Riverfront Park Redevelopment Update

slide-2
SLIDE 2

Building on the Master Plan

Voters approved a $64 million bond for redevelopment that didn’t raise taxes

slide-3
SLIDE 3

Overview

The 5 bond projects

slide-4
SLIDE 4

View from Above

slide-5
SLIDE 5

Red Wagon Meadow

Improved trail with ADA access through the Red Wagon Meadow. Completed in time for Bloomsday.

slide-6
SLIDE 6

Howard Street Bridge South

The first phase of the Promenades

Deck poured in two sets. Completed first layer of pour in August. Timeline: Spring 2018

slide-7
SLIDE 7

Howard Street Bridge South

slide-8
SLIDE 8

Rotary Fountain

Fountain needs significant plumbing and electrical repairs. Est. $950,000 The cost to convert it into a splash pad is nearly equal. Ideal time to repair given construction around south bank. The above-ground fountain will not change.

slide-9
SLIDE 9

Recreational Ice Ribbon and SkyRide

Ice ribbon pathway is completely poured. Shared SkyRide and Ribbon ticketing facility and concessions under construction. Fall 2017

slide-10
SLIDE 10

Recreational Ice Ribbon and SkyRide

slide-11
SLIDE 11

Looff Carrousel

Construction: Spring 2018

Upper: design image. Lower: Photo taken late August 2017.

slide-12
SLIDE 12

Looff Carrousel

slide-13
SLIDE 13

Programming the South Bank

slide-14
SLIDE 14

Regional Playground

Currently at 30% design Construction: 2019

slide-15
SLIDE 15

Pavilion

Garco/NAC/Berger team in design validation phase until mid-October. Focusing on illumination, shade/shelter, and elevation – all with an emphasis

  • n connecting to the river.

Added $2.5M to restore Master Plan budget of $24M. Next Open House: October 3 for revised preliminary concepts. Early demolition could begin this fall.

slide-16
SLIDE 16

West Havermale Island & Power Play

West Havermale at 30% design development.

slide-17
SLIDE 17

Promenades

90% design on the Promenades. Images of central promenade on Havermale Island.

slide-18
SLIDE 18

Promenades

North Bank entrance

slide-19
SLIDE 19

Lead Artist

Public Art: Arts Committee recommended & Park Board approved Meejin Yoon as Lead Artist. Art Plan in development, initial draft will be shared at an Open House this fall.

slide-20
SLIDE 20

Pathways During Construction

slide-21
SLIDE 21

Timeline

Recreational Ice Ribbon & SkyRide Facility Early 2017 – Fall 2017 Looff Carrousel Early 2017 – Spring 2018 Regional Playground 2019 U.S. Pavilion Fall 2017– Winter 2019 Promenades Summer 2016 – Winter 2019

slide-22
SLIDE 22

Working Budget

Project Budget

Ice Ribbon and SkyRide Facility $ 9,434,916 Looff Carrousel $ 10,195,833 Howard Street Bridge South $ 7,216,139 North Promenade $ 2,655,763 West Havermale Island $ 4,650,113 U.S. Pavilion $22,162,236 snxʷ meneʔ (formerly Canada Island)* $ 10,268 Regional Playground / North Bank $ 5,629,772 Red Wagon Meadow / South Bank East* $ 158,782 Program Level Owner Costs $ 5,634,543

Total $71,169,183

Includes total bond amount of $64.3m plus anticipated earned interest, grants, and utility reimbursements

*Not one of the 5 promised bond projects Updated: August 10, 2017

slide-23
SLIDE 23

Questions & Comments?