RESERVOIR SEPTEMBER 2020 PROJECT OBJECTIVES A NEW RESERVOIR IS - - PowerPoint PPT Presentation

reservoir
SMART_READER_LITE
LIVE PREVIEW

RESERVOIR SEPTEMBER 2020 PROJECT OBJECTIVES A NEW RESERVOIR IS - - PowerPoint PPT Presentation

HIGH SYSTEM RESERVOIR SEPTEMBER 2020 PROJECT OBJECTIVES A NEW RESERVOIR IS NEEDED IN THE HIGH SYSTEM PRESSURE ZONE: TO INCREASE SYSTEM RELIABILITY FIRE FLOW & PEAK DEMAND SUPPLY DURING THE SUMMER TO MEET WASHINGTON STATE


slide-1
SLIDE 1

HIGH SYSTEM RESERVOIR

SEPTEMBER 2020

slide-2
SLIDE 2

PROJECT OBJECTIVES

A NEW RESERVOIR IS NEEDED IN THE HIGH SYSTEM PRESSURE ZONE:

  • TO INCREASE SYSTEM RELIABILITY – FIRE FLOW

& PEAK DEMAND SUPPLY DURING THE SUMMER

  • TO MEET WASHINGTON STATE DEPARTMENT

OF HEALTH REQUIREMENTS (WSP)

  • AFFECTS ALL CITY WATER CUSTOMERS SOUTH

OF 14TH AVE.

slide-3
SLIDE 3

HIGH SYSTEM PRESSURE ZONE

29th Ave 33rd Ave Ray Street Manito Blvd 17th Ave Freya Street Bernard Street

DOWNTOWN LOWER S. HILL MID S. HILL (HIGH SYSTEM) UPPER S. HILL

slide-4
SLIDE 4

CURRENT RESERVOIRS IN THE HIGH SYSTEM PRESSURE ZONE

33rd & Lamonte near Sacajawea Garden Park at 37th Avenue near Stone Street

slide-5
SLIDE 5

WATER SYSTEM BASICS

Low Pressure Zone

Water is pumped to successively higher reservoirs

Top System High System Intermediate Glennaire Southview Pumping Wells Downtown Lower South Hill Mid South Hill Upper South Hill

Lower Browne’s Mtn

Upper Browne’s Mtn

slide-6
SLIDE 6

LOCATION SELECTION CRITERIA

  • VACANT LAND (MIN 1 AC, IDEALLY 2 AC) AND

IDEALLY CITY OWNED

  • CLOSE TO TRANSMISSION MAINS – WITHIN 5

OR 6 BLOCKS

  • NEAR THE CENTER OF THE PRESSURE ZONE
  • ELEVATION OF APPROX. 2380’ OR HIGHER TO

KEEP RESERVOIR HEIGHT TO 100’ OR LESS

  • RELATIVELY FLAT
  • MAXIMIZE DISTANCE TO ADJACENT HOMES
slide-7
SLIDE 7

LOCATION SELECTION

Near center of pressure zone

slide-8
SLIDE 8

LOCATION SELECTION

Near center of pressure zone Close to transmission main

slide-9
SLIDE 9

LOCATION SELECTION

Near center of pressure zone Close to transmission main Above about 2380 Note: land slopes downhill north of 29th Ave and is therefore too low for a tank.

slide-10
SLIDE 10

LOCATION SELECTION

Near center of pressure zone Close to transmission main Above about 2380 Meets all three criteria

slide-11
SLIDE 11

LOCATION SELECTION

  • Feasible area outlined green below
  • Feasible tank site must be:
  • Vacant and at least 1-2 acres
  • Relatively flat
  • Ideally city owned

29th Ave. Cook St Arthur St 29th Ave.

slide-12
SLIDE 12

29th Ave. Thurston Ave. Arthur St. Cook St. This is the feasible area circled green on the preceding exhibit

slide-13
SLIDE 13

29th Ave. Thurston Ave. Arthur St. Cook St. Feasible site within this area needs to be:

  • 1-2 acres
slide-14
SLIDE 14

29th Ave. Thurston Ave. Arthur St. Cook St. Hamblen Elem Hamblen Park

Our Lady Of Fatima 31st & Napa SE Blvd

Garden Park Tank Feasible site within this area needs to be:

  • 1-2 acres
slide-15
SLIDE 15

29th Ave. Thurston Ave. Arthur St. Cook St. Hamblen Elem Hamblen Park Garden Park Tank

Our Lady Of Fatima 31st & Napa SE Blvd

Criteria to evaluate Close to existing t-main? Nr center of pressure zone? At or above 2380’? Vacant land min 1 ac? Relatively flat? City owned? Distant from nearby homes?

slide-16
SLIDE 16

29th Ave. Thurston Ave. Arthur St. Cook St.

