Remediation OAC 3745 300 11 Certified Professional 8 Hour Training - - PowerPoint PPT Presentation

remediation
SMART_READER_LITE
LIVE PREVIEW

Remediation OAC 3745 300 11 Certified Professional 8 Hour Training - - PowerPoint PPT Presentation

Remediation OAC 3745 300 11 Certified Professional 8 Hour Training Dan Tjoelker Overview VAP remediation requirements Complete pathways to off property receptors Types of remedies Documentation of remedies


slide-1
SLIDE 1

Remediation

OAC 3745‐300‐11 Certified Professional 8‐Hour Training

Dan Tjoelker

slide-2
SLIDE 2

Overview

  • VAP remediation requirements
  • Complete pathways to off‐property

receptors

  • Types of remedies
  • Documentation of remedies
  • Changes to remedies
  • Technical guidance documents

2

slide-3
SLIDE 3

Background

  • Phase II = identify COCs
  • Applicable risk goals

– Excess cancer = 1 x 10‐5 – Excess non‐cancer = 1

  • Decision for remedy if risk goals are

exceeded

3

slide-4
SLIDE 4

Conducted when COCs do not comply with:

  • Generic standards (Rule 08)
  • PSRA standards (Rule 09)
  • Background levels (Rule 07)
  • Any other applicable VAP standard

4

slide-5
SLIDE 5

Pathway omission

  • The statute specifies that the CNS covers all

releases, including those that have left the property

  • Volunteer must demonstrate diligent efforts to

implement remedy to off‐property receptor

  • If unable, pathway can be omitted

5

slide-6
SLIDE 6

Pathway omission process

  • Determine off‐property receptors
  • Determine potential pathways
  • Provide each property owner written notice of

potential pathways and potential associated risks

6

slide-7
SLIDE 7

Pathway omission process

  • Explain to owner activities that may be

employed as part of the investigation

  • Offer to pay all costs
  • Document all discussions/correspondence

with owners where they refused the remedy

  • Document any other reason that prevented

installation of remedy

7

slide-8
SLIDE 8

Requesting the pathway omission

  • Must be done before NFA letter is issued
  • Must document all the steps outlined in the

process

  • Must incur the costs of the agency review
  • The agency will generally approve a request

within ninety days after receipt

8

slide-9
SLIDE 9

Interim Measures

  • Property not meeting applicable

standards prior to issuing an NFA letter

  • Conducted prior to remedy achieving

applicable standards

  • Must be protective of human health and

environment

9

slide-10
SLIDE 10

Types of remediation

  • Active remediation
  • Passive remediation
  • Institutional controls
  • Engineering controls

10

slide-11
SLIDE 11

Active Remediation

  • Reduces mass, toxicity, or mobility of

COC

  • Most common is soil removal

11

slide-12
SLIDE 12

Passive Remediation

  • Remedial activities relied upon as in situ

natural methods and documented in peer‐ reviewed scientific literature, which reduce the mass, toxicity, mobility or concentration of a chemical of concern over distance and time through natural attenuation processes

12

slide-13
SLIDE 13

Natural attenuation processes

  • Adsorption
  • Absorption
  • Advection
  • Dispersion
  • Diffusion
  • Dilution from recharge
  • Volatilization

13

slide-14
SLIDE 14

Other types of natural attenuation

  • Aerobic biodegradation
  • Anaerobic biodegradation
  • Chemical oxidation processes
  • Hydrolysis and other reactions

14

slide-15
SLIDE 15

Monitored natural attenuation

  • Natural attenuation conclusion must

be supported

  • Standards met during a certain time

frame

15

slide-16
SLIDE 16

Institutional Controls

  • Established by recording deed

restriction

  • Transferable
  • Eliminates or mitigates exposure to

hazardous substances or petroleum

  • Monitored, maintained, and

enforced

16

slide-17
SLIDE 17

Engineering Controls

  • Relies on its ability to block a complete

exposure pathway

  • Must be reliable for the climatic conditions

and activities at the property to which the control will be applied

  • Monitored and maintained per operation and

maintenance plan

17

slide-18
SLIDE 18

Examples of Engineering Controls

  • Pavements acting as barrier caps
  • Soil caps to eliminate direct contact to

chemicals or prevent groundwater contamination

  • Foundations and building floor slabs
  • Sub‐slab vapor diversion systems

18

slide-19
SLIDE 19

Risk Mitigation Measures and Risk Mitigation Plans

  • Contained in risk mitigation plan
  • Implemented as

‒Condition of covenant, or ‒Within O&M plan

  • Must have periodic reporting

19

slide-20
SLIDE 20

Risk Mitigation Measures

  • Needed when there is potential

exposure to construction workers before or after issuance of NFA

  • Apply if POC is breached
  • Safety precautions to mitigate or

eliminate human exposure

20

slide-21
SLIDE 21

Risk Mitigation Measures

  • Documented in risk mitigation plan if

measures are necessary for the property to meet applicable standards after issuance of the no further action letter

21

slide-22
SLIDE 22

Documentation of remedial activities

  • Environmental covenant
  • Risk mitigation plan
  • Operation and Maintenance Plan

22

slide-23
SLIDE 23

Environmental Covenant

  • Required for “environmental

response projects” with institutional controls

  • Applies to properties with NFA letters

that request a CNS

  • Institutional controls = Activity and

Use Limitations (AULs)

