SLIDE 1 Right of Entry for Environmental and Technical Investigations in Project Development
Why & How
David Brown-ODOT
SLIDE 2
SLIDE 3 Purpose
The purpose of this procedure is to establish accountabilities, roles, responsibilities for
- btaining a temporary Right of Entry (ROE)
from a property owner for various environmental and technical investigations as a part of the project development process.
SLIDE 4
Background
ROE are used to gain access to private & public property. Compensation is not offered. ODOT may be held responsible for damages caused by the investigations.
SLIDE 5 Background
Most property owners will and have allowed entry.
- Dept. of Justice will assist ODOT when owners
decline entry or are non-responsive. ODOT team members may be required to testify in a court hearing.
SLIDE 6
Scope & Statute
The requirements and guidelines of this procedure apply to all projects and assignments that involve the need to enter private and/or public property to perform environmental or technical investigations . All work is done in compliance with ORS 35.220.
SLIDE 7
Accountabilities
The Region Project Leader (PL) ensures the team members perform on schedule. The Region Environmental Coordinator (REC) coordinates most of the requests, and works with each of the Technical Specialists (TECH).
SLIDE 8 Accountabilities
The REC & each TECH comply with all conditions of the Right of Entry, including providing notice prior to entry onto the property. The Senior Right of Way Agent (ROW) coordinates with the Technical Specialists and Regional Environmental Coordinator in drafting the ROE, for example the wording of what type
- f investigation and how it is performed.
SLIDE 9 Accountabilities
The Senior Right of Way Agent (ROW) prepares, mails, tracks the ROE. ROW communicates with the property owners. 24-hr notice must be given to the property
- wner prior to entry, usually by the TECH or
REC..
SLIDE 10
Roles & Responsibilities
The PL is a facilitator. Ensures that team members needing to enter the property perform & stay on schedule. The REC role is to manage dates and people involved in the investigations.
SLIDE 11
Roles & Responsibilities
The REC and or TECH will obtain the following: Identify the properties that need ROE and the Technical Specialists needed to perform the investigations. A description of the work to be done. The boundaries of the work area. Schedule for the work/investigations to take place.
SLIDE 12 Roles & Responsibilities
The REC forwards this information to ROW. ROW provides the following: Prepares the Right of Entry for each property
SLIDE 13
Roles & Responsibilities
Mails the ROE to property owners via certified mail, return receipt requested. Makes follow-up contact as needed & tracks comments. Provides signed copies of ROE to team members, which they should carry with them when performing the investigation.
SLIDE 14 Roles & Responsibilities
ROW Advises team members if ROE can not be
60 day window for obtaining ROE. If ROE refused or non responsive owner, ROW requests written justification for investigation from Technical Specialist. Justification submitted to
- DOJ. DOJ obtains court order for entry.
SLIDE 15
Modified Method-USFS/BLM
Team member notifies USFS/BLM verbally or via e-mail. If verbal, write e-mail documenting permission to do non-invasive work in lieu of ROE.
SLIDE 16
Right of Entry Form
SLIDE 17
The Right of Entry Form
SLIDE 18
Archaeology - Culturally Modified (Peeled) Trees
SLIDE 19
Archaeology - Rock Cairns
SLIDE 20
Archaeology - Lithic Scatter
SLIDE 21
Archaeology - Rock Art
SLIDE 22
Historic Resources/Artifacts
SLIDE 23
Hazardous Materials
SLIDE 24
Wetlands
SLIDE 25 Rare Plants
Pumice Grape-fern Peck’s Milkvetch Tygh Valley Milkvetch
SLIDE 26
Tree Art
SLIDE 27
Petroglyph
SLIDE 28
Hart Mountain
SLIDE 29
SLIDE 30
Small Rock Circle
SLIDE 31
Large Rock Ring
SLIDE 32
Petroglyph
SLIDE 33
Tree Pamphleteering
SLIDE 34
Arborglyph