Our Lady Of Fatima

Criteria Met Close to existing t-main yes Nr center of pressure zone yes At or above 2380 yes Vacant land min 1 ac barely Relatively flat yes City owned no Distant from nearby homes no Other: tank would be large impact to this small area, no guarantee it could be acquired, very close to adjacent homes

slide-17
SLIDE 17

29th Ave. Thurston Ave. Arthur St. Cook St.

SE Blvd

Criteria Met Close to existing t-main yes Nr center of pressure zone yes At or above 2380 yes Vacant land min 1 ac yes Relatively flat no City owned no Distant from nearby homes no Other: steeply sloped small property would result in high construction costs, substantial rock removal, this property likely is best used as commercial, no guarantee it could be acquired

slide-18
SLIDE 18

29th Ave. Thurston Ave. Arthur St. Cook St.

31st & Napa

Criteria Met Close to existing t-main yes Nr center of pressure zone yes At or above 2380 yes Vacant land min 1 ac barely Relatively flat no City owned yes Distant from nearby homes no Other: steeply sloped small parcel would result in high construction costs, substantial rock removal, most highly visible alternative, very close to adjacent homes

slide-19
SLIDE 19

29th Ave. Thurston Ave. Arthur St. Cook St. Garden Park Tank Criteria Met Close to existing t-main yes Nr center of pressure zone yes At or above 2380 yes Vacant land min 1 ac no Relatively flat no City owned yes Distant from nearby homes no Other: due to small area, questionable construction feasibility, very close to adjacent homes

slide-20
SLIDE 20

29th Ave. Thurston Ave. Arthur St. Cook St. Hamblen Elem Criteria Met Close to existing t-main yes Nr center of pressure zone yes At or above 2380 yes Vacant land min 1 ac yes Relatively flat yes City owned no Distant from nearby homes yes Other: school district not supportive of this idea

slide-21
SLIDE 21

LOCATION SELECTION

29th Ave. Cook St Arthur St

ADDITIONAL SITES CONSIDERED OUTSIDE DESIRED AREA Ferris HS

  • Relatively flat
  • Far from t-main – 3,500 add’l feet
  • 30’ lower results in 130’ tank height
  • Minimal available land, not city owned
  • Not near center of zone
  • Adds at least 50% to project cost
slide-22
SLIDE 22

LOCATION SELECTION

29th Ave. Cook St Arthur St

ADDITIONAL SITES CONSIDERED OUTSIDE DESIRED AREA Hazel’s Creek

  • City owned, relatively flat, plenty of area
  • Far from t-main – 4,000 add’l feet
  • 50’ lower results in 150’ tank height
  • Not near center of zone
  • Adds at least 50% to project cost
slide-23
SLIDE 23

LOCATION SELECTION

ADDITIONAL SITES CONSIDERED OUTSIDE DESIRED AREA South Complex/KXLY

  • City owned, relatively flat, plenty of area
  • Far from t-main – 5,000 add’l feet
  • 40’ lower results in 140’ tank height
  • Not near center of zone
  • Adds at least 50% to project cost

29th Ave. Cook St Arthur St

slide-24
SLIDE 24

LOCATION SELECTION

ADDITIONAL SITES CONSIDERED OUTSIDE DESIRED AREA Thorton Murhpy Park

  • City owned, relatively flat, plenty of area,
  • n t-main route
  • 100’ lower results in 200’ tank height
  • Not feasible

