Risk Management in Major Regeneration Projects October 2012 Risk - - PowerPoint PPT Presentation

risk management in major regeneration projects
SMART_READER_LITE
LIVE PREVIEW

Risk Management in Major Regeneration Projects October 2012 Risk - - PowerPoint PPT Presentation

Risk Management in Major Regeneration Projects October 2012 Risk Management October 2012 Introduction Regeneration are responsible for the delivery of a range of major programmes: Elephant And Castle Aylesbury Canada Water


slide-1
SLIDE 1

Risk Management in Major Regeneration Projects

October 2012

Risk Management October 2012

slide-2
SLIDE 2

Introduction

  • Regeneration are responsible for the

delivery of a range of major programmes:

– Elephant And Castle – Aylesbury – Canada Water – Bermondsey Spa – Southwark Schools for the Future

as well as various capital investment projects for other departments.

Risk Management October 2012

slide-3
SLIDE 3

Risk Management Framework

Risk identification, assessment, strategic mitigation and monitoring and reporting is integral to the project management of these projects and programmes. The basic tool for this is the risk log using the council’s standard format.

Risk Management October 2012

slide-4
SLIDE 4

Process

  • At project or programme inception a workshop is held

with a range of project stakeholders to capture potential risks, likelihood, impact and approaches to mitigation and the appropriate risk owner

  • A risk log is prepared by the project manager and issued

to relevant parties.

  • Risks are reviewed at regular intervals linked to key

project meetings, reviewing status, mitigation and any new risks arising.

  • Following key project gateways, workshops are held to

ensure the risk log is refreshed and updated.

Risk Management October 2012

slide-5
SLIDE 5

Risk Monitoring and reporting

Corporate Governance - Individual project risk logs are reviewed by Project Directors on a monthly basis to inform programme risk logs which in turn are reviewed by Regeneration SMT on a quarterly basis. The departmental risk log informs the corporate risk log which is considered by the Audit and Governance Committee. Project/Programme Governance – Project/Programme Risks are reviewed at project team meetings and subsequently at project and programme board meetings. Exception – By exception significant risks are escalated as required to ensure that senior stakeholders are aware of issues rather than waiting for regular reporting intervals.

Risk Management October 2012

slide-6
SLIDE 6

Example - Elephant and Castle

St Marys Leisure Centre Phase 1A Demolition Masterplan

Project Level Programme Level

Elephant and Castle Programme Regeneration

Departmental Level

Corporate Risk Log

Corporate Level Risk Management October 2012

slide-7
SLIDE 7

Affordable Housing

  • Key objective of the E&C regeneration

programme is to deliver 1400 affordable homes as required in the adopted E&C SPD by 2026

  • 25% minimum affordable requirements

within the Lend Lease Regeneration Agreement applying only to Heygate site

  • Delivery of requirement to be profiled over a

15 year period.

Risk Management October 2012

slide-8
SLIDE 8

Risks affecting delivery

Main risk areas affecting delivery of target:

  • Delay/failure to get planning permission to deliver

housing schemes incorporating affordable homes (as a result of non-compliance or objection)

  • Non-financial viability of private developments mean that

S106 affordable housing provision fails to meet required 35% target figure and in turn the 1400 unit figure not achieved within 2011-2026 period.

  • No housing grant increases risk that Lend Lease are

unable to achieve minimum 25% as per Regeneration Agreement.

Risk Management October 2012