DRAFT PUBLIC/STAKEHOLDER CONSULTATION #2 Dufferin Park Master Plan City of Brantford October 15, 2019 SESSION AGENDA DUFFERIN PARK MASTER PLAN ARRIVAL & SIGN-IN 5:00 OPENING REMARKS 5:15 WELCOME & INTRODUCTIONS 5:20 PRESENTATION


slide-1
SLIDE 1

PUBLIC/STAKEHOLDER CONSULTATION #2

October 15, 2019

City of Brantford

Dufferin Park Master Plan

DRAFT

slide-2
SLIDE 2

SESSION AGENDA

DUFFERIN PARK MASTER PLAN ARRIVAL & SIGN-IN OPENING REMARKS WELCOME & INTRODUCTIONS PRESENTATION NEXT STEPS CLOSING REMARKS 5:00 5:15 5:20 5:25 6:30 6:55

slide-3
SLIDE 3

PROJECT TEAM ORGANIZATION

L A N D S C A P E A R C H I T E C T S

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

The MBTW Group

Jon Joyce, Principal

Stakeholders

Lima Architects Inc.

DUFFERIN PARK MASTER PLAN

slide-4
SLIDE 4

PROJECT GOAL

DUFFERIN PARK MASTER PLAN

The goal of the study is to create a new, comprehensive Master Plan for Dufferin Park that will:

Effectively guide the future redevelopment of the Park. Ensure the Park and the amenities are developed in a way that is feasible and cohesive. Provide recommendations for implementation, including cost and phasing.

slide-5
SLIDE 5

Identify & Assess Existing Conditions Draft Concept Plans

Final Master Plan Consultation Framework Review Field Investigation

PIC #1 PIC #2 Analyze and Consolidate Feedback Preferred Concept Plan Detailed Evaluation Preliminary Evaluation

PROJECT TIMELINE

DUFFERIN PARK MASTER PLAN

WE ARE HERE

slide-6
SLIDE 6

AREA CONTEXT

DUFFERIN PARK MASTER PLAN

Site Boundary LEGEND

D u f f e r i n A v e n u e S t P a u l A v e n u e P a r k s i d e D r i v e Brant Avenue Preston Blvd. Palmerston Avenue
  • W. Ross

McDonald School For The Blind Christ The King School Lansdowne-Costain Public School

Margaret Chandler Heritage House Lawrence Street

D u f f e r i n T e n n i s & L a w n B

  • w

l i n g C l u b

B r a n t f

  • r

d G e n e r a l H

  • s

p i t a l

Ada Avenue
slide-7
SLIDE 7

SITE CONTEXT

DUFFERIN PARK MASTER PLAN

LEGEND Site Boundary TOTAL AREA

  • Tennis Court (6)
  • Parking Lot (±85 spaces)
  • Playground (climber & swings)
  • Lawn Bowling Green (2)
  • Ball Diamond
  • Junior Soccer Field (with goal

posts) 7.5 acres SIZE EXISTING FEATURES

D u f f e r i n A v e n u e S t P a u l A v e n u e J u n i
  • r
S
  • c
c e r F i e l d B a l l D i a m
  • n
d P a r k i n g L
  • t
T e n n i s C
  • u
r t s T e n n i s C
  • u
r t s L a w n B
  • w
l i n g L a w n B
  • w
l i n g P l a y g r
  • u
n d

Residential Low Density Christ The King School

  • W. Ross

McDonald School For The Blind Margaret Chandler Heritage House

E n t r y D r i v e
slide-8
SLIDE 8

EXISTING SITE FEATURES

DUFFERIN PARK MASTER PLAN

Dufferin Club

Dufferin Club Dufferin Club Tennis Courts Lawn Bowling Green Playground Swing Set Parking Area Junior Soccer Ball Diamond
slide-9
SLIDE 9

SUMMARY OF PIC #1

DUFFERIN PARK MASTER PLAN

Tuesday, May 23rd, 2019

  • 1. Project Team Welcome and Introductions
  • 2. Review of Site Context and Existing Conditions
  • 3. Exploration of Programming Possibilities
  • 4. Presentation of Design Study A, B & C
  • 5. Table Group Discussions
  • 6. Question & Answer Period

53

Participants at PIC #1

290

Comments

slide-10
SLIDE 10

DESIGN STUDY A

  • A. Axial
5 10 20 50m 1:1000

Park amenities are organized branching off of a central axis.