29th Ave. Cook St Arthur St

slide-25
SLIDE 25

LOCATION SELECTION

ADDITIONAL SITES CONSIDERED OUTSIDE DESIRED AREA Lincoln Park

  • City owned, relatively flat, plenty of area,

roughly the same elevation as Hamblen Park

  • Far from t-main – 4,000 add’l feet
  • Adds at least 50% to project cost

29th Ave. Cook St Arthur St

slide-26
SLIDE 26

29th Ave. Thurston Ave. Arthur St. Cook St. Hamblen Park Criteria Met Close to existing t-main yes Nr center of pressure zone yes At or above 2380 yes Vacant land min 1 ac yes Relatively flat yes City owned yes Distant from nearby homes yes Other: only site to meet all criteria

slide-27
SLIDE 27
slide-28
SLIDE 28
slide-29
SLIDE 29

RESERVOIR DIMENSIONS

  • APPROX. 100’ TALL (AT HAMBLEN PARK – VARIES

IN OTHER LOCATIONS)

  • APPROX. 2 MILLION GALLON CAPACITY
  • 50’-60’ DIAMETER AT ITS BASE (I.E., PEDESTAL

DIAMETER)

  • 100’ TANK DIAMETER (I.E., TOP DIAMETER)
slide-30
SLIDE 30

HAMBLEN PARK

HAMBLEN ELEMENTARY 37TH AVE. 625’ CRESTLINE ST. NAPA ST. 625’

slide-31
SLIDE 31

HAMBLEN PARK

HAMBLEN ELEMENTARY 37TH AVE. 625’ CRESTLINE ST. NAPA ST. 625’ PARK AREA = 9 AC TANK FOOTPRINT = 0.08 AC <1% OF PARK AREA

slide-32
SLIDE 32

HAMBLEN PARK

HAMBLEN ELEMENTARY 37TH AVE. 625’ CRESTLINE ST. NAPA ST. 325’ 200’ Undisturbed tree buffer To nearest home

slide-33
SLIDE 33
slide-34
SLIDE 34
slide-35
SLIDE 35
slide-36
SLIDE 36

AVAILABLE RESERVOIR TYPES

Hydropillar Standpipe Water spheroid

slide-37
SLIDE 37

POST FALLS, ID

slide-38
SLIDE 38

MITIGATION MEASURES IF TANK IS LOCATED IN HAMBLEN PARK

  • START WITH HAMBLEN PARK, POSSIBLY

INCLUDE OTHER PARKS

  • THREE PARKS IN SOUTHGATE

NEIGHBORHOOD – HAMBLEN, SOUTH COMPLEX, BEN BURR

  • ACQUISITION OF CONSERVATION LAND
slide-39
SLIDE 39

PROJECT SCHEDULE & NEXT STEPS

✓PRESENT PROJECT TO SOUTHGATE AND LINCOLN HEIGHTS NEIGHBORHOOD MEETINGS ✓HOLD COMMUNITY MEETING ADVERTISED TO ALL RESIDENTS WITHIN A SEVERAL BLOCK RADIUS (MID SEPTEMBER)

slide-40
SLIDE 40

PROJECT SCHEDULE & NEXT STEPS

✓PRESENT PROJECT TO SOUTHGATE AND LINCOLN HEIGHTS NEIGHBORHOOD MEETINGS ✓HOLD COMMUNITY MEETING ADVERTISED TO ALL RESIDENTS WITHIN A SEVERAL BLOCK RADIUS (MID SEPTEMBER)

  • EVALUATE & INCORPORATE COMMUNITY INPUT & SURVEY

RESULTS (FALL 2020)

  • SELECT TANK SITE AND BEGIN PERMITTING (WINTER 2020)
slide-41
SLIDE 41

PROJECT SCHEDULE & NEXT STEPS

✓PRESENT PROJECT TO SOUTHGATE AND LINCOLN HEIGHTS NEIGHBORHOOD MEETINGS ✓HOLD COMMUNITY MEETING ADVERTISED TO ALL RESIDENTS WITHIN A SEVERAL BLOCK RADIUS (MID SEPTEMBER)

  • EVALUATE & INCORPORATE COMMUNITY INPUT & SURVEY

RESULTS (FALL 2020)

  • SELECT TANK SITE AND BEGIN PERMITTING (WINTER 2020)
  • ANOTHER PUBLIC MEETING (ASSOCIATED WITH PERMITTING,

WINTER 2020/21)

