riverfront park redevelopment update building on the
play

Riverfront Park Redevelopment Update Building on the Master Plan - PowerPoint PPT Presentation

Riverfront Park Redevelopment Update Building on the Master Plan Voters approved a $64 million bond for redevelopment that didnt raise taxes Overview The 5 bond projects View from Above Red Wagon Meadow Improved trail with ADA access


  1. Riverfront Park Redevelopment Update

  2. Building on the Master Plan Voters approved a $64 million bond for redevelopment that didn’t raise taxes

  3. Overview The 5 bond projects

  4. View from Above

  5. Red Wagon Meadow Improved trail with ADA access through the Red Wagon Meadow. Completed in time for Bloomsday.

  6. Howard Street Bridge South The first phase of the Promenades Deck poured in two sets. Completed first layer of pour in August. Timeline: Spring 2018

  7. Howard Street Bridge South

  8. Rotary Fountain Fountain needs significant plumbing and electrical repairs. Est. $950,000 The cost to convert it into a splash pad is nearly equal. Ideal time to repair given construction around south bank. The above-ground fountain will not change.

  9. Recreational Ice Ribbon and SkyRide Ice ribbon pathway is completely poured. Shared SkyRide and Ribbon ticketing facility and concessions under construction. Fall 2017

  10. Recreational Ice Ribbon and SkyRide

  11. Looff Carrousel Construction: Spring 2018 Upper: design image. Lower: Photo taken late August 2017.

  12. Looff Carrousel

  13. Programming the South Bank

  14. Regional Playground Currently at 30% design Construction: 2019

  15. Pavilion Garco/NAC/Berger team in design validation phase until mid-October. Focusing on illumination, shade/shelter, and elevation – all with an emphasis on connecting to the river. Added $2.5M to restore Master Plan budget of $24M. Next Open House: October 3 for revised preliminary concepts. Early demolition could begin this fall.

  16. West Havermale Island & Power Play West Havermale at 30% design development.

  17. Promenades 90% design on the Promenades. Images of central promenade on Havermale Island.

  18. Promenades North Bank entrance

  19. Lead Artist Public Art: Arts Committee recommended & Park Board approved Meejin Yoon as Lead Artist. Art Plan in development, initial draft will be shared at an Open House this fall.

  20. Pathways During Construction

  21. Timeline Recreational Ice Ribbon & SkyRide Facility Early 2017 – Fall 2017 Looff Carrousel Early 2017 – Spring 2018 Regional Playground 2019 U.S. Pavilion Fall 2017– Winter 2019 Promenades Summer 2016 – Winter 2019

  22. Working Budget Project Budget Ice Ribbon and SkyRide Facility $ 9,434,916 Looff Carrousel $ 10,195,833 Howard Street Bridge South $ 7,216,139 North Promenade $ 2,655,763 West Havermale Island $ 4,650,113 U.S. Pavilion $22,162,236 snxʷ meneʔ (formerly Canada Island)* $ 10,268 Regional Playground / North Bank $ 5,629,772 Red Wagon Meadow / South Bank East* $ 158,782 Program Level Owner Costs $ 5,634,543 Total $71,169,183 *Not one of the 5 promised bond projects Includes total bond amount of $64.3m plus Updated: August 10, 2017 anticipated earned interest, grants, and utility reimbursements

  23. Questions & Comments?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend