1
ProtoDUNE SP CPA and FC ProtoDUNE SP CPA and FC QA/QC Plan QA/QC - - PowerPoint PPT Presentation
ProtoDUNE SP CPA and FC ProtoDUNE SP CPA and FC QA/QC Plan QA/QC - - PowerPoint PPT Presentation
ProtoDUNE SP CPA and FC ProtoDUNE SP CPA and FC QA/QC Plan QA/QC Plan Jonathan Asaadi University of Texas Arlington 1 Overview Overview This talk is meant to convey some of the lessons learned from MicroBooNE and LArIAT This is
2
Overview Overview
- This talk is meant to convey some of the
lessons learned from MicroBooNE and LArIAT
- This is also trying to outline various checks,
tests, controls, and assurances that should be in place
– Many of these tests are planned / being done / will
be done during installation
– Not a fully exhaustive list and will likely need to be
expanded as different aspects of the detector come into sharper focus
3
Component Tests/Procedure Notes
Large metal components for the field cage and cathode Soaking bath and rinse to remove grease and large pieces of F.O.D. Requires a place large enough to allow for cleaning and drying
- f components prior to
assembly Drilled holes in all components Identifying and removing metal shavings, burrs, Need to check any internal components of large machined parts Small component (elbows, screws, etc) cleaning Ultra sonic bath soak Need to keep track of which components go where and repackaging after cleaning
QA/QC related to cleanliness QA/QC related to cleanliness
4
QA/QC related to cleanliness QA/QC related to cleanliness
- The various components of the cathode
and field cage will come in many pieces
– Rolled form field cage tubes – G10 I beams – Plastic Caps – etc…
- Assuring these pieces meet cleanliness
requirements before assembly is important
– For MicroBooNE and LArIAT this required having
access to series of ultra-sonic baths for small components
– Larger soaking baths (simple green cleaning
solution) for large metal pieces (field cage rings)
– Checking for metal burs, foreign object debris,
and grease before moving the parts to
Soaking bath for MicroBooNE Soaking bath for MicroBooNE Field Cage Tubes Field Cage Tubes
5
QA/QC related to cleanliness QA/QC related to cleanliness
MicroBooNE DocDB 2259 can be made available to help
6
QA/QC related to components QA/QC related to components
Component Tests/Procedure Notes
Threaded components Application of anti-galling coating MicroBooNE used moly-coat sprayed on all bolts Interferences between mating components Ensuring the correct bolt/nut/washer is installed in the correct place There are often many very similar components and the need to have them (re)labeled following cleaning / coating and cataloged is important Identifying correct bolt head types Need E-Field studies for various types to minimize potential source for breakdown
7
QA/QC related to components QA/QC related to components
- The need for cleaning of bolts
(applying anti-galling material),
- rganizing bolts / head types is
important
– We had quite a few examples of
bolts galling without moly-coat
– Need to be careful of which bolts
(size and head type) apply
- Need a comprehensive list of
all the bolts prior to installation
– Will help with vendor availability – All the parts need to be cleaned,
coated, and cataloged for installation….so knowing what they are in advance helps
Application of moly-coat to Application of moly-coat to MicroBooNE screws MicroBooNE screws E-field study for different E-field study for different bolt head components bolt head components
8
QA/QC related to components QA/QC related to components
- Following the cleaning and
coating of all the small components, making sure they are identified and cataloged for use during installation is and important control to have in place
– On MicroBooNE and LArIAT we had a
few instances where similar enough looking components were installed in the wrong place
– These were caught during later test
fits, but a better control system could have prevented this
- For something as large as
(proto)DUNE and being built in different places, this a system of checks should be in place early
MicroBooNE TPC during MicroBooNE TPC during installation with very tight installation with very tight clearances clearances Similar enough bolt initially Similar enough bolt initially installed in the wrong position installed in the wrong position
9
QA/QC related to cathode QA/QC related to cathode
Component Tests/Procedure Notes
Flatness of assembled cathode Survey test done during construction and following installation This can be a time consuming process, but can be an essential driver of the physics so needs to be accounted for Electrical connectivity between cathode components Resistive measurement (or possibly small current measurement) The application of resistive coating will likely require a bit more thought to verify electrical connection Tests of high voltage bus Stand-alone high voltage tests Assembled and installed cryo- tests The details of this component still remain a bit less clear to me...so the details of the tesing here are not thought out yet
10
QA/QC related to cathode QA/QC related to cathode
- The MicroBooNE cathode was a similar
construction (panels and tubes)
- Ensuring hole patterns (or maybe slot
locations) line up for protoDUNE’s much larger structure will make installation easier
- Alignment measurements take time to do
and should build in sufficient weeks for an iterative align/measure/shim/repeat
MicroBooNE achieved a cathode flatness of MicroBooNE achieved a cathode flatness of +/- 6 mm over the 10.3 meter length +/- 6 mm over the 10.3 meter length
11
QA/QC related to cathode QA/QC related to cathode
- Testing of both the
mechanical and electrical performance of the HV-Bus should be done prior to installation
– These tests are likely best both
warm and cold
- Following installation, the
verification of the HV-bus will need to be considered in the QA/QC plan
– Likely as part of the overall CPA
checkout post installation
12
QA/QC for resistor divider boards QA/QC for resistor divider boards
Component Tests/Procedure Notes
Test of individual resistor and varistor components High voltage tests to verify behavior and function Tests should be done warm and cold and results should be cataloged by components Matching components to ensure correct tube-to-tube resistance Resistive measurement (or possibly small current measurement) Test should be done warm and cold Resistors and varistor tests Spark tests and clamping behavior Done for MicroBooNE and LArIAT in the cold...but this was more for safety reasons Testing of the PCB board Destructive HV tests as well as baseline HV performance tests We found problems with the boards in LArIAT and had to go to directly soldering components onto the field cage
13
QA/QC for resistor divider boards QA/QC for resistor divider boards
- For MicroBooNE and
LArIAT we built a rig to perform QC tests of the resistors at 100% of their
- perating voltages in the
cold (open air argon dewar)
– A similar rig was used for
destructive tests because we could force the potential to ground quickly (simulating a spark condition)
14
- The “Lighting Wheel”
was a rig that Hans Jostlein built for us that allowed us to give ~2 Joule sparks to resistor and varistor components in the cold as well as test their clamping voltage and resistance after the application of sparking
- Allowed us to pick out
varistors and resistors which performed the best following the tests
MicroBooNE DocDB 3397 provides details of the tests performed
QA/QC for resistor divider boards QA/QC for resistor divider boards
15
QA/QC during initial assembly QA/QC during initial assembly
Component Tests/Procedure Notes
Mechanical test fits to look for interferences High voltage tests to verify behavior and function This assumes the cryostat is ready before the detector is complete….but could be done before actual installation if the schedule allows Verify electrical conductivity of the cathode High voltage tests to verify behavior and function (Need to think how the resistive coating complicates this measurement) Verify the resistor divider network Apply ~1 kV to the cathode in incremental steps and check the current is as expected as well as verify the voltage near the APA
16
QA/QC during initial assembly QA/QC during initial assembly
- In MicroBooNE and LArIAT we
did a number of “mock” installations and dry runs
– TPC test fits – Electronics and PMT mounting
using mechanical spares
– Cable routing and interference
testing
- Allowed to catch problems
early and anticipate changes to installation plans before the actual detector was ready to go
- The same extent of tests may
not be possible for protoDUNE, but should be considered
Mechanical fit tests done with Mechanical fit tests done with “dummy” motherboards on LArIAT “dummy” motherboards on LArIAT
TPC test fits and moch cable routing done TPC test fits and moch cable routing done with MicroBooNE and LArIAT with MicroBooNE and LArIAT
17
- Once the cathode / field cage
and APA’s are installed, the electrical network should be verified
– Testing the current seen when
~1kV is applied to the cathode
- “Did we connect everything
correctly?”
– Measuring the impedance
between the field cage and the cryostat
– Measuring the capacitance in the
RC network setup by the field cage
QA/QC during initial assembly QA/QC during initial assembly
MicroBooNE 1kV MicroBooNE 1kV test of the field test of the field cage network post cage network post installation installation
18
- This list here is by no means exhaustive
– Instead meant to help during the planning stage based on
previous experience building and installing LArTPC’s
- Many of the tests mentioned here have complete
testing documents that were done for MicroBooNE
– I am happy to help in the transformation of these
documents into ones for protoDUNE as well as work with
- thers in the development of new testing procedures for the
new components
- E.g. Beam plug, HV-Bus, etc….
- Thinking through these things now does make the
process go faster
– New things will pop up during installation, but if you’ve