Distribution Water Main Extension and Replacement Multiple locations Project ID : MED625 Entire Project duration: 2015-2017 Engineering Firm: KS Engineers, PC Contractor: Judlau Contracting, Inc. Project Name: Distribution of Water Main


  1. Distribution Water Main Extension and Replacement – Multiple locations Project ID : MED625 Entire Project duration: 2015-2017 Engineering Firm: KS Engineers, PC Contractor: Judlau Contracting, Inc. Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 1

  2. Project Intent & Purpose: Intent: • Upgrade existing water mains (newer & bigger) Purpose:  Increased population (demand)  Aging infrastructure (increase the useful life) Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 2

  3. Scope of Work Water Main Extension & Replacement  Extension & Replacement of Existing 12” & 20” Distribution Water Mains.  Roadway Restoration.  Installation of Catch Basins and Basin Connections Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 3

  4. Project Duration May 2015 – August 2015 • Delancey Street (between Columbia Street and Pitt Street) • Pitt Street (between Delancey Street and East Houston Street) • Rivington Street (between Pitt Street and Clinton Street) August 2015 – April 2016 • Bowery (between Canal Street and East 4th Street) • First and Second Streets (between Bowery and Second Avenue) • Second Avenue (between East 2 nd Street and East Houston Street ) Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 4

  5. Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 5

  6. Allowable Work Days/Hours: (as per NYC DOT Stipulations)  7:00AM-6:00PM: Monday-Friday (Weekend Work as Needed) • Bowery and auxiliary blocks between Spring Street and East 4th Street  10:00PM-6:00AM: Monday- Friday (Weekend Work as Needed) • Bowery between Canal Street and Spring Street  TBD • Delancey Street between Columbia Street and Pitt Street • Pitt Street between Delancey Street and East Houston Street • Rivington Street between Pitt Street and Clinton Street Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 6

  7. New York City DOT Traffic Stipulations During Construction on Bowery between Canal Street & Spring Street • Night Work 10PM-6AM • 5ft pedestrian walkways • Two 12ft wide Northbound lanes • One 12ft wide Southbound lane • No construction materials on Bowery • 50ft X 8ft of curb lane on one-way streets for enclosed storage of materials • On Delancey Street – Two 11ft wide Eastbound Lanes & Two 11ft wide Westbound Lanes • At other cross streets- One 10ft wide lane on one-way streets, Two 10ft wide lanes on two way streets Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 7

  8. New York City DOT Traffic Stipulations During Construction on Bowery between Spring Street & East 4 th Street • Day Work 7AM-6PM • 5ft pedestrian walkways • Will not impact Northbound and Southbound traffic at the same time. • One 12ft wide Southbound lane • One 12ft wide Northbound lane • No construction materials on Bowery • 50ft X 8ft of curb lane on one-way streets for enclosed storage of materials • At Cross Streets – 11ft wide lanes for one-way traffic & Two 10ft wide lanes for two-way traffic Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 8

  9. COMMUNITY IMPACTS & WHAT TO EXPECT Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 9

  10. COMMUNITY IMPACTS • Pedestrian access will be maintained at all times • Intermittent street closures and/or limited access may be necessary • Bus routes affected by the project: • Bowery (Canal St. – E. 4th St.) – M103 • DDC will monitor operation and work within DEP Noise Code regulations • Sidewalk and/or loading dock access from the curb may be temporarily restricted while work is conducted (coordination will be arranged on a case by case basis) • Parking may be temporarily restricted during construction Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 10

  11. Water Service Interruptions: Water service disruption planned • Typically 8hrs (not consecutive) • 72 hour advance notice will be provided • Specific instruction will be provided prior to water shutoff • If your water service is not restored within 3 hours of the indicated on the Shutoff notice, please contact the community construction Liaison (CCL) or 311 if after hours. Special Needs: • Individuals with special needs should contact the CCL • DDC field staff will work specially with those individuals to minimize certain inconveniences Rodent Control: • A rodent survey will be performed prior to construction • Rodent Control Stations will be installed by a professional rodent control contractor Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 11

  12. Keeping You Informed Office of Community Outreach & Notification, DDC • DDC has assigned Amanda Girgis of KS Engineers, PC as the Community Construction Liaison (CCL). She will keep the community informed by: • Being the first point of contact between the project and the community • Identifying, addressing and/or resolving field inquiries & issues as well as any coordination between the project and needs of the affected stakeholders • Providing regular updates/advisories for the community to better plan around construction activities • CCL contact information: • Name: Amanda Girgis • Email: MED625CCL@gmail.com • Field Office: 84 Bowery, 6th Floor, New York NY 10013 • Telephone : (646)-723-9925 • DDC Website: www.nyc.gov/ddc • DDC Video: www.nyc.gov/webuild • During Non-Working hours, please call 311 and give the Project ID: MED625 Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 12

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.