Scale Efficient Network Extensions Background and issues this Rule - - PowerPoint PPT Presentation

scale efficient network extensions
SMART_READER_LITE
LIVE PREVIEW

Scale Efficient Network Extensions Background and issues this Rule - - PowerPoint PPT Presentation

Scale Efficient Network Extensions Background and issues this Rule change is seeking to address Chris Spangaro and Elisabeth Ross Wholesale, Environment and Transmission team Adelaide 20 October 2010 AEMC PAGE 1 Purpose of this presentation


slide-1
SLIDE 1

AEMC PAGE 1

Scale Efficient Network Extensions

Background and issues this Rule change is seeking to address Chris Spangaro and Elisabeth Ross Wholesale, Environment and Transmission team

Adelaide 20 October 2010

slide-2
SLIDE 2

AEMC PAGE 2

Purpose of this presentation

  • Outline the background to this Rule change request
  • Highlight the key issues this Rule change is seeking to address
  • Clarify the objective of SENEs
  • Summarise the proposed Rule change
  • Discuss some of the challenges in implementing the proposed

frameworks

slide-3
SLIDE 3

AEMC PAGE 3

Background to this Rule change request

slide-4
SLIDE 4

AEMC PAGE 4

Review of Energy Market Frameworks in light of Climate Change Policies: findings

  • The MCE requested the AEMC

conduct a review of energy market frameworks in light of climate change policies

  • Patterns of generation investment are

changing

  • Existing frameworks require

strengthening to manage these changes

slide-5
SLIDE 5

AEMC PAGE 5

Review of Energy Market Frameworks in light of Climate Change Policies: recommendations

  • A new framework to promote the

efficient connection of clusters of new generation in proximate locations over time: SENEs

  • Provides a mechanism to allow

forward looking network investment for generation connection

  • Generators pay an average cost

charge for use of the SENE

  • Requires customers to underwrite

the risk of asset stranding

Existing network

~ ~ ~ ~ ~ ~

SENE hub

slide-6
SLIDE 6

AEMC PAGE 6

Illustrative examples of opportunities for scale efficiencies

  • Magnitude of efficiency gains

depend on : – number and volume of gens – geographical spread of gens – distance from shared network

  • Example 1: Coordinating

connections for 4 generators over 35km of line would save a total of $12m Citipower/Powercor

  • Example 2: coordinating

connection of 2000 MW of generation would save the first connecting 500 MW generator $75m Grid Australia Example 1 Example 2

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% First gen stand alone cost First gen shared cost First gen stand alone cost First gen shared cost

Stand alone cost versus shared cost for first connecting generator

slide-7
SLIDE 7

AEMC PAGE 7

The SENE Rule change request

  • MCE endorsed the recommendation

and submitted a Rule change request

  • MCE considered the proposal should

promote the NEO by: – overcoming the risk of inefficient asset duplication – ensuring efficient assets are built – minimising risk to consumers

slide-8
SLIDE 8

AEMC PAGE 8

Consultation on this Rule change to date

  • 28 submissions, 2 supplementary

submissions received on the Consultation Paper

  • A shift away from more widespread

support for SENEs

  • Still some need for change
  • Concerns with the proposed Rule:

– level of risk imposed on customers – complexity of the proposed Rule – implications for competitive neutrality between generators

slide-9
SLIDE 9

AEMC PAGE 9

Interaction of this Rule change with the TFR

  • MCE has directed the AEMC to

conduct a review of transmission frameworks

  • The scope of SENEs and the TFR

may overlap

  • The AEMC has decided to

progress the SENEs Rule change independently

  • However, the scope of the TFR

will be a consideration in considering any potential Rule change to accommodate SENEs

slide-10
SLIDE 10

AEMC PAGE 10

Nature of the problem

Issues this Rule change is seeking to address

slide-11
SLIDE 11

AEMC PAGE 11

Patterns of generation investment are changing

  • The scale of generation investment is

changing

  • New technologies have different

characteristics from past generation investment: – relatively small compared to “lumpy” network investment for connection – some low cost sources of generation are remote from existing networks

  • New generation may be clustered and

seek connection over a period of time

slide-12
SLIDE 12

AEMC PAGE 12

Connecting new types of generation is challenging

  • The economies of scale in network

investment imply coordinating generation connection will lower total system costs

  • Achieving efficient connection outcomes

is challenging because: – coordination challenges – the temporal nature of the problem – managing the risk of stranded assets

  • Achieving optimal investment outcomes

requires an entity to bear the asset stranding risk

slide-13
SLIDE 13

AEMC PAGE 13

Connecting new types of generation is challenging

  • The existing arrangements are unlikely to

allow efficient outcomes for new patterns of generation

  • No entity has an incentive to provide forward

looking investment for connections – The existing frameworks do not encourage or reward speculative building of network assets

  • This may lead to inefficient outcomes,

including: – duplication of network assets – delays in connection

slide-14
SLIDE 14

AEMC PAGE 14

Objective of SENEs

slide-15
SLIDE 15

AEMC PAGE 15

The purpose of this Rule change request

To allow the efficient connection of multiple generators with multiple owners in proximate areas over time and to charge an efficient price for that service

slide-16
SLIDE 16

AEMC PAGE 16

Summary of the Rule change request

slide-17
SLIDE 17

AEMC PAGE 17

The proposed Rule change

Trigger for considering a SENE

  • AEMO to identify possible SENE zones in its

annual NTNDP

  • NSPs to identify credible options in their APR or
  • n their website

Investment test

  • NSPs to consider opportunities for scale

efficiencies and, if so, publish: – Planning report – Standard connection offer

  • Construction of the SENE triggered by

connection agreement with at least one generator

slide-18
SLIDE 18

AEMC PAGE 18

The proposed Rule change

Cost allocation and charging methodology

Time Annual charge for SENE ($) NSP’s annual revenue requirement Charges paid by generators Charges borne by consumers Rebates to consumers G2 enters G3 enters G4 enters G1 enters

  • Generators pay an average

cost charge for use of the SENE

  • Customers underwrite any

remaining costs

The shaded areas will be equal if generation connects as expected

slide-19
SLIDE 19

AEMC PAGE 19

The proposed Rule change

Access provisions

  • Generators are entitled to compensation where

constrained off by another generator Regulatory oversight

  • AER prepares guidelines
  • AER has the ability to veto the connection offer
  • Forecasts to be reviewed by AEMO
  • A policy review to be undertaken by the AEMC

5 years after commencement

slide-20
SLIDE 20

AEMC PAGE 20

Challenges in implementing SENEs

slide-21
SLIDE 21

AEMC PAGE 21

Implementation challenges

  • The existing connections

framework was developed to meet historical requirements

  • We now seek to allow different

types of generation to connect using shared assets

  • SENEs, as proposed, do not fit

naturally within existing frameworks

  • This creates additional complexity

for any SENEs framework

slide-22
SLIDE 22

AEMC PAGE 22

Implementation challenges – examples from proposed framework

  • Connection assets are typically

funded by generators, but SENEs require initial customer funding to allow forward looking investment

  • The Rules do not envisage assets

that were once funded by customers subsequently being funded by generators

  • The proposed Rule defines a SENE

as being part of the network but it is treated differently from the remainder of the network

slide-23
SLIDE 23

AEMC PAGE 23

Implementation challenges – a single framework for many different configurations

Every SENE is likely to be unique

Existing network

~ ~ ~

Existing network

~ ~ ~

SENE hub

~

slide-24
SLIDE 24

AEMC PAGE 24