Ross-Adams Site Characterization Report and EE/ CA - Update - - PowerPoint PPT Presentation

ross adams site characterization report and ee ca update
SMART_READER_LITE
LIVE PREVIEW

Ross-Adams Site Characterization Report and EE/ CA - Update - - PowerPoint PPT Presentation

Ross-Adams Site Characterization Report and EE/ CA - Update Hydaburg Meeting December 14, 2010 Presentation Overview Why we are here USFS and Newmont/Dawn Settlement Agreement and Consent Order EE/CA process overview Why we


slide-1
SLIDE 1

Ross-Adams Site Characterization Report and EE/ CA - Update

Hydaburg Meeting December 14, 2010

slide-2
SLIDE 2

2

Presentation Overview

 Why we are here  USFS and Newmont/Dawn Settlement

Agreement and Consent Order

 EE/CA process overview  Why we need POW Island opinions

and input

 Open house process  Site Introduction

slide-3
SLIDE 3

3

Why We Are Here

 Newmont/Dawn voluntarily entered into

Administrative Settlement and Order on Consent

 POW Island residents are stakeholders in the Ross-

Adams removal action process

 Last update was Sept. 2009  New information to share:

  • Results of Site Characterization
  • Schedule for completion of draft EE/CA

 Provide details on future activities

slide-4
SLIDE 4

4

The Agreement

 April 2009, Newmont/Dawn entered into an Administrative

Order on Consent with the USDA Forest Service for Ross- Adams

  • To complete:
  • Planning documents
  • Site Investigation
  • Site Characterization Report
  • Engineering Evaluation / Cost Analysis (EE/CA)
  • Human Health and Ecological Risk Assessment
  • Objectives are:
  • Work with the USFS to develop an appropriate remedy with

stakeholder input

  • Complete the EE/CA and Risk Assessment process in a timely

manner

 Agreement does not include clean up

slide-5
SLIDE 5

5

The Tasks Completed So Far

 Planning documents (SAP, QAPP & SSHP)

completed and approved June 5, 2009

 Field Investigation – Completed 3 Phases in 2009

  • # 1 June 8 - 12
  • # 2 July 18 - August 2
  • # 3 September 20 - 26

 Site Characterization Report

  • Draft Report submitted for agency review March 18, 2010
  • Final Report approved by USFS December 2010
slide-6
SLIDE 6

6

EE/ CA Process

EE/CA = Engineering Evaluation and Cost Analysis EE/CA is a process under CERCLA (Superfund) to

develop and evaluate potential removal actions

The Ross-Adams EE/CA will develop and evaluate

removal actions designed to reduce human health and environmental radiologic and chemical hazards

Steps completed so far by USFS and Newmont /

Dawn provide the information needed to design and evaluate removal alternatives

EE/CA process will consist of a Draft EE/CA for

public review and another community meeting

slide-7
SLIDE 7

7

Why we need Community

  • pinions and input

 Evaluation of removal actions (clean up) for the

site will consider community land use and food gathering practices

 Future risk assessment modeling will develop

specific exposure scenarios to represent community land use and food consumption

slide-8
SLIDE 8

8

Open house process

 Information on the Site Characterization and

future steps for the process are presented on the posters positioned throughout the room

 Project experts from the USFS, Newmont / Dawn

and consulting team are here to talk you through the information and answer questions

 Comment cards and comment recorders are

available to document your opinions and comments

 Take your time and ask as many questions as you

would like

slide-9
SLIDE 9

9

Ross-Adams Site Location

slide-10
SLIDE 10

10

Ross-Adams Site

slide-11
SLIDE 11

11

Bokan Mountain Radiometrics

slide-12
SLIDE 12

12

Ross-Adams Site

slide-13
SLIDE 13

13

slide-14
SLIDE 14

14