RAN Reliability Requirements
RASC June 10, 2020 RASC010, RASC011, RASC012
RAN Reliability Requirements RASC June 10, 2020 RASC010, RASC011, - - PowerPoint PPT Presentation
RAN Reliability Requirements RASC June 10, 2020 RASC010, RASC011, RASC012 Purpose & Purpose: Present draft framing, discuss preliminary Key analysis results, review industry trends and Takeaways benchmark Key Takeaways: How we
RASC June 10, 2020 RASC010, RASC011, RASC012
Key Takeaways:
change, recognizing an evolving risk profile
and growing flexibility needs with the changing resource mix
regions including pros and cons of different metrics Purpose: Present draft framing, discuss preliminary analysis results, review industry trends and benchmark
3
Explore Decide Do
Problem Definition & Education Exploration
Proposal & Business Rules Software, BPM updates & Training Deploy to production Review
Defines important design elements and derives options via higher fidelity modeling. Selects an option and details specific design.
We are here
Defines needs to address through additional steps. Can iterate as move through the process.
3
summer
mitigate risk
current and future portfolios
resource mix
impacted by uncertainty and variability
4
indicator of how close the system is to emergency or loss of load.*
highly variable and uncertain
5
Margin = Available non-intermittent generation + intermittent generation + RDT limit + Net Scheduled Interchange + Load Resources (BTMG + LMR + EDR) - Load - Operating Reserve
RDT = Regional Dispatch Transfer Limit | BTMG = Behind the Meter Generation LMR = Load Modifying Resources | EDR = Emergency Demand Response * Emergencies include alerts through to load shed
Time Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
6
2018
None Moderate High
Systemwide Historical Margins
Month Hour
Risks exist outside
Severe Moderate Mild Margin Risk Occurrence Occurrences are defined as Max Gen, Alert, or RSG greater than three times average Severity is color-coded by margin size
7
Margin = Available non-intermittent generation + intermittent generation + RDT limit + Load Resources (BTMG + LMR + EDR) + Net Scheduled Interchange - Load - Cleared Operating Reserve
Assumption Current Approach Trial Analysis Assumptions
resource capacity Flat capacity throughout the year based on summer performance. Using 8760 profiles corresponding to 2018 weather year.
external support Adjustment to the PRM based on imports during summer peak. Using monthly average NSI from the last 3 years, assuming a perfect unit.
rates (FOR) Modelled as a single average forced outage rate for the entire year. Modeled with adders / subtractors at different date-hour based on temperature correlation model using 3- years of historical data.
Optimized to avoid outages during peak summer load periods. Scheduled using a 90% optimality (“best behavior”) assumption.
Adjustments to summer-Focused LOLE Modeling Assumptions
8 2 4 6 8 10 12 14 16 1 2 3 4 5 6 7 8 9 10 11 12 GW Month 2 4 6 8 10 12 14 16 1 2 3 4 5 6 7 8 9 10 11 12 GW Month 2 4 6 8 10 12 14 16 1 2 3 4 5 6 7 8 9 10 11 12 GW Month 2 4 6 8 10 12 14 16 1 2 3 4 5 6 7 8 9 10 11 12 GW Month
Planned Maintenance Forced Outages Intermittent Production Non-Firm External Support
Current Trial
Draft analysis of 2018
Time Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Modifying Loss of Load Expectation inputs to reflect seasonality can better reflect risk throughout the year
9
2018 EUE
Trial Method Current Method
Risks shift outside of summer months
Loss of Load Expectation*
No risk Moderate Risk High Risk
Time Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Month Hour
Modeled 2018
*0.1 LOLE Target
10
** Does not include very recent change in MTEP F3 that adjusts load growth from 60% to 50%.
MTEP 2019 AFC 2033
(760TWh)
**
* As announced plans submitted to commissions
Future III, 2030**
(954 TWh)
Future 1 2040
(825 TWh)
11
+ Standard deviation ++ Reflects changes between Day Ahead and Real Time, including forecast error
Scenario Input Size Average (Range) (GW) Variability+ (GW) Current Wind
6 (0 to 16) 3
Solar
NA NA
FutureI-2040 Wind
13 (0.3 to 31 ) 7
Solar
14 (0 to 52 ) 16
FutureIII-2030 Wind
37 (0.8 to 85) 20
Solar
2 (0 to 6) 2
MTEP19AFC 2033 Wind
18 (0.4 to 43) 10
Solar
6 (0 to 23) 7
Total Wind
23 (0.3 85) 17
Solar
7 (0 to 52) 11
11
12
Time Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Future 1 2040
No risk Moderate Risk High Risk
0.1 Loss of Load Expectation
Time Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Month Hour
Proxy Operator Experience*
Risks shift outside of summer months & traditional peak hours
* 0.6 LOLE Target
Draft results
Interval LOLE (day) LOLP (%) EUE (MWh) EDNS (MW) Annual 0.10 0.03 1,765 700 Interval LOLE (day) LOLP (%) EUE (MWh) EDNS (MW) Annual 0.10 0.03 3,021 1,550 Interval LOLE (day) LOLP (%) EUE (MWh) EDNS (MW) Annual 0.10 0.03 3,550 2,400
MTEP 2019 AFC 2033
**
Future III, 2030 Future 1 2040
Portfolios with similar LOLE result in a wide range of EUE values
LOLE = Loss of Load Expectation EUE = Expected Unserved Energy
13
EDNS = Expected Demand Not Supplied
Draft results
the evaluation of options
14 |
June 10, 2020
PRESENTED TO PREPARED BY
MISO Resource Adequacy Subcommittee Sam Newell Michael Hagerty Hannes Pfeifenberger Walter Graf
Brattle.com | 2
RA METRIC BENCHMARK
Brattle.com | 3
Metric Description Pros Cons Examples
Loss-of-Load Probability (LOLP)
Probability of demand exceeding available resources at least once within a year. Units: % chance of >= 1 event per year Easy to calculate and understand Does not consider duration or size of an unserved load event Northwest Power and Conservation Council: 5% LOLP
Loss-of-Load Events (LOLE)
Expected number of events per year in which demand is not served. One event in ten years translates to 0.1 LOLE per year. Units: Events per year Easy to calculate and understand Used by most U.S. systems Does not consider duration or size of an unserved load event Most U.S. Systems: 1 loss-of-load event per decade or 0.1 event per year
Loss-of-Load Hours (LOLH)
Expected number of hours per year in which demand is not served. One day in ten years translates to 2.4 LOLH per year. Units: Hours per year Considers the loss of load duration Used by NERC Does not consider size of an unserved load event SPP: 2.4 LOLH per year (equal to 1 day in 10 years)
Normalized Expected Unserved Energy (EUE)
Expected MWh of load that will not be served as a result of demand exceeding available
Units: % of expected annual load Considers both the duration and depth
Used by NERC Requires more sophisticated statistical methodologies Alberta: Max annual EUE of 800 MWh Australia NEM: Max of 0.002% normalized EUE
RA METRIC BENCHMARK
Brattle.com | 4
Under NERC Standard BAL-502-RF-03, MISO must calculate the planning reserve margin necessary to achieve 0.1 LOLE (but may have flexibility in how it sets requirements) RTOs across the U.S. implement 0.1 LOLE differently
RTO 1-in-10 Standard Definition Event Type
MISO 0.1 loss-of-load events per year
Firm load shed after all operating reserves and DR deployed
NYISO 0.1 loss-of-load events per year
Firm load shed after 10 min and 30 min operating reserves and voltage reduction deployed
ISO-NE 0.1 loss-of-load events per year
Firm load shed after voltage reduction and DR deployed, but 200 MW
PJM 0.1 days with loss-of-load per year
Firm load shed after interruptible load and 30 min reserves deployed, but before voltage reduction or 10 min reserves deployed
SPP 2.4 loss-of-load hours per year
Not explicitly defined
Source: Pfeifenberger, et al., Resource Adequacy Requirements: Reliability and Economic Implications, Prepared for FERC, September 2013.
RA METRIC BENCHMARK
In its 2016 assessment, NERC chose two metrics to represent a consistent measure across different areas: Expected Unserved Energy (EUE)
satisfying all planning criteria
result of demand exceeding available capacity Loss of Load Hours (LOLH)
capacity, which accounts for duration of events but not magnitude NERC has included estimates of these two metrics in its reliability assessment reports since then
Brattle.com | 5
Source: NERC, Probabilistic Assessment Improvement Plan: Summary and Recommendations Report, December 2015. Available at: https://www.nerc.com/comm/PC/Reliability%20Assessment%20Subcommittee%20RAS%202013/ProbA%20%20Summary%20and%20Recommendations%20final%20Dec%2017.pdf
RA METRIC BENCHMARK
We recommend that MISO consider adopting EUE if:
consistent level of load shed each year…
switching away from LOLE
Brattle.com | 6
Metric Pros Cons
Loss-of-Load Metrics (LOLE, LOLP, LOLH)
duration or size of events
system size. Does not allow for direct comparison among jurisdictions
not aligned across markets
in electricity industry
EUE Metric
magnitude of load shed events due to inadequate supply
not effected by growth in system
across systems of different sizes.
target level based on LOLE/EUE studies
Brattle.com | 7
RA CONSTRUCT ELEMENTS BENCHMARK
MISO is considering reforms to address three different types of shortages
Brattle.com | 8
We primarily focus in these slides on the Resource Adequacy construct to ensure sufficient installed capacity in MISO
Types of Shortages Installed capacity
insufficient to meet demand year-round
Available capacity
insufficient during shoulder months due to excess outages Hourly (8760) RA simulations Hourly (8760) RA simulations
Primary Analytical Tool Committed capacity
insufficient to meet real-time flexibility needs DA-to-RT (DART) simulations Yes, and the RA construct can account for sub- annual needs and capabilities (to inform investments) Primarily an outage coordination issue, but can be informed by identified RA needs and have implications for resource accreditation
Is it a Resource Adequacy Issue?
Primarily an operations and E&AS markets issue to better use installed capacity; add RA requirement
RA CONSTRUCT ELEMENTS BENCHMARK
MISO analyses of historical data suggest reliability risks are shifting away from just summer peak So what is next? What are the key elements of its design to consider when evaluating potential changes to the MISO RA construct?
Brattle.com | 9
Future Reliability Risks Resource Adequacy Requirements Resource Accreditation
Key elements fall into three categories:
RA CONSTRUCT ELEMENTS BENCHMARK
Brattle.com | 10
Tools
What tools can assess future reliability risks?
Primarily, SERVM and GE-MARS, combined with future scenarios
Patterns of Reliability Risks
Are there times outside summer peak with reliability risks?
Southern Company and TVA observe risks in the summer & winter PJM and ISO-NE identified winter fuel security and availability risks AESO identified tight “supply cushion” hours year-round, many in summer despite load being highest in winter
Metrics
What are the right metrics to quantify those risks?
Most U.S. system operators use LOLE Alberta, Australia, European systems use EUE NERC uses EUE and LOLH in its assessments Future Reliability Risks
Note: Examples from Alberta and Ontario refer to their proposed market designs that have since been delayed or cancelled
RA CONSTRUCT ELEMENTS BENCHMARK
Brattle.com | 11
Requirement Periods
Should there be multiple periods or a single annual period addressing year- round risks?
ISO-NE, PJM, and Alberta set a single annual requirement to address year-round risks Ontario, Southern Company, and TVA set seasonal requirements CAISO and NYISO set monthly requirements
System-Wide Requirement
How to determine the system-wide or zonal requirement for each period?
Most markets continue to set a RM based on peak load hours Alberta proposed setting its RM based on tightest supply hours Ontario proposed design considers the relative costs of reducing LOLE in each season for setting seasonal requirements
Local Requirements
How to translate the system-wide or zonal requirement to each LSE?
CPUC requires LSEs to meet the same 15% RM each month with separate local/zonal requirements SPP requires its LREs to meet 12% RM during summer peak
Additional RA Requirements
Are additional RA products needed?
California added a Flexible RA (installed capacity) requirement Resource Adequacy Requirements
Note: Examples from Alberta and Ontario refer to their proposed market designs that have since been delayed or cancelled
Basis for Accreditation
How to determine resource availability during each requirement period? Should it account for planned outages?
CPUC uses ELCC for both wind and solar; UCAP for rest NYISO sets solar & wind values based on average output during peak load hours (e.g., 2-6 pm in June – August for summer) Alberta proposed UCAP as average output during 200 tightest supply-cushion hours, irrespective of planned or forced outages
Participation Requirements
Will different requirements be allowed for different resources across periods? What obligations to place on resource availability during shortage events?
PJM used to allow Summer DR (only available in the summer) Ontario proposes to allow for Seasonal or Annual resources CPUC and NYISO set monthly/seasonal values for solar and wind Singapore proposes to allow daytime-only participation for DR
Penalties & Incentives
How to assess performance and set penalties and incentives during events?
Performance incentives/penalties assessed in ISO-NE and PJM based on availability during shortage events Alberta proposed to assess based on shortage events and tight supply hours
RA CONSTRUCT ELEMENTS BENCHMARK
Brattle.com | 12
Resource Accreditation
Note: Examples from Alberta and Ontario refer to their proposed market designs that have since been delayed or cancelled