  • INCORPORATE ADD’L COMMUNITY INPUT, FINALIZE

PERMITTING (WINTER 2020/21)

slide-42
SLIDE 42

PROJECT SCHEDULE & NEXT STEPS

✓PRESENT PROJECT TO SOUTHGATE AND LINCOLN HEIGHTS NEIGHBORHOOD MEETINGS ✓HOLD COMMUNITY MEETING ADVERTISED TO ALL RESIDENTS WITHIN A SEVERAL BLOCK RADIUS (MID SEPTEMBER)

  • EVALUATE & INCORPORATE COMMUNITY INPUT & SURVEY

RESULTS (FALL 2020)

  • SELECT TANK SITE AND BEGIN PERMITTING (WINTER 2020)
  • ANOTHER PUBLIC MEETING (ASSOCIATED WITH PERMITTING,

WINTER 2020/21)

  • INCORPORATE ADD’L COMMUNITY INPUT, FINALIZE

PERMITTING (WINTER 2020/21)

  • PROJECT DESIGN (WINTER/SPRING 2021)
  • CONSTRUCTION (2021-2022)
slide-43
SLIDE 43

CONCLUDING THOUGHTS

  • THIS TANK IS AN IMPROVEMENT THE CITY HAS TO MAKE
  • IF YOU LIVE ANYWHERE SOUTH OF 14TH AVE., YOU BENEFIT
slide-44
SLIDE 44

CONCLUDING THOUGHTS

  • THIS TANK IS AN IMPROVEMENT THE CITY HAS TO MAKE
  • IF YOU LIVE ANYWHERE SOUTH OF 14TH AVE., YOU BENEFIT
  • EVERY LOCATION PRESENTED TONIGHT WILL BE CONTROVERSIAL
  • THE RESERVOIR MUST BE LOCATED IN THE VICINITY OF HAMBLEN PARK AND

SO WILL BE VISIBLE FROM THIS AREA REGARDLESS OF LOCATION

slide-45
SLIDE 45

CONCLUDING THOUGHTS

  • THIS TANK IS AN IMPROVEMENT THE CITY HAS TO MAKE
  • IF YOU LIVE ANYWHERE SOUTH OF 14TH AVE., YOU BENEFIT
  • EVERY LOCATION PRESENTED TONIGHT WILL BE CONTROVERSIAL
  • THE RESERVOIR MUST BE LOCATED IN THE VICINITY OF HAMBLEN PARK AND

SO WILL BE VISIBLE FROM THIS AREA REGARDLESS OF LOCATION

  • HAMBLEN PARK MEETS ALL THE CRITERIA
  • HAMBLEN DOESN’T DISPROPORTIONATELY IMPACT SOME NEIGHBORS

BECAUSE IT’S A BLOCK AWAY FROM THE NEAREST HOME

slide-46
SLIDE 46

CONCLUDING THOUGHTS

  • THIS TANK IS AN IMPROVEMENT THE CITY HAS TO MAKE
  • IF YOU LIVE ANYWHERE SOUTH OF 14TH AVE., YOU BENEFIT
  • EVERY LOCATION PRESENTED TONIGHT WILL BE CONTROVERSIAL
  • THE RESERVOIR MUST BE LOCATED IN THE VICINITY OF HAMBLEN PARK AND

SO WILL BE VISIBLE FROM THIS AREA REGARDLESS OF LOCATION

  • HAMBLEN PARK MEETS ALL THE CRITERIA
  • HAMBLEN DOESN’T DISPROPORTIONATELY IMPACT SOME NEIGHBORS

BECAUSE IT’S A BLOCK AWAY FROM THE NEAREST HOME

  • THE COMPLETED TANK IMPACTS LESS THAN 1% OF THE AREA IN HAMBLEN
  • PARK. THE PARK WILL NOT BE LOST OR DESTROYED AS SOME FEAR.
  • A TANK IN HAMBLEN PARK IS AN OPPORTUNITY TO END UP WITH

COMMUNITY ASSETS WHICH WOULD NOT BE REALIZED AT OTHER LOCATIONS

slide-47
SLIDE 47

PROCEDURAL MATTERS

  • THE PROJECT WEBPAGE IS YOUR SOURCE FOR UP TO DATE INFORMATION

INCLUDING:

  • THIS PRESENTATION
  • THE SURVEY I REFERENCED
  • FAQS
  • STATUS UPDATES
slide-48
SLIDE 48

PROCEDURAL MATTERS

  • THE PROJECT WEBPAGE IS YOUR SOURCE FOR UP TO DATE INFORMATION

INCLUDING:

  • THIS PRESENTATION
  • THE SURVEY I REFERENCED
  • FAQS
  • STATUS UPDATES
  • BECAUSE OF THE IMPRACTICALITY OF PUBLIC QUESTIONS/COMMENTS WITH

THIS MEETING FORMAT, YOU CAN SUBMIT COMMENTS AND QUESTIONS TO THE EMAIL ADDRESS ON THE WEB PAGE

slide-49
SLIDE 49

QUESTION & COMMENTS

  • COMMENT/QUESTION: THE PROPOSED TANK WILL SEVERELY IMPACT THE
  • PARK. HOW MUCH OF THE PARK WILL BE IMPACTED?
slide-50
SLIDE 50

QUESTION & COMMENTS

  • COMMENT/QUESTION: THE PROPOSED TANK WILL SEVERELY IMPACT THE
  • PARK. HOW MUCH OF THE PARK WILL BE IMPACTED?
  • RESPONSE: AS WE’VE ATTEMPTED TO COMMUNICATE IN THIS PRESENTATION,

WE DO NOT TAKE LOCATING THIS TANK IN THE PARK LIGHTLY. WE’VE COVERED TONIGHT THE 10 OTHER SITES CONSIDERED AND THE SUBSTANTIAL DISADVANTAGES OF EACH. RECALL THAT LESS <1% OF THE TOTAL PARK AREA WILL BE CONSUMED BY THE PROPOSED TANK. THE TEMPORARY CONSTRUCTION IMPACT OF THIS TANK AFFECTS A LARGER AREA, APPROX. 1 ACRE OR 12% OF THE SITE. THAT IMPACTED AREA WILL BE REPLANTED AND RESTORED IMMEDIATELY FOLLOWING CONSTRUCTION.

slide-51
SLIDE 51

QUESTION & COMMENTS

  • COMMENT/QUESTION: IF THIS TANK DOES END UP BEING IN HAMBLEN PARK,

PLEASE DON’T “IMPROVE” THIS PARK. WE LIKE IT JUST THE WAY IT IS.

slide-52
SLIDE 52

QUESTION & COMMENTS

  • COMMENT/QUESTION: IF THIS TANK DOES END UP BEING IN HAMBLEN PARK,

PLEASE DON’T “IMPROVE” THIS PARK. WE LIKE IT JUST THE WAY IT IS.

  • RESPONSE: WE HAVE RECEIVED THIS COMMENT FROM A NUMBER OF PEOPLE.

WE HAVE ALSO RECEIVED THE OPPOSITE COMMENTS FROM A NUMBER OF

  • PEOPLE. WE LOOK FORWARD TO REVIEWING THE SURVEY RESULTS TO SEE

WHAT THE MAJORITY OF PEOPLE WAY ON THIS ISSUE. THE CITIZENS WILL GUIDE OUR MITIGATION MEASURES. PARK IMPROVEMENTS DO NOT NECESSARILY MEAN DEVELOPING THE PARK.

slide-53
SLIDE 53

QUESTION & COMMENTS

  • COMMENT/QUESTION: IS “IMPACTS TO THE PUBLIC” ONE OF THE SITE

SELECTION CRITERIA?

slide-54
SLIDE 54

QUESTION & COMMENTS

  • COMMENT/QUESTION: IS “IMPACTS TO THE PUBLIC” ONE OF THE SITE

SELECTION CRITERIA?

  • RESPONSE: YES, IT IS.
  • ONLY CONSIDERING VACANT PARCELS (AS OPPOSED TO BUYING HOMES AND

DEMOLISHING HOUSES) IS ONE WAY TO REDUCE THE IMPACT TO PUBLIC.

