scale efficient network extensions
play

Scale Efficient Network Extensions Background and issues this Rule - PowerPoint PPT Presentation

Scale Efficient Network Extensions Background and issues this Rule change is seeking to address Chris Spangaro and Elisabeth Ross Wholesale, Environment and Transmission team Adelaide 20 October 2010 AEMC PAGE 1 Purpose of this presentation


  1. Scale Efficient Network Extensions Background and issues this Rule change is seeking to address Chris Spangaro and Elisabeth Ross Wholesale, Environment and Transmission team Adelaide 20 October 2010 AEMC PAGE 1

  2. Purpose of this presentation • Outline the background to this Rule change request • Highlight the key issues this Rule change is seeking to address • Clarify the objective of SENEs • Summarise the proposed Rule change • Discuss some of the challenges in implementing the proposed frameworks AEMC PAGE 2

  3. Background to this Rule change request AEMC PAGE 3

  4. Review of Energy Market Frameworks in light of Climate Change Policies: findings • The MCE requested the AEMC conduct a review of energy market frameworks in light of climate change policies • Patterns of generation investment are changing • Existing frameworks require strengthening to manage these changes AEMC PAGE 4

  5. Review of Energy Market Frameworks in light of Climate Change Policies: recommendations ~ • A new framework to promote the efficient connection of clusters of ~ new generation in proximate locations over time: SENEs ~ • Provides a mechanism to allow forward looking network investment Existing for generation connection network ~ • Generators pay an average cost ~ charge for use of the SENE • Requires customers to underwrite ~ the risk of asset stranding SENE hub AEMC PAGE 5

  6. Illustrative examples of opportunities for scale efficiencies Stand alone cost versus shared cost • Magnitude of efficiency gains for first connecting generator depend on : – number and volume of gens 100% 90% – geographical spread of gens 80% – distance from shared network 70% 60% • Example 1 : Coordinating 50% connections for 4 generators over 40% 30% 35km of line would save a total of 20% $12m Citipower/Powercor 10% 0% First gen stand First gen First gen stand First gen • Example 2 : coordinating alone cost shared cost alone cost shared cost connection of 2000 MW of Example 1 Example 2 generation would save the first connecting 500 MW generator $75m Grid Australia AEMC PAGE 6

  7. The SENE Rule change request • MCE endorsed the recommendation and submitted a Rule change request • MCE considered the proposal should promote the NEO by: – overcoming the risk of inefficient asset duplication – ensuring efficient assets are built – minimising risk to consumers AEMC PAGE 7

  8. Consultation on this Rule change to date • 28 submissions, 2 supplementary submissions received on the Consultation Paper • A shift away from more widespread support for SENEs • Still some need for change • Concerns with the proposed Rule: – level of risk imposed on customers – complexity of the proposed Rule – implications for competitive neutrality between generators AEMC PAGE 8

  9. Interaction of this Rule change with the TFR • MCE has directed the AEMC to conduct a review of transmission frameworks • The scope of SENEs and the TFR may overlap • The AEMC has decided to progress the SENEs Rule change independently • However, the scope of the TFR will be a consideration in considering any potential Rule change to accommodate SENEs AEMC PAGE 9

  10. Nature of the problem Issues this Rule change is seeking to address AEMC PAGE 10

  11. Patterns of generation investment are changing • The scale of generation investment is changing • New technologies have different characteristics from past generation investment: – relatively small compared to “lumpy” network investment for connection – some low cost sources of generation are remote from existing networks • New generation may be clustered and seek connection over a period of time AEMC PAGE 11

  12. Connecting new types of generation is challenging • The economies of scale in network investment imply coordinating generation connection will lower total system costs • Achieving efficient connection outcomes is challenging because: – coordination challenges – the temporal nature of the problem – managing the risk of stranded assets • Achieving optimal investment outcomes requires an entity to bear the asset stranding risk AEMC PAGE 12

  13. Connecting new types of generation is challenging • The existing arrangements are unlikely to allow efficient outcomes for new patterns of generation • No entity has an incentive to provide forward looking investment for connections – The existing frameworks do not encourage or reward speculative building of network assets • This may lead to inefficient outcomes, including: – duplication of network assets – delays in connection AEMC PAGE 13

  14. PAGE 14 Objective of SENEs AEMC

  15. The purpose of this Rule change request To allow the efficient connection of multiple generators with multiple owners in proximate areas over time and to charge an efficient price for that service AEMC PAGE 15

  16. Summary of the Rule change request AEMC PAGE 16

  17. The proposed Rule change Trigger for considering a SENE • AEMO to identify possible SENE zones in its annual NTNDP • NSPs to identify credible options in their APR or on their website Investment test • NSPs to consider opportunities for scale efficiencies and, if so, publish: – Planning report – Standard connection offer • Construction of the SENE triggered by connection agreement with at least one generator AEMC PAGE 17

  18. The proposed Rule change Cost allocation and charging methodology • Generators pay an average Annual charge for SENE ($) cost charge for use of the Charges paid Rebates to by generators SENE consumers Charges borne • Customers underwrite any by consumers NSP’s annual remaining costs revenue requirement G1 G2 G3 G4 Time enters enters enters enters The shaded areas will be equal if generation connects as expected AEMC PAGE 18

  19. The proposed Rule change Access provisions • Generators are entitled to compensation where constrained off by another generator Regulatory oversight • AER prepares guidelines • AER has the ability to veto the connection offer • Forecasts to be reviewed by AEMO • A policy review to be undertaken by the AEMC 5 years after commencement AEMC PAGE 19

  20. Challenges in implementing SENEs AEMC PAGE 20

  21. Implementation challenges • The existing connections framework was developed to meet historical requirements • We now seek to allow different types of generation to connect using shared assets • SENEs, as proposed, do not fit naturally within existing frameworks • This creates additional complexity for any SENEs framework AEMC PAGE 21

  22. Implementation challenges – examples from proposed framework • Connection assets are typically funded by generators, but SENEs require initial customer funding to allow forward looking investment • The Rules do not envisage assets that were once funded by customers subsequently being funded by generators • The proposed Rule defines a SENE as being part of the network but it is treated differently from the remainder of the network AEMC PAGE 22

  23. Implementation challenges – a single framework for many different configurations Every SENE is likely to be unique Existing Existing network network ~ ~ ~ ~ ~ ~ SENE hub ~ AEMC PAGE 23

  24. PAGE 24 AEMC

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend