1
Canadian Regulatory Perspective on Safety Challenges for New NPP
- A. Viktorov,
Canadian Nuclear Safety Commission IAEA Technical Meeting June 22-26, 2015
Safety Challenges for New NPP A. Viktorov, Canadian Nuclear Safety - - PowerPoint PPT Presentation
Canadian Regulatory Perspective on Safety Challenges for New NPP A. Viktorov, Canadian Nuclear Safety Commission IAEA Technical Meeting June 22-26, 2015 1 How this presentation works.. 1. CNSC outline 2. Preparation for new build in Canada
1
Canadian Nuclear Safety Commission IAEA Technical Meeting June 22-26, 2015
2
3
4
5
6
– But several specific reactor designs considered
7
Act Regulations Licences, Certificates, Licence Conditions and Orders
Requirements “must meet” Enabling Legislation
Requirements Guidance
8
8
Site preparation under Licence to Prepare Site Construction under Licence to Construct
Operation under Licence to Operate Decommissioning under Licence to Decommission Release from licensing under Licence to Abandon
9
Page - 9
~ 9 years from the initial trigger to the
10
– Tool to determine whether the vendor is ready for potential deployment in Canada – Standardized process – Requires design to be essentially complete
11
– That is, no safety challenges that could not be resolved based on the current knowledge and technology
12
prevention and mitigation
13
13
achieve satisfactory resolution
14
– Reactors are safe to operate – safety challenges are understood
– at least, for the traditional technologies
– Economics – Public acceptance – Regulatory readiness, for novel technologies
15
– Malevolent acts – Cyber security – Counterfeit, fraudulent or suspect items – Digitalization of plant control – Loss of know-how in countries with established programs – Acquiring expertise, in countries starting to develop nuclear energy
16
– Assessment of DiD – Design Extension Conditions – Emergency Mitigating Equipment – Engagement with IAEA
17
18
– Design features to deal with DEC – SAMG – Increased understanding of safety margins in DEC
– Quantification of site specific hazards – PSA
19
– This documents sets requirements for New NPP – Used as guidance in conduct of Periodic Safety Reviews
The concept of defence in depth shall be applied to all organizational, behavioural, and design-related safety and security activities to ensure they are subject to overlapping provisions. The levels of defence in depth shall be independent to the extent practicable.
20
– Logical and comprehensive approach – Very cumbersome in application
21
– The design authority shall identify the set of design-extension conditions (DECs) ... These DECs shall be used to further improve the safety of the NPP by enhancing the plant's capabilities to withstand accidents that are … more severe than DBAs …
22
– Based on the Plant State diagram – next slide
23
24
25
– Includes inspection, testing and maintenance requirements
– Reasonable confidence in functionality of SSC under harsh conditions
26
27
28
– Could be commercial grade
29
– Active Canadian participation – Few notable differences in interpretation of high level requirements
30
31
32
33
Page - 33
– Loop-based, integrated or pool-type LWR – Sodium, lead, gas cooled
– Factory fuelled – Remote operation
34
Page - 34
35
– better understand the state of the art and its safety case – examine public acceptability (i.e. develop a position and plan to show how confidence will be developed) – review existing requirements, codes and standards for applicability – assess whether any additional requirements (i.e., security, human factors, emergency response, etc) needed – understand sensitivity to external hazards
36
– MDEP – SMR regulatory forum – INPRO – Gen IV Forum
37
– Safety is not the biggest challenge
38