  • FAVORING A RESERVOIR SITE WHICH IS AT LEAST 300’ FROM THE NEAREST

ADJACENT HOME IS ANOTHER WAY TO REDUCE IMPACTS TO THE PUBLIC.

  • SELECTING A SITE WHICH REDUCES COSTS WE ALL HAVE TO PAY IS YET ANOTHER

WAY TO REDUCE IMPACTS TO THE PUBLIC.

  • PLACING THE TANK CENTRALLY IN A TREED AREA ALSO REDUCES THE VISUAL

IMPACT TO THE PUBLIC.

slide-55
SLIDE 55

QUESTION & COMMENTS

  • COMMENT/QUESTION: WAS THE POTENTIAL REDUCTION IN PROPERTY VALUES

ONE OF THE CONSIDERATIONS FOR TANK SITE SELECTION?

slide-56
SLIDE 56

QUESTION & COMMENTS

  • COMMENT/QUESTION: WAS THE POTENTIAL REDUCTION IN PROPERTY VALUES

ONE OF THE CONSIDERATIONS FOR TANK SITE SELECTION?

  • RESPONSE: ONE OF THE CRITERIA IS TO LOCATE THIS TANK AWAY FROM

ADJACENT HOMES TO THE MAXIMUM EXTENT POSSIBLE TO REDUCE IMPACTS INCLUDING ANY POTENTIAL IMPACTS TO PROPERTY VALUES. HAMBLEN PARK IS THE LOCATION THAT PLACES THE PROPOSED TANK FURTHER FROM ADJACENT RESIDENTS THAN ANY OTHER ALTERNATIVE WHILE STILL ACCOUNTING FOR COST CONSIDERATIONS.

slide-57
SLIDE 57

QUESTION & COMMENTS

  • COMMENT/QUESTION: HAS AN ENVIRONMENTAL REVIEW BEEN PERFORMED

YET? HAS A TREE PRESERVATION/REPLACEMENT PLAN BEEN DEVELOPED?

slide-58
SLIDE 58

QUESTION & COMMENTS

  • COMMENT/QUESTION: HAS AN ENVIRONMENTAL REVIEW BEEN PERFORMED

YET? HAS A TREE PRESERVATION/REPLACEMENT PLAN BEEN DEVELOPED?

  • RESPONSE: NO, THIS WILL OCCUR ONCE SITE SELECTION HAS BEEN FINALIZED.
slide-59
SLIDE 59

QUESTION & COMMENTS

  • COMMENT/QUESTION: HAVE YOU CONSIDERED VARIOUS COLOR SCHEMES

OR A MURAL TO REDUCE VISUAL THE IMPACTS TO THIS TANK.

slide-60
SLIDE 60

QUESTION & COMMENTS

  • COMMENT/QUESTION: HAVE YOU CONSIDERED VARIOUS COLOR SCHEMES

OR A MURAL TO REDUCE VISUAL THE IMPACTS TO THIS TANK.

  • RESPONSE: THOSE EVALUATIONS WILL BE PERFORMED WITH COMMUNITY

INPUT FOLLOWING FINALIZATION OF TANK SITE SELECTION. AS YOU SUGGEST, THERE ARE A NUMBER OF OPTIONS FOR REDUCING THE VISUAL IMPACTS.

slide-61
SLIDE 61

QUESTION & COMMENTS

  • COMMENT/QUESTION: WILL CELL PHONES ANTENNAE AND/OR AIRCRAFT

WARNING LIGHTS BE INSTALLED ATOP THIS TANK.

slide-62
SLIDE 62

QUESTION & COMMENTS

  • COMMENT/QUESTION: WILL CELL PHONES ANTENNAE AND/OR AIRCRAFT

WARNING LIGHTS BE INSTALLED ATOP THIS TANK.

  • RESPONSE: YES, AIRCRAFT WARNING LIGHTS MUST BE INSTALLED. CELL

PHONE ANTENNAE INSTALLATION WILL NOT BE A PART OF THIS PROJECT. CELL PHONE COMPANIES DESIRING TO PUT ANTENNAE ATOP THIS TANK WILL HAVE TO COMPLY WITH A SEPARATE PERMITTING PROCESS THAT IS NOT RELATED TO TANK CONSTRUCTION.