Storage W/C Drop Off

DUFFERIN PARK MASTER PLAN

I d e a l a l i g n m e n t
  • f
p r
  • p
  • s
e d c
  • u
r t s n
  • r
t h
  • s
  • u
t h t
  • a
l l
  • w
f
  • r
  • p
t i m a l p l a y v a l u e . Tennis (4) Tennis (4) Open Play Lawn Arrival Lawn Play Parking (32) Landscape Planting Landscape Buffer Shade Structure Gathering Area Potential Future Trail Connection Landscape Buffer Bio-swale Christ The King School
  • W. Ross McDonald
School For The Blind Margaret Chandler Heritage House Residential Low Density S t P a u l A v e n u e Shade Structure Berm Multi-Use Skills Court Heritage Plaque Potential Lawn Bowling Greens
slide-11
SLIDE 11

DESIGN STUDY B

  • B. Loop
5 10 20 50m 1:1000

Park amenities are organized around a looping trail.

DUFFERIN PARK MASTER PLAN

S t P a u l A v e n u e Tennis (6) Pickleball (4) Open Play Lawn Arrival Lawn Play Parking (32) W/C Storage Landscape Buffer Shade Structure Potential Future Trail Connection Christ The King School
  • W. Ross McDonald
School For The Blind Margaret Chandler Heritage House Residential Low Density I d e a l a l i g n m e n t
  • f
p r
  • p
  • s
e d c
  • u
r t s n
  • r
t h
  • s
  • u
t h t
  • a
l l
  • w
f
  • r
  • p
t i m a l p l a y v a l u e . Woodland Buffer Berm Berm Exercise Station Exercise Station Exercise Station Shade Structure Potential Lawn Bowling Greens Beach Volleyball Courts
slide-12
SLIDE 12

DESIGN STUDY C

  • C. Multiple Loops & Zones
5 10 20 50m 1:1000

Park amenities are grouped in zones along looping trails.

I d e a l a l i g n m e n t
  • f
p r
  • p
  • s
e d c
  • u
r t s n
  • r
t h
  • s
  • u
t h t
  • a
l l
  • w
f
  • r
  • p
t i m a l p l a y v a l u e . Tennis (6) Open Meadow/ Lawn Open Play Lawn Parking (40) Shade Structure Landscape Buffer Landscape Buffer Bio-swale Christ The King School
  • W. Ross McDonald
School For The Blind Margaret Chandler Heritage House Residential Low Density S t P a u l A v e n u e Pickleball (2) Open Play Lawn Viewing Lawn Storage W/C Waiting Wall with Sign/Plaque Multi-Use Skills Court Play Trellis/Gathering Area Mulch Path Drop Off

DUFFERIN PARK MASTER PLAN

Berm Berm Exercise Station Exercise Station Exercise Station
slide-13
SLIDE 13

PIC #1 QUESTIONS

DUFFERIN PARK MASTER PLAN

  • 1. What do you think the priorities should be for the park?
  • 2. What do you like about each of the Design Studies and why?
  • Design Study A
  • Design Study B
  • Design Study C
  • 3. Is there anything else you would like the design team to consider?

Participants at PIC #1 were asked the following questions:

slide-14
SLIDE 14

SOME OF WHAT WE HEARD

DUFFERIN PARK MASTER PLAN

Having the tennis courts split up is best

Plant trees to provide a screen/buffer

Like the open, green space for play

Like the pedestrian, walking loop Improved play area Washroom building

“ ”

Like the multi-use skills court

Concerned about noise from pickleball courts

Don’t like the berm along the street

Concerned about volleyball courts

slide-15
SLIDE 15

Sports Courts 37% Site Circulation 20% Buildings + Structures 14% Play Areas 11% Landscape + Buffers 9% Other 9%

SOME OF WHAT WE HEARD

DUFFERIN PARK MASTER PLAN

slide-16
SLIDE 16

SOME OF WHAT WE HEARD

DUFFERIN PARK MASTER PLAN

SPORTS COURTS

Tennis (42 comments)

  • Priority program element
  • 6-8 courts with separation (2 areas)
  • Viewing area (berm or bleachers)
  • Shade (not trees)
  • Tournament staging

Pickleball (34 comments)

  • Priority program element (rapid growth of sport)
  • 4 designated courts
  • Maximize separation from residential (noise)

Multi-use Court (11 comments)

  • Priority program element (flexible use)
  • Accommodate multiple sports / activities

Volleyball (12 comments)

  • Maintenance + operations concerns
  • Safety (cleanliness) concerns

Bocce (6 comments)

  • Positive program addition
  • Multi-generational activity opportunity

SITE CIRCULATION

Vehicular Access + Parking (29 comments)

  • Priority program element
  • Support for maintain existing entrance
  • Preference for more spaces (40+)
  • Support emergency services
  • Accessible

Pedestrian Walkways / Trails (17 comments)

  • Multi-use
  • Access throughout the park
  • Connections to park edges

Fitness Loop / Stations (13 comments)

  • Multi-generational activity opportunity
  • Promotes health and fitness
slide-17
SLIDE 17

SOME OF WHAT WE HEARD

DUFFERIN PARK MASTER PLAN

PLAY AREAS

Open Lawn (16 comments)

  • Provides flexible use
  • Allows for active and passive activities
  • Maximizes use of park
  • Picnic / events opportunities

Playground (9 comments)

  • Priority program element
  • Improved equipment (safe / accessible)

Splash Pad (7 comments)

  • Desirable element

BUILDINGS + STRUCTURES

Office Space (10 comments) Storage (9 comments) Washrooms (7 comments) Concession / Kitchen (3 comments) Change Rooms (2 comments)

OTHER

Flexible / Efficient Spaces (5 comments) Site Lighting (3 comments) Park Operations (2 comments) Lawn Bowling – remain (2 comments) Baseball – remain (2 comment)

slide-18
SLIDE 18

PIC #1

DESIGN STUDY A DESIGN STUDY B DESIGN STUDY C PREFERRED MASTER PLAN

PREFERRED MASTER PLAN

DUFFERIN PARK MASTER PLAN

slide-19
SLIDE 19

PREFERRED MASTER PLAN

DUFFERIN PARK MASTER PLAN

slide-20
SLIDE 20

Asphalt paved trail Multi-use court Open lawn area

PREFERRED MASTER PLAN

DUFFERIN PARK MASTER PLAN

New parking lot Accessible washroom & equipment storage Tennis courts Playground Shade structure with seating

A B C D E F

slide-21
SLIDE 21

PREFERRED MASTER PLAN

DUFFERIN PARK MASTER PLAN

Incorporate heritage plaque Matching roof line and pillars

slide-22
SLIDE 22
slide-23
SLIDE 23
slide-24
SLIDE 24
slide-25
SLIDE 25
slide-26
SLIDE 26
slide-27
SLIDE 27

PHASING STRATEGY

DUFFERIN PARK MASTER PLAN

slide-28
SLIDE 28

PHASE 1

DUFFERIN PARK MASTER PLAN

  • Demolition of existing softball;
  • Construction of new tennis courts, including Shade Structure;
  • Construction of new lawn bowling (off-site)
  • Installation of area specific landscape and site furniture.
slide-29
SLIDE 29

PHASE 2

DUFFERIN PARK MASTER PLAN

  • Construction of Play Area (including St Paul Avenue edge);
  • Construction of Multi-use Skills Court;
  • Construction of playground Shade Structure;
  • Construction of pedestrian walkways;
  • Installation of area specific landscape and site furniture.
  • Demolition of existing Dufferin Club;

Demolition of existing lawn bowling;

  • Demolition of existing Tennis Courts;

Demolition of existing Playground;

slide-30
SLIDE 30

PHASE 3

DUFFERIN PARK MASTER PLAN

  • Demolition of a portion (approximately half) of the existing parking lot;
  • Construction of Universal Washroom and Storage Building (470ft2), including servicing upgrades;
  • Construction of Open Lawn Area;
  • Construction of pedestrian walkways / connections;
  • Installation of area specific landscape and site furniture.
slide-31
SLIDE 31

PHASE 4

DUFFERIN PARK MASTER PLAN

  • Demolition of remaining existing parking lot;
  • Construction of new Parking Area;
  • Demolition and construction would ideally occur during Fall, when park facility use decreases;
  • Construction of pedestrian walkways / connections;
  • Installation of area specific landscape and site furniture.
slide-32
SLIDE 32

PRELIMINARY COST SUMMARY

DUFFERIN PARK MASTER PLAN

PHASE 1 : $845,000

  • Demolition of existing softball
  • New tennis courts, and shade structure
  • Installation of landscape and site furniture

PHASE 2 : $840,000

  • Demolition of existing lawn bowling
  • Demolition of existing Tennis Courts
  • Demolition of existing playground
  • Demolition of Dufferin Club building
  • Construction of Play Area
  • Construction of Multi-use Skills Court
  • Construction of playground Shade Structure
  • Construction of pedestrian walkways
  • Installation of landscape and site furniture

PHASE 3 : $660,000

  • Demolition of a portion of the existing parking lot
  • Universal Washroom and Storage Building (470ft2)
  • Construction of Open Lawn Area
  • Construction of pedestrian walkways
  • Installation of landscape and site furniture

PHASE 4 : $395,000

  • Demolition of remaining existing parking lot
  • Construction of new Parking Area
  • Construction of pedestrian walkways
  • Installation of landscape and site furniture

T

TOTAL : $2,740,000.00 (Including contingencies)

slide-33
SLIDE 33

NEXT STEPS

DUFFERIN PARK MASTER PLAN

slide-34
SLIDE 34

Thank You!

Contact: Email: parksandtrails@brantford.ca Phone: (519) 759-4150 ext. 5524