SLIDE 1
Public Engagement for Planning Trails Josh Garcia Trails Program - - PowerPoint PPT Presentation
Public Engagement for Planning Trails Josh Garcia Trails Program - - PowerPoint PPT Presentation
Public Engagement for Planning Trails Josh Garcia Trails Program Coordinator Overview JCOS Background Trail Development Guidebook Trail Proposal Process Lessons Learned Trail Proposal Process Regional Coordinators Natural Planning
SLIDE 2
SLIDE 3
SLIDE 4
SLIDE 5
SLIDE 6
Trails Proposal Process
Planning Natural Resources Regional Coordinators Visitor Relations Coordinator Trails Team Rangers Trails Program Coordinator
Trail Proposal Process
SLIDE 7
Evaluation Criteria
Natural Resources Visitor Experience Readiness Timeliness
SLIDE 8
Submittal Period Opens
Jan 12- Feb 23, 2018 Outreach:
Website Social Media Trails Talk Forum MTB Groups
SLIDE 9
Proposals Received
66 Proposals
14 JCOS Staff 32 MTB Advocacy Groups
159 Miles of Trail Proposed!
SLIDE 10
MTB Skills Parks
SLIDE 11
Trail Rerealignments
SLIDE 12
Regional Trails
SLIDE 13
Initial Evaluation Team Evaluations Evaluation Workshops Final Recommendation Workshop Proposal Responses
Evaluation Process
SLIDE 14
Outcomes
Category # of Proposals Percent Miles of Trail Approved for Design/Implementation 5 8% 5.06 Advance for Further Study 35 53% 114.24 Forego 26 39% 40.45
SLIDE 15
GIS Web Map
SLIDE 16
Lessons Learned
SLIDE 17
Better Outreach
SLIDE 18
Improved Relationships
SLIDE 19
SLIDE 20
MTB Skills Courses
SLIDE 21
Improving the Process
SLIDE 22
Provide Sideboards
SLIDE 23
vs.
SLIDE 24