23

slide-24
SLIDE 24

Environmental Covenant

http://epa.ohio.gov/derr/volunt/volunt.aspx

24

slide-25
SLIDE 25

Environmental Covenant

  • CP must submit draft with NFA Letter
  • Should discuss language with VAP prior to

issuance of NFA

  • CP should discuss implications of AULs with

Volunteer

  • Recordation of environmental covenant

within 30 days of CNS issuance

25

slide-26
SLIDE 26

Risk Mitigation Plan

  • Required if the risk mitigation

measures are necessary for the property to meet applicable standards after issuance of the NFA letter

26

slide-27
SLIDE 27

Risk Mitigation Plan Contents

  • Purpose of the plan, including summary of

potential health risks

  • Specific precautions against exposure
  • Directions on how to handle environmental

media

  • Locations on property where plan will be

implemented

27

slide-28
SLIDE 28

Risk Mitigation Plan Contents

  • Provisions for when the plan will be

implemented

  • Provisions for notifying construction workers
  • Summary explanation of precautions
  • Annual notification provisions
  • Criteria for termination

28

slide-29
SLIDE 29

Operation and Maintenance Plan

  • Required when:

–Engineering control is employed –Any remedial activity not completed prior to NFA issuance

29

slide-30
SLIDE 30

Operation and Maintenance Plan Contents

  • Summary of applicable standards
  • Plan for implementation
  • Plan for evaluating effectiveness
  • Description of equipment
  • Plan for adjustments

30

slide-31
SLIDE 31

Operation and Maintenance Plan Contents (cont.)

  • Address potential problems
  • Placeholder for keeping records
  • Plan for termination of remedial

activities

31

slide-32
SLIDE 32

Operation and Maintenance Plan Reporting

  • At least annually
  • Demonstrate efficacy of remedy
  • Report on contingency measures
  • Confirm remedy is still in place

32

slide-33
SLIDE 33

Operation and Maintenance Agreement

  • Generic template available through

VAP

  • O&M plan and agreement must be

submitted with NFA Letter

  • O&M agreement negotiated after

submittal

33

slide-34
SLIDE 34

Changes to the remedy post‐CNS

  • Volunteer may choose to change the

remedy

  • Collect data necessary to support new

remedy

  • Maintain existing remedy until the new

remedy is implemented

34

slide-35
SLIDE 35

Remedy revision notice

  • Description of remedial activities
  • Statement from CP that property meets

applicable standards

  • List of information used to justify new remedy
  • Description of new remedy
  • New environmental covenant or O&M plan, as

applicable

35

slide-36
SLIDE 36

Remedy revision acknowledgment

  • Agency does not review remedy
  • Property can be considered for compliance

audit

  • TA account must be opened if O&M plan,

agreement or environmental covenant changes

36

slide-37
SLIDE 37

Remedy revision approval

  • Volunteer opens a TA account for the

cost of agency review and approval letter

  • No compliance audit expectations

37

slide-38
SLIDE 38

Technical decisions relating to remedies

  • http://epa.ohio.gov/portals/30/vap/tgc/TGC_Index.pdf
  • Archived decisions available for informational

purposes only

  • Four relate to remedies

38

slide-39
SLIDE 39

Passive remedy for potential future exposure scenarios

  • Passive remedy can be implemented to

protect on and off‐property receptors

  • Requires O&M plan
  • CP must demonstrate that the remedy is

appropriate for site

39

slide-40
SLIDE 40

Injection wells

  • Formal injection permit may not be

necessary if fluids do not exceed standards

  • CP must apply and receive 5X26 exemption

for remedial projects

  • More information found at:

http://epa.ohio.gov/ddagw/UIC.aspx

40

slide-41
SLIDE 41

Hazardous Waste Reporting Requirements

  • Comply with annual reporting

requirements found in 3745‐52‐41 if Volunteer:

– Generates 1000 kg hazardous waste/month (or subject to 3745‐52‐34) and, – Ships hazardous waste off‐site

41

slide-42
SLIDE 42

Hazardous Waste Reporting Requirements

Further information:

  • http://epa.ohio.gov/dmwm/Home

/HWAnnualReportProgram.aspx

  • Division of Materials and Waste

Management – (614) 644‐2917

42

slide-43
SLIDE 43

Fence as a Remedy

  • Q: Fence = engineering or

institutional control?

  • A: Fence = engineering control

43

slide-44
SLIDE 44

Fence as a Remedy

  • CNS is void if fence is damaged or

compromised and is part of AUL

  • Opportunity to cure if fence is

damaged or compromised and is part of engineering control

44

slide-45
SLIDE 45

Fence as a Remedy

  • Numerous scenarios for fence to

be compromised

  • Fence within engineering control

allows volunteer to inspect and repair; avoiding CNS voidance

45

slide-46
SLIDE 46

Remedy Top Mistakes List

 No remedy implemented in absence

  • f O&M plan

 No O&M for engineering control  Slab or foundation omitted as engineering control

46

slide-47
SLIDE 47

Remedy Top Mistakes List

 Construction worker risk not mitigated  No Risk Management Plan included  Effectiveness of remedy not documented

47

slide-48
SLIDE 48

Remedy Top Mistakes List

 Disposal media not properly characterized  Remedy implementation not documented

48

slide-49
SLIDE 49

Remedy Top Mistakes List

 Deed restrictions not recorded  Insufficient sampling data  Financial assurance mechanism not included in O&M agreement

49

slide-50
SLIDE 50

Remedy Top Mistakes List

 Failure to implement applicable response requirements  USD not verified properly

50