Riverfront Park Redevelopment Update Leroy Eadie, Parks & - - PowerPoint PPT Presentation

riverfront park redevelopment update
SMART_READER_LITE
LIVE PREVIEW

Riverfront Park Redevelopment Update Leroy Eadie, Parks & - - PowerPoint PPT Presentation

Riverfront Park Redevelopment Update Leroy Eadie, Parks & Recreation Director Garrett Jones, Parks Planning Manager Berry Ellison, Program Manager Jo-Lynn Brown, Program Coordinator Jon Moog, RFP Director Fianna Dickson, Communications


slide-1
SLIDE 1

Riverfront Park Redevelopment Update

Leroy Eadie, Parks & Recreation Director Garrett Jones, Parks Planning Manager Berry Ellison, Program Manager Jo-Lynn Brown, Program Coordinator Jon Moog, RFP Director Fianna Dickson, Communications Manager

slide-2
SLIDE 2

Building on the Master Plan

Voters approved a $64 million bond for redevelopment that didn’t raise taxes

slide-3
SLIDE 3

Overview

The 5 bond projects

slide-4
SLIDE 4

Red Wagon Meadow

Improved trail with ADA access through the Red Wagon Meadow. Completed in time for Bloomsday.

slide-5
SLIDE 5

Howard Street Bridge South

The first phase of the Promenade

Crews worked hard through cold winter to remove the bridge. The first span was placed mid- April, second span early May. Pier 4 has a deeper riverbed than topographic data showed. Redesigned Pier 4. Timeline: Fall 2017

slide-6
SLIDE 6

Howard Street Bridge South

slide-7
SLIDE 7

Rotary Fountain

Fountain needs significant plumbing and electrical repairs. Est. $950,000 The cost to convert it into a splash pad is nearly equal. Ideal time to repair given construction around south bank. The above-ground fountain will not change.

slide-8
SLIDE 8

Recreational Ice Ribbon and SkyRide

Foundation for building in place, and ice ribbon pathway is visible. Construction: Fall 2017

slide-9
SLIDE 9

Recreational Ice Ribbon and SkyRide

slide-10
SLIDE 10

Looff Carrousel

Columns erected early May. Horses undergoing restoration. Construction: Spring 2018

slide-11
SLIDE 11

Looff Carrousel

slide-12
SLIDE 12

Programming the South Bank

Transition Plan Action

2017 2018

& Beyond

slide-13
SLIDE 13

Programming the South Bank

slide-14
SLIDE 14

Regional Playground

Currently at 30% design Estimated construction start: Spring 2018

slide-15
SLIDE 15

U.S. Pavilion

State approved Progressive Design Build for Pavilion, a multi-use space. Design Build team Garco/NAC/Berger Partnership selected in March through Request for Qualifications/Proposals. 120-day design planning phase. July 10 sharing preliminary designs. Selective demolition begins Fall 2017. Construction: thru 2019

slide-16
SLIDE 16

West Havermale Island & Power Play

West Havermale at 30% design development.

slide-17
SLIDE 17

Promenades

Berger is at 60% design on the Promenades. Images of central promenade on Havermale Island.

slide-18
SLIDE 18

Promenades

North Bank entrance

slide-19
SLIDE 19

Renaming Canada Island

Spokane Tribe proposed two names: snxʷ meneʔ (Sin-HOO-men-huh) Salmon people nkʷn̓ntew ̓ s (N-coo-en-tehws) Land that causes a fork in the river snxʷ meneʔ received nearly 60% of the public vote, and unanimous selection by the Park Board.

slide-20
SLIDE 20

Lead Artist

Public Art: Arts Committee recommended & Park Board approved Meejin Yoon as Lead Artist. Art Plan in development, initial draft planned for early summer.

slide-21
SLIDE 21

Pathways During Construction

slide-22
SLIDE 22

Timeline

Recreational Ice Ribbon & SkyRide Facility Early 2017 – Fall 2017 Looff Carrousel Early 2017 – Spring 2018 Regional Playground Spring 2018 – Summer 2019 U.S. Pavilion Spring 2018 – Winter 2019 Promenades Summer 2016 – Winter 2019

slide-23
SLIDE 23

Working Budget

Project Budget

Ice Ribbon and SkyRide Facility $ 9,434,916 Looff Carrousel $ 10,195,833 Howard Street Bridge South $ 7,216,139 North Promenade $ 2,655,763 West Havermale Island $ 4,650,113 U.S. Pavilion $19,662,236 snxʷ meneʔ (formerly Canada Island)* $ 10,268 Regional Playground / North Bank $ 5,629,772 Red Wagon Meadow / South Bank East* $ 158,782 Program Level Owner Costs $ 6,311,178

Total $65,925,000

Includes total bond amount of $64.3m plus $1,625,000 interest earned

*Not one of the 5 promised bond projects Updated: April 13, 2017

slide-24
SLIDE 24

Questions & Comments?