Quiet Zone / Wayside Horn Experience Presentation to: City of - - PowerPoint PPT Presentation

quiet zone wayside horn experience
SMART_READER_LITE
LIVE PREVIEW

Quiet Zone / Wayside Horn Experience Presentation to: City of - - PowerPoint PPT Presentation

San Clemente Quiet Zone / Wayside Horn Experience Presentation to: City of Encinitas Coastal Mobility and Livability Working Group Tom Bonigut, Deputy Public Works Director City of San Clemente April 25, 2017 Coastal Rail Corridor Before


slide-1
SLIDE 1

Tom Bonigut, Deputy Public Works Director City of San Clemente April 25, 2017

San Clemente Quiet Zone / Wayside Horn Experience

Presentation to:

City of Encinitas Coastal Mobility and Livability Working Group

slide-2
SLIDE 2

2

Coastal Rail Corridor

Before the Beach Trail

slide-3
SLIDE 3

Coastal Rail Corridor

Before the Beach Trail

slide-4
SLIDE 4

4

Typical RR Crossings – Before

slide-5
SLIDE 5
  • 1998: Original Beach Trail design
  • 1999: Public and Council rejected design
  • 2000 – 2003: New design
  • 2003: Council approves new design; OCTA approves lease for trail
  • 2003: Protest Trail Application CPUC, BNSF, Caltrans Rail Division
  • 2004: Settlement agreement with CPUC and BNSF; also Caltrans Rail Division
  • 2004: Coastal Commission approval of Trail Plan
  • 2005: Start Trail Phase I construction
  • 2006: Finish Trail Phase I; FRA Train Horn Rule issued
  • 2007: Start Trail Phase II construction
  • 2008: Phase II trail complete
  • 2011: OCTA completed initial at-grade crossing safety upgrades; AWS initial testing
  • Dec 2011: QZ established at North Beach crossings
  • April 2014: AWS and additional safety improvements completed
  • August 2014: Submitted FRA waiver request
  • April 2015: FRA conditionally approved AWS
  • Early 2016: Additional fence completed
  • June 2016: Activated AWS

Timeline

slide-6
SLIDE 6

6

Beach Trail

slide-7
SLIDE 7

7

Beach Trail

slide-8
SLIDE 8

Beach Trail

slide-9
SLIDE 9

Beach Trail Fencing Options

slide-10
SLIDE 10

Other Beach Trail Fencing

slide-11
SLIDE 11
  • 16 total
  • 9 CPUC approved at-grade

Beach Trail Area RR Crossings

  • 2 crossings QZ
  • 7 crossings Wayside Horn
slide-12
SLIDE 12

Federal Railroad Administration (FRA) 2006 “Train Horn Final Rule”

  • Purpose
  • Improve Safety
  • Allow Quiet Zones
  • Oversight
  • Did not deal with “stand alone” pedestrian crossings
  • Did not make connection between pedestrian crossings as solution to

trespassing deaths

  • Result
  • San Clemente caught in Federal/State bureaucratic snafu

12

slide-13
SLIDE 13

Train Horn Noise!

slide-14
SLIDE 14

Train Horn Noise!

slide-15
SLIDE 15

Orange County Transportation Authority Rail Crossing Safety Program

  • Improved over 50 rail

crossings throughout OC

  • Funded mostly by Measure

M2 Half-Cent Countywide Sales Tax

  • 88% OCTA
  • 12% Local City Match

15

slide-16
SLIDE 16

North Beach North Beach Quiet Zone

slide-17
SLIDE 17

Potential Options to Obtain Quiet Zone for Other Crossings

  • “Bookend” at-grade crossings with two public

vehicular crossings

  • Designate Pier private crossing as public – qualify

most but not all at-grade crossings under a QZ

  • State and/or Federal legislation to allow QZ at

pedestrian crossings

  • Then pursued AWS via CPUC, nullified by legal action

17

slide-18
SLIDE 18

FRA Waiver Submittal Per FRA Rules of Practice 49 CFR Part 211

  • Presented three options
  • 1. Redefine length of Quiet Zone
  • 2. Modified Wayside Horn (Audible Warning System – AWS)
  • 3. Allow Quiet Zone w/o public vehicular crossing
  • FRA approved Option 2 with conditions

18

slide-19
SLIDE 19

19

San Clemente AWS

slide-20
SLIDE 20

20

San Clemente AWS

slide-21
SLIDE 21

21

San Clemente AWS

slide-22
SLIDE 22

22

El Portal

slide-23
SLIDE 23

FRA Required Fencing

slide-24
SLIDE 24

24

FRA Required Fencing

slide-25
SLIDE 25

FRA Required Fencing

slide-26
SLIDE 26

TOTAL COST Almost $23 million

  • Beach Trail incl. crossings: $15.2 million
  • Initial at-grade safety upgrades: $2.4 million
  • Two vehicle and one ped crossing
  • Remainder at-grade safety upgrades, AWS and

extra fencing: $5 million

  • 7 ped crossings
  • Ongoing insurance and O&M: $75-80k

26