trigger for AEMO identifies possible SENE As per Option 1 considering a zones SENE NSPs identify credible options, published in APR/on website Investment test Implicit in NSP planning and firm Explicit assessment of net market connection agreements benefits and firm connection representing 25% of capital costs agreements representing 25% of of SENE capital costs of SENE Cost allocation Generators pay a proportional As per Option 1 and charging average cost charge. Customers methodology underwrite risk but face an expected cost of zero. Access Mandated compensation As per the shared network. Terms provisions arrangements of access to be negotiated between NSP and generator Regulatory AER has power of veto, AEMO As per Option 1 oversight reviews forecasts AEMC PAGE 9

  10. Options 3 and 4 Incremental approach to SENEs AEMC PAGE 10

  11. Overview of Options 3 and 4 • Generator (or group of generators) connection enquiry to NSP triggers consideration of need for incremental capacity above first generator’s requirements • RIT-T used to assess efficiency of incremental capacity • First generator(s) pay stand alone cost of their connection – subsequent connecting generators contribute to this cost • Under Option 3, customers permanently fund incremental capacity • Under Option 4, customer charges reduce as subsequent generators connect AEMC PAGE 11

  12. Incremental approach Existing Additional capacity to allow network future generation entry ~ ~ ~ Conceptual connection requirements for first generator AEMC PAGE 12

  13. Option 3: Incremental approach to SENEs Trigger for considering a SENE A generator connection enquiry Investment test Signed connection agreement with first generator, RIT-T applied to incremental capacity Cost allocation and charging First generator(s) pays stand alone cost, methodology subsequent generators contribute to this, customers pay for incremental capacity Access provisions As per the shared network. Terms of access to be negotiated between NSP and generator Regulatory oversight AER reviews application of RIT-T, AEMO reviews generation forecasts AEMC PAGE 13

  14. Option 4: Incremental approach with generators bearing costs Trigger for considering a SENE A generator connection enquiry Signed connection agreement with first Investment test generator, RIT-T applied to incremental capacity Cost allocation and charging First generator(s) pays stand alone cost, methodology customers underwrite additional capacity. Both these charges reduce with additional connections Access provisions As per the shared network. Terms of access to be negotiated between NSP and generator Regulatory oversight AER reviews application of RIT-T, AEMO reviews generation forecasts AEMC PAGE 14

  15. Comparison of charging arrangements for Options 3 and 4 Option 3 Option 4 NSP’s NSP’s annual annual revenue revenue for SENE for SENE Day 1 All gens All gens Day 1 connect connect Customers Generators AEMC PAGE 15

  16. Summary of Options 3 and 4 Design feature Option 3 Option 4 Trigger for A generator connection enquiry As per Option 3 considering a SENE Investment test Signed connection agreement with As per Option 3 first generator, RIT-T applied to incremental capacity Cost allocation First generator(s) pays stand First generator(s) pays stand and charging alone cost, subsequent generators alone cost, customers underwrite methodology contribute to this, customers pay additional capacity. Both these for incremental capacity charges reduce with additional connections Access As per the shared network. Terms As per Option 3 provisions of access to be negotiated between NSP and generator Regulatory AER reviews application of RIT-T, As per Option 3 oversight AEMO reviews generation forecasts AEMC PAGE 16

  17. Option 5 SENEs as part of the shared network with a new generator charge AEMC PAGE 17

  18. Overview of Options 5 • A new type of prescribed transmission service for shared connections, such as SENEs • Shared connections are defined as all elements of transmission network spurs shared by more than one party but which are not required to support DNSP load • These assets would support a new type of prescribed transmission service, paid by generators • The cost of the SENE would enter the regulatory asset base and charges would form part of the maximum allowed revenue • Any costs not recovered from generators would automatically be recovered from customers AEMC PAGE 18

  19. Option 5: SENEs as shared network Trigger for considering a SENE A generator connection enquiry Investment test Signed connection agreement with first generator, RIT-T applied to entire investment Cost allocation and charging A charge for a new type of prescribed methodology transmission service is introduced relating to SENEs, which generators pay. Customers pay for spare SENE capacity Access provisions As per the shared network. Terms of access to be negotiated between NSP and generator Regulatory oversight AER reviews application of RIT-T, AEMO reviews generation forecasts AEMC PAGE 19

  20. Comparison of charging arrangements for Options 1 and 5 NSP’s annual NSP’s annual Charges paid revenue revenue by generators for SENE ($) Rebates to for SENE ($) consumers Charges paid Costs Costs borne by by generators underwritten by customers customers Time G1 G2 G3 G4 Time G1 G2 G3 G4 enters enters enters enters enters enters enters enters AEMC PAGE 20

  21. Option 5: SENEs as shared network Trigger for considering a SENE A generator connection enquiry Investment test Signed connection agreement with first generator, RIT-T applied to entire investment Cost allocation and charging A charge for a new type of prescribed methodology transmission service is introduced relating to SENEs, which generators pay. Customers pay for spare SENE capacity Access provisions As per the shared network. Terms of access to be negotiated between NSP and generator Regulatory oversight AER reviews application of RIT-T, AEMO reviews generation forecasts AEMC PAGE 21

  22. PAGE 22 Where to from here? AEMC

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend