PROPOSED WAIBLE CREEK TRUNK REIMBURSEMENT DISTRICT PUBLIC HEARING February 18, 2020 Elle Allan, Development Services Supervisor Utility Operations & Services Department PURPOSE Inform Board about request to form the Waible Creek


slide-1
SLIDE 1

PROPOSED WAIBLE CREEK TRUNK REIMBURSEMENT DISTRICT PUBLIC HEARING

February 18, 2020 Elle Allan, Development Services Supervisor Utility Operations & Services Department

slide-2
SLIDE 2

PURPOSE

  • Inform Board about request to form the

Waible Creek Trunk Reimbursement District (RD)

  • Review the project boundaries and cost

distribution methodology

  • Hear testimony from interested parties
  • After considering testimony, adopt the

R&O to form the Waible Creek Trunk RD

slide-3
SLIDE 3

WAIBLE CREEK TRUNK SANITARY SEWER IMPROVEMENTS

slide-4
SLIDE 4

PROJECT COST ELIGIBILITY

  • Eligible RD Costs
  • 12-inch diameter sewer, and smaller
  • Offsite and downstream of Development
  • Non-Eligible Costs
  • Upsize for greater than 12-inch diameter
  • Onsite of Development
slide-5
SLIDE 5

PROPOSED RD COST DISTRIBUTION METHODOLOGY

slide-6
SLIDE 6

QUESTIONS HEARD FROM BENEFITED PROPERTIES

  • When is payment of RD Charge due?
  • Due at time of permit for connection to sewer
  • 10-year sunset clause
  • Why are other nearby properties not included?
  • Benefited Properties must have a direct connection
  • Other nearby properties will gain indirect benefit
  • Can the RD Charge be apportioned in the future?
  • This is an option; requires application & public hearing
slide-7
SLIDE 7
  • After considering testimony, adopt the

Resolution and Order to establish the Waible Creek Trunk Reimbursement District