Roslindale Gateway Path 25% Concept Design

July 25, 2018

slide-2
SLIDE 2
  • A safer connection for cyclists and

pedestrians from Roslindale Village to the Arboretum

  • A link for underserved portions of

Roslindale to the Arboretum and the Village

  • A connection to the Blackwell

Path Extension (and the Southwest Corridor)

Project Goals

slide-3
SLIDE 3

10% Design

2015 2016

HW completes 10% design

  • f Blackwell Path Extension

HW conducts site walks with WalkUP Roslindale, LivableStreets and the Arboretum

2017

Public Meeting HW completes 10% design of Roslindale Gateway Path HW conducts site walk with APC Public Site Walk

slide-4
SLIDE 4

Draft Design Kick-Off Meeting Survey Final Design Public Meeting

Oct 2017 2018

Stakeholder Meeting Public Meeting (MBTA Portion)

25% Design

slide-5
SLIDE 5
  • 25% design of entire path
  • Limited survey of the Arboretum
  • Preliminary grading of alignment
  • Identify gateways and secondary

connections

  • Identify preferred materials
  • Review options for site amenities
  • Evaluate planning-level construction

costs

  • Develop graphics showing path

perspectives

Scope of Project

slide-6
SLIDE 6

Primary Path

Roslindale Village Arboretum Blackwell Path to Forest Hills Station MBTA parcel

slide-7
SLIDE 7

MBTA Section

slide-8
SLIDE 8

MBTA Section - Grades

slide-9
SLIDE 9

MBTA Section - Photos

slide-10
SLIDE 10

Primary Gateway

Bussey Brook Meadow Gate

slide-11
SLIDE 11

Secondary Gateway

Unnamed Gate on Arborough Street Unnamed Gate on Walter Street

slide-12
SLIDE 12

Path Materials

Stabilized Soil Ipe Boardwalk

slide-13
SLIDE 13

Safety

In-grade textured surfacing Pavement markings and reflectors Vegetated, defined edge

slide-14
SLIDE 14

Path Rendering

slide-15
SLIDE 15

Next Steps

  • Complete the 25%

conceptual design for MBTA section

  • Prepare estimates of

probable costs for MBTA section

  • Continue to work with

stakeholders on the remaining sections of the path

slide-16
SLIDE 16

Jennifer Relstab, P.E.