Distribution Water Main Extension and Replacement Multiple locations Project ID : MED625 Entire Project duration: 2015-2017 Engineering Firm: KS Engineers, PC Contractor: Judlau Contracting, Inc. Project Name: Distribution of Water Main


slide-1
SLIDE 1

04/07/15 Slide 1 Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625

Distribution Water Main Extension and Replacement – Multiple locations

Project ID: MED625

Entire Project duration: 2015-2017

Engineering Firm: KS Engineers, PC Contractor: Judlau Contracting, Inc.

slide-2
SLIDE 2

04/07/15 Slide 2 Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625

Project Intent & Purpose:

Intent:

  • Upgrade existing water mains (newer & bigger)

Purpose:

  • Increased population (demand)
  • Aging infrastructure (increase the useful life)
slide-3
SLIDE 3

04/07/15 Slide 3 Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625

Scope of Work Water Main Extension & Replacement

Extension & Replacement of Existing 12” & 20” Distribution Water Mains. Roadway Restoration. Installation of Catch Basins and Basin Connections

slide-4
SLIDE 4

04/07/15 Slide 4 Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625

Project Duration

May 2015 – August 2015

  • Delancey Street (between Columbia Street and Pitt Street)
  • Pitt Street (between Delancey Street and East Houston Street)
  • Rivington Street (between Pitt Street and Clinton Street)

August 2015 – April 2016

  • Bowery (between Canal Street and East 4th Street)
  • First and Second Streets (between Bowery and Second Avenue)
  • Second Avenue (between East 2nd Street and East Houston Street )
slide-5
SLIDE 5

04/07/15 Slide 5 Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625

slide-6
SLIDE 6

04/07/15 Slide 6 Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625

Allowable Work Days/Hours:

(as per NYC DOT Stipulations)

7:00AM-6:00PM: Monday-Friday

(Weekend Work as Needed)

  • Bowery and auxiliary blocks between Spring Street and East 4th Street

10:00PM-6:00AM: Monday- Friday (Weekend Work as Needed)

  • Bowery between Canal Street and Spring Street

TBD

  • Delancey Street between Columbia Street and Pitt Street
  • Pitt Street between Delancey Street and East Houston Street
  • Rivington Street between Pitt Street and Clinton Street
slide-7
SLIDE 7

04/07/15 Slide 7 Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625

New York City DOT Traffic Stipulations During Construction on Bowery between Canal Street & Spring Street

  • Night Work 10PM-6AM
  • 5ft pedestrian walkways
  • Two 12ft wide Northbound lanes
  • One 12ft wide Southbound lane
  • No construction materials on Bowery
  • 50ft X 8ft of curb lane on one-way streets for enclosed storage of materials
  • On Delancey Street– Two 11ft wide Eastbound Lanes & Two 11ft wide Westbound

Lanes

  • At other cross streets- One 10ft wide lane on one-way streets, Two 10ft wide lanes
  • n two way streets
slide-8
SLIDE 8

04/07/15 Slide 8 Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625

New York City DOT Traffic Stipulations During Construction on Bowery between Spring Street & East 4th Street

  • Day Work 7AM-6PM
  • 5ft pedestrian walkways
  • Will not impact Northbound and Southbound traffic at the same time.
  • One 12ft wide Southbound lane
  • One 12ft wide Northbound lane
  • No construction materials on Bowery
  • 50ft X 8ft of curb lane on one-way streets for enclosed storage of

materials

  • At Cross Streets– 11ft wide lanes for one-way traffic & Two 10ft wide lanes

for two-way traffic

slide-9
SLIDE 9

04/07/15 Slide 9 Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625

COMMUNITY IMPACTS & WHAT TO EXPECT

slide-10
SLIDE 10

04/07/15 Slide 10 Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625

COMMUNITY IMPACTS

  • Pedestrian access will be maintained at all times
  • Intermittent street closures and/or limited access may be necessary
  • Bus routes affected by the project:
  • Bowery (Canal St. – E. 4th St.) – M103
  • DDC will monitor operation and work within DEP Noise Code regulations
  • Sidewalk and/or loading dock access from the curb may be temporarily

restricted while work is conducted (coordination will be arranged on a case by case basis)

  • Parking may be temporarily restricted during construction
slide-11
SLIDE 11

04/07/15 Slide 11 Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625

Water Service Interruptions:

Water service disruption planned

  • Typically 8hrs (not consecutive)
  • 72 hour advance notice will be provided
  • Specific instruction will be provided prior to water shutoff
  • If your water service is not restored within 3 hours of the indicated on the

Shutoff notice, please contact the community construction Liaison (CCL) or 311 if after hours. Special Needs:

  • Individuals with special needs should contact the CCL
  • DDC field staff will work specially with those individuals to minimize certain

inconveniences Rodent Control:

  • A rodent survey will be performed prior to construction
  • Rodent Control Stations will be installed by a professional rodent control

contractor

slide-12
SLIDE 12

04/07/15 Slide 12 Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625

Keeping You Informed

Office of Community Outreach & Notification, DDC

  • DDC has assigned Amanda Girgis of KS Engineers, PC as the Community

Construction Liaison (CCL). She will keep the community informed by:

  • Being the first point of contact between the project and the community
  • Identifying, addressing and/or resolving field inquiries & issues as well as

any coordination between the project and needs of the affected stakeholders

  • Providing regular updates/advisories for the community to better plan

around construction activities

  • CCL contact information:
  • Name:

Amanda Girgis

  • Email:

MED625CCL@gmail.com

  • Field Office:

84 Bowery, 6th Floor, New York NY 10013

  • Telephone :

(646)-723-9925

  • DDC Website: www.nyc.gov/ddc
  • DDC Video: www.nyc.gov/webuild
  • During Non-Working hours, please call 311 and give the Project ID: MED625