regulatory proposal to the aer 2011 2015
play

Regulatory Proposal to the AER, 2011 2015 0 Public Forum, 17 - PowerPoint PPT Presentation

Regulatory Proposal to the AER, 2011 2015 0 Public Forum, 17 December 2009 Presentation outline 1 Charles Popple Group General Manager Networks Strategy and Development 1. Background About SP AusNet Our network and distribution area


  1. Regulatory Proposal to the AER, 2011 – 2015 0 Public Forum, 17 December 2009

  2. Presentation outline 1 Charles Popple Group General Manager Networks Strategy and Development 1. Background About SP AusNet ► Our network and distribution area ► Focus on customer service ► Asset management strategy 2. Our Proposal Building blocks ► 2006-2010 regulatory period ► Capex ► Opex ► Other building blocks 3. Outcomes Impact on customers ► Pricing and tariffs ► Reliability

  3. 1. Background About SP AusNet 2 ► Our network and distribution area ► Focus on customer service ► Asset management strategy

  4. Snapshot of our network 3 � Distributes electricity to 610,000 customer supply points � Spans more than 80,000 sq km � 47 66/22 kV zone substations � 57,000 distribution substations � 371,000 power poles and 100,000 streetlights � 46,000 kilometres of underground cable and overhead lines

  5. Unique characteristics of our distribution area 4 � Difficult terrain and climatic conditions – Alpine regions are mountainous, heavily forested, with significant vegetation cover – Coastal areas are subject to high winds and salt – Windy and dry conditions in Victoria’s south and hot, dry and windy conditions in the North � Covers some of Melbourne’s fastest growing suburban corridors � Average customer density is low, reflecting isolated farms and small country towns � Great Dividing Range imposes a physical separation

  6. Our focus on customer service 5 � In the current regulatory period, invested $71 million (real 2010 $) specifically to improve customer service and reliability � In the forthcoming regulatory period, our Proposal – meets safety and technical standards – sets out plans to maintain supply reliability – includes some specific measures to deliver targeted improvements in customer service

  7. Historic network performance 6 400 350 300 250 Network USAIDI 200 150 100 50 0 2005 2006 2007 2008 2009 � Note: Based on 3.2 Beta exemption regime

  8. Asset management strategy (AMS) 7 � Basis of SP AusNet’s expenditure plans and demonstrates that those plans are consistent with the NEL objectives and rule requirements � Informed by 30-year Network Development Strategy, which addresses the longer term capacity and investment requirements of the network � Underpinned by the regulatory and commercial imperatives of delivering prudent and efficient cost and service performance, without compromising safety � This does not mean lowest possible cost nor does it mean guaranteed supply � Rigorous cost benefit analysis of all expenditure decisions, including risk management in relation to asset performance and network reliability

  9. 8 ► 2006-2010 regulatory period ► Other building blocks Building blocks ► Capex ► Opex 2. Our Proposal

  10. Summary of our Proposal 9 � Overarching objective is a safe network, with efficient and sustainable customer service Summary of key forecasts � Proposed capital and operating expenditure maintains existing levels of network Capex (Net real 2010 $) $ 1,372 M performance � Proposal reflects the financial environment, Opex (Real 2010 $) $894 M climate change and customer expectations � Forecast capital and operating and Closing RAB (By 2015, nominal) $3,264 M maintenance expenditures are driven by: – increased asset replacement works WACC (Nominal) 10.86% – increased augmentation and customer connection capex New demand tariffs – IT expenditure - 46.25% P 0 of – higher unit costs � Changes proposed to strengthen incentives to - 5.5% P x of improve network reliability � AMI will be used to deliver cost-reflective price signals through new tariffs

  11. Review of 2006-2010 regulatory period 10 Key Factors SP AusNet’s Response � Peak demand growth and the costs of � Safety: Statutory safety requirements and servicing customer connection growth internal safety policies and practices are consistently above ESC forecasts complied with at all times � Input costs have risen faster than the rate of cost escalation assumed by the ESC � Customer connections: Highly responsive to � Disruptive natural events including six connection requests extreme events have occurred, such as 2007 � Network reliability: Invested significantly Gippsland Floods, 2008 April Storm and 2009 Bushfires ($71 million in real 2010 $) to improve � Global financial crisis has resulted in a sharp customer reliability increase in the cost of capital � Network reinforcement: Increased Network wide utilisation, following prudent and economic deferral of some reinforcement projects � Information technology: Replacement and rationalisation of IT systems and infrastructure to maintain IT capability

  12. Historical capex 11 � Forecast: $996M (real 2010 $, net of Historical expenditure versus Benchmark customer contributions) 300 � SP AusNet will spend approx $247M (33%) over the regulatory allowance 250 � Includes additional work undertaken 200 specifically to improve reliability Real 2010$M 150 � SP AusNet has successfully funded this extra capex 100 50 0 2006 2007 2008 2009 2010 Actual S-Factor Benchmark

  13. Forecast capex 12 Forecast capital expenditure versus historical expenditure � Total net capex forecast for the 2011- 2015 regulatory period: $1,372M (real 350 2010 $) 300 � 48% higher than in the previous 250 48% regulatory period Real 2010$M 200 � Averages $274M p.a. 150 100 50 0 EDPR Average 2011 2012 2013 2014 2015 Benchmark 2006-10 Reinforcement Net Customer Connections Reliability Maintain Quality Improve Env, Safety and Legal SCADA and Network Control Non-System - IT Non System - General

  14. Main drivers of increase in forecast capex 13 Driver Capex Impact � Demand growth: forecast growth in � Network reinforcement and Customer maximum demand of 4.4% (versus actual Connections: to provide sufficient new growth of 6.7% to date in current regulatory capacity period) and growth in customer connections of 2.1% � Asset replacement (Reliability Maintain) and � Maintaining network condition compliance (Environmental, Safety and Legal) : to ensure that public safety and network reliability and quality are maintained � Maintaining our Information Technology (IT) � Non-system IT: to provide system capability infrastructure needed to facilitate asset management, operational efficiency and planned customer service standards � Higher unit costs: unit rates predicted to � All categories of capex increase by around 9.5% in real terms over forecast period

  15. Meeting demand growth 14 � Customer connections forecast to Forecast reinforcement and customer connection capex average 13,596 p.a. (2.1% p.a.) , continues to be strong over the forthcoming 180 regulatory period 150 Demand forecasts 53% 120 2500 4.8% Real 2010$M 2400 4.7% 90 2300 4.6% % growth rate 60 2200 4.5% MVA 2100 4.4% 30 2000 4.3% 1900 4.2% 0 1800 4.1% Average 2011 2012 2013 2014 2015 2011/12 2012/13 2013/14 2014/15 2015/16 2006-10 Year 50% POE (MVA) % Growth (MVA) Reinforcement Net Customer Connections

  16. Meeting growth in peak demand 15 Growth corridors � Demand associated with new housing developments tends to be relatively peaky due to the rapid uptake of air conditioning � Air-conditioning electrical load is responsible for the peak load on the network on an increasing number of occasions each year Temperature dependant load Source: VENCorp Electricity Transmission Planning in Victoria

  17. Maintaining network condition 16 � SP AusNet’s asset replacement Forecast Asset replacement (Reliability Maintain) and compliance (Environmental, Safety and Legal) capex programs are condition based 120 � There is a strong correlation between asset age and condition 100 � Implementation of the asset plans 80 53% maintains the average age of the Real 2010$M network 60 40 20 0 Average 2011 2012 2013 2014 2015 2006-10 Reliability Maintain Env, Safety and Legal

  18. Network age profile 17 Installation profile � Our asset replacement strategies minimise asset life cycle costs by: 3.0% – careful modelling of network performance risk Assets with 50 to 60 … are expected to year expected life be replaced over this 2.5% – focused condition monitoring programs built over this period period ... – sophisticated analysis of asset life 2.0% extension and replacement options % of Replacment Cost – selective asset life extension programs 1.5% – efficient delivery of asset replacement though integration with network 1.0% augmentation projects 0.5% Major development of Actual and proposed metro and country replacement profile similar to distribution network original profile 0.0% 1935 1940 1945 1950 1955 1960 1965 1970 1975 1980 1985 1990 1995 2000 2005 2010 2015 2020 Year of Installation

  19. Deliverability 18 � SP AusNet has recently reviewed its organisational structure to enhance its delivery capability � Annual levels of capex forecast are already being achieved in the most recent years of the current regulatory period � Average real increase of 48% in forecast electricity distribution capex represents a 17% increase on total annual SP AusNet capex � SP AusNet’s experience in efficiently executing its previous capex program is reflected in its Project Delivery Model

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend