Public Information & Environmental Impact Statement Scoping Meeting Huntley to Wilmarth Transmission Line
Docket CN‐17‐184/TL‐17‐185 | https://mn.gov/puc
Public Information & Environmental Impact Statement Scoping - - PowerPoint PPT Presentation
Public Information & Environmental Impact Statement Scoping Meeting Huntley to Wilmarth Transmission Line Docket CN 17 184/TL 17 185 | https://mn.gov/puc Huntley to Wilmarth Transmission Line Agenda 1. Overview of Meeting and
Docket CN‐17‐184/TL‐17‐185 | https://mn.gov/puc
4/11/2018 Commission Docket CN‐17‐184/TL‐17‐185 | https://mn.gov/puc 2
4/11/2018 Commission Docket CN‐17‐184/TL‐17‐185 | https://mn.gov/puc 3
4/11/2018 Commission Docket CN‐17‐184/TL‐17‐185 | https://mn.gov/puc 4
Application Filed & Accepted as Complete Scope of Environmental Impact Statement (EIS) Draft EIS developed and issued by DOC Contested Case Hearing Closed Final EIS Developed and Issued by DOC Report from the Administrative Law Judge Decision by the Public Utilities Commission Contested Case Hearing before an Administrative Law Judge Public Information & Environmental Scoping Meeting Public Meeting and Comment Period on Draft EIS Advisory Taskforce
4/11/2018 Commission Docket CN‐17‐184/TL‐17‐185 | https://mn.gov/puc 5
4/11/2018 Commission Docket CN‐17‐184/TL‐17‐185 | https://mn.gov/puc 6
4/11/2018 Commission Docket CN‐17‐184/TL‐17‐185 | https://mn.gov/puc 7
4/11/2018 Commission Docket CN‐17‐184/TL‐17‐185 | https://mn.gov/puc 8
4/11/2018 Commission Docket CN‐17‐184/TL‐17‐185 | https://mn.gov/puc 9
Blue area is MISO territory
The project is needed to relieve congestion on the transmission grid in southern Minnesota that is inhibiting low‐cost electricity from generation facilities in the area, including wind farms, from reaching customers.
– Gather data – Consult with stakeholders – Generate route options – Public meetings (spring/summer 2017) – Refine route options (Fall 2017)
150 foot easement required