reliability requirements user group call
play

Reliability Requirements User Group Call 07/16/2014 Dede Subakti - PowerPoint PPT Presentation

Reliability Requirements User Group Call 07/16/2014 Dede Subakti Gautham Katta Perry Servedio Pia Sok Agenda 1. Progress Report a. RA Processing 2. Topics for Discussion a. Monthly RA Processing Time-line b. Monthly Procurement &


  1. Reliability Requirements User Group Call 07/16/2014 Dede Subakti Gautham Katta Perry Servedio Pia Sok

  2. Agenda 1. Progress Report a. RA Processing 2. Topics for Discussion a. Monthly RA Processing Time-line b. Monthly Procurement & Demonstration of RA c. CAM/RMR/DR/Local Areas d. Resource Adequacy Capacity Data (TTM) 3. Upcoming Deadlines 4. Questions Page 2

  3. Progress Report Page 3

  4. RA Processing August Monthly Resource Adequacy  Completed August T-45 validation on 06/16/2014  Completed August T-25 validation on 07/03/2014  LSE to log in to CIRA to review replacement requirement determination  LSE that has a replacement requirement may provide additional Specified Replacement capacity by resubmitting the RA plan before August T-11 (due date – 07/18/2014) Annual NQC Process  Received QC calculations from CPUC  Completed discrepancy analysis  Waiting on QC calculations from other LRAs  Targeting Draft List publication in early August Page 4

  5. Topics for Discussion Page 5

  6. Monthly RA Processing Time-line http://www.caiso.com/Documents/2014MonthlyResourceAdequacyPlanDueDates.pdf Page 6

  7. Monthly Procurement & Demonstration of RA LSEs must meet three individual requirements ISO Tariff Section 40.7(a) 1. Procure 115% of Peak Load Forecast 2. Procure 100% of Local Need ISO Tariff Section 40.7(b) 3. Replacement Requirement for Scheduled Generation Outages Page 7

  8. Monthly Procurement & Demonstration of RA Local & System Requirement (40.7.a.i & 40.7.a.ii) Page 8

  9. Monthly Procurement & Demonstration of RA • Replacement Requirement for LSE (Tariff Section 40.7.b) Page 9

  10. What is the “PEAK Results” Screen? • This screen does not report a local (40.7.a.i) or system (40.7.a.ii) or replacement requirement (40.7.b) deficiencies. • It just shows what counted as “Operationally Available RA” for purposes of the replacement requirement (40.7.b) analysis. Page 10

  11. CAM/RMR/DR and Local Areas Look familiar? What do you do here? Can you translate CPUC credit amounts to ISO template? Page 11

  12. CAM/RMR/DR and Local Areas CAM and RMR Credit Location Translation: Indication TAC Area NP26 PGE SP26 SCE DR Credit Location Translation: Indication TAC Area Non-LCR SYS San Diego-IV SDG LA Basin SCE Big Creek-Ventura SCE Bay Area PGE Fresno PGE Humboldt PGE Kern PGE NCNB PGE Sierra PGE Stockton PGE Page 12

  13. Total Resource Adequacy Capacity (TTM) Total Resource Adequacy Capacity Minimum RA Day (MW) Maximum RA Day (MW) 60000 55000 50000 45000 40000 35000 30000 25000 06/2013 07/2013 08/2013 09/2013 10/2013 11/2013 12/2013 01/2014 02/2014 03/2014 04/2014 05/2014 06/2014 Page 13

  14. Internal Resource Adequacy Capacity (TTM) GEN Type Resource Adequacy Capacity Minimum RA Day Maximum RA Day 50000 45000 40000 35000 30000 25000 20000 15000 10000 5000 0 06/2013 07/2013 08/2013 09/2013 10/2013 11/2013 12/2013 01/2014 02/2014 03/2014 04/2014 05/2014 06/2014 Page 14

  15. External Resource Adequacy Capacity (TTM) Intertie+TieGen Type Resource Adequacy Capacity Minimum RA Day Maximum RA Day 7000 6000 5000 4000 3000 2000 1000 0 06/2013 07/2013 08/2013 09/2013 10/2013 11/2013 12/2013 01/2014 02/2014 03/2014 04/2014 05/2014 06/2014 Page 15

  16. Upcoming Deadlines Page 16

  17. Upcoming Deadlines Monthly RA deadlines 1. September 2014 T-45: 07/17/2014 2. August 2014 T-11: 07/18/2014 3. September 2014 T-25: 08/06/2014 Import Allocation Process 1. Step 8 requests due on 07/18/2014 2. Step 9 requests due on 07/21/2014 Please use import allocation request template found on Reliability Requirements webpage under “Templates” http://www.caiso.com/planning/Pages/ReliabilityRequirements Page 17

  18. Upcoming Deadlines Market Simulation for M2M and FRACMOO • August 25 – September 12, 2014 – Structured: August 25 – 29 • Structured scenarios only for M2M – Unstructured: September 1 – 12 • ISO plans on using September 2014 RA data for market simulation Page 18

  19. Questions? Page 19

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend