City of York Council Review of the Housing for Older People Project Presentation to Audit and Governance Committee 29 July 2015 Introduction CYC embarked on a programme of work for the re-provision of accommodation for older people in


  1. City of York Council Review of the Housing for Older People Project Presentation to Audit and Governance Committee 29 July 2015

  2. Introduction � CYC embarked on a programme of work for the re-provision of accommodation for older people in July 2011 � This involved plans for new residential care facilities and a Care Village – a relatively new and innovative concept to provide greater choice to the older people of York � A comprehensive public consultation supported the proposals � The planned timescale for delivery of the programme slipped considerably due to a series of complex challenges relating to: - - site suitability; site suitability; - design and specification; and - affordability. � This led to the termination in March 2015 of a protracted competitive dialogue process � An alternative solution is now being implemented to meet the City’s needs � In February 2015, the Chief Executive commissioned an independent review of programme management and governance to identify lessons to be learned and recommendations for future major change programmes � The review was completed in June 2015.

  3. Scope of Work � Strategic context and fit Programme � Risk assessment Initiation � Initial scrutiny � Consultation and engagement � Outline business case Programme � Programme governance and communication Governance � Affordability risk � Wider linkages � Programme management arrangements Programme � Risk management Management and � Resourcing and capacity Resourcing � Project costs � Programme management arrangements Procurement � Risk management Process � Resourcing and capacity � Learning for revised modernisation programme Approach to alternative � Programme management and governance solution

  4. Key Findings – Areas of Good Practice � There was a comprehensive and well managed public consultation with positive feedback from external stakeholders � A wider reference group was set up for ongoing engagement with external stakeholders � Successful transition of residents and staff following closure of 2 homes in March 2012, independently assessed as meeting best practice � Some elements of good project management at work-stream level, for example disciplined reporting to Programme Board, debate of risks and actions required � A well run procurement process despite significant affordability challenges and reducing market appetite � Considerable commitment and diligence from project team to explore ways to address challenges and find an affordable solution

  5. Key Findings – Areas for Improvement and Learning Issue Recommendations CYC Response � A disciplined business case � CYC have invested in a 1. Business Case process should be adhered to programme management The business case for the investment ensure all options generated, system, Verto. evolved over a period of time in a appraised and risks evaluated at an � This has the functionality fragmented way. early stage . to support this disciplined It was difficult to evidence that all options � The Treasury Green Book approach approach. were considered and risks mitigated. is recommended as best practice. � Risk registers should be � Verto provides the 2. Programme Governance and Communication Communication maintained by work-stream to feed maintained by work-stream to feed disciplined approach disciplined approach a project risk log. required for effective risk Governance arrangements over risk were management and � A risk assurance framework inconsistent. escalation. approach is recommended for Significant risks were not systematically � CYC are considering a Risk escalation to CMT and Cabinet. escalated to Corporate Management Team Controller role. � CYC officers and Members to and Cabinet. � Major programmes are examine options for creating an Governance arrangements failed due to appropriate governance now managed under CYC’s the perceived risk to the Council of framework to allow debate of Transformation Board. disclosing the commercial sensitivities of significant commercial risks. the programme in a public domain. � Developments in other sectors There was limited consideration of the should be fully considered as part wider strategic developments in Adult of options appraisal. Social Care, Housing and the Health sector.

  6. Key Findings – Areas for Improvement and Learning Issue Recommendations CYC Response � There should be a greater focus on � A financial model is 3. Financial Evaluation challenging the economic, under development for Issues raised relating to affordability at operational and financial the new programme. earlier stages of the project should have assumptions as part of the early � CYC recognise the need alerted CYC to the need for more rigorous phase of business case financial scrutiny. to invest in specialist development. skills to ensure this is robust and flexible. � Major projects should be supported � CYC have taken steps to 4. Programme Management by comprehensive, best practice by comprehensive, best practice address through the address through the There were some weaknesses in There were some weaknesses in programme management implementation of Verto. arrangements, for example project arrangements. planning, roles and resourcing and risk escalation. � Appropriately skilled support on � CYC has recognised the 5. Procurement Process complex procurements is necessary need for contingency CYC officers involved had limited to allow fuller consideration of planning and enhanced experience in competitive dialogue and commercial implications, for procurement expertise. associated commercial issues. example the impact of market � CYC is examining ways to A contingency plan was not considered in failure and contingency planning. address commercial skills advance of the formal procurement phase gaps. on which the outcome of the project was critically dependent.

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.