proposed complete streets improvements
play

Proposed Complete Streets Improvements S. Walter Reed Drive from 5 th - PowerPoint PPT Presentation

Proposed Complete Streets Improvements S. Walter Reed Drive from 5 th Street S. to 9 th Road S. Penrose & Arlington Heights Civic Association 2015 Northbound on S Walter Reed Dr March 19, 2016 9:00 AM at Thomas Jefferson Theatre Project


  1. Proposed Complete Streets Improvements S. Walter Reed Drive from 5 th Street S. to 9 th Road S. Penrose & Arlington Heights Civic Association 2015 Northbound on S Walter Reed Dr March 19, 2016 9:00 AM at Thomas Jefferson Theatre

  2. Project Location

  3. Where we are in the process… Project Phases Scope & Concept Engineering Design Construction Development • Plans are at 60% complete • Working on obtaining real estate easements • Working through 60% design comment resolution

  4. Project Purpose & Objectives • Create permanent improvements to painted road diet and to address existing speeding issues • Full complete streets project • Our intention is to move forward to construction as soon as possible • To implement as many of the scope elements as possible • If we are unable to obtain easements, the improvements that require those easements will be removed from the project

  5. Major Scope Elements & Improvements • Major intersection redesign at 5 th St and 9 th St. • Driveway and access redesign at 8 th St S • Intersection nubs and drainage improvements • New bus stops • Landscaping in the raised medians and possibly large curb extensions • Paving the section needed for widening • Install new pavement markings and signage • Replacing cracked sections of sidewalk

  6. Critical Easements • 12 Temporary Construction • Working with Engineering and Real Estate • Will be notifying and speaking with property owners very soon

  7. Other Adjacent Projects • Separate from S. Walter Reed Complete Street Project • Bikeshare station in front of Patrick Henry at 8 th Street • Bioretention at 5 th Street (NW) and 9 th Street (SE) • Traffic signal at 7 th Street • Traffic signal at 9 th Street

  8. Next Steps & Milestones – • Civic engagement of 60% plans – March 2016 • Utility relocation coordination – ongoing. throughout 2016 • Easement acquisition – ongoing. throughout 2016 • 90% design plans – August 2016 • Informational presentation of 90% plans – September 2016 • 100% design plans – November 2016 • County construction permits – January 2017 • Procurement & Advertisement – December to March 2017 • Construction award – May 2017 • Construction completion – June 2017 to March 2018

  9. Questions or Comments?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend