Proposed Complete Streets Improvements S. Walter Reed Drive from 5 th - - PowerPoint PPT Presentation

proposed complete streets improvements
SMART_READER_LITE
LIVE PREVIEW

Proposed Complete Streets Improvements S. Walter Reed Drive from 5 th - - PowerPoint PPT Presentation

Proposed Complete Streets Improvements S. Walter Reed Drive from 5 th Street S. to 9 th Road S. Penrose & Arlington Heights Civic Association 2015 Northbound on S Walter Reed Dr March 19, 2016 9:00 AM at Thomas Jefferson Theatre Project


slide-1
SLIDE 1

Proposed Complete Streets Improvements

  • S. Walter Reed Drive from 5th Street S. to 9th Road S.

2015 Northbound on S Walter Reed Dr

Penrose & Arlington Heights Civic Association March 19, 2016 9:00 AM at Thomas Jefferson Theatre

slide-2
SLIDE 2

Project Location

slide-3
SLIDE 3

Where we are in the process…

Scope & Concept Development Engineering Design Construction

Project Phases

  • Plans are at 60% complete
  • Working on obtaining real estate easements
  • Working through 60% design comment resolution
slide-4
SLIDE 4

Project Purpose & Objectives

  • Create permanent improvements to painted road diet and to address

existing speeding issues

  • Full complete streets project
  • Our intention is to move forward to construction as soon as possible
  • To implement as many of the scope elements as possible
  • If we are unable to obtain easements, the improvements that require

those easements will be removed from the project

slide-5
SLIDE 5

Major Scope Elements & Improvements

  • Major intersection redesign at 5th St and 9th St.
  • Driveway and access redesign at 8th St S
  • Intersection nubs and drainage improvements
  • New bus stops
  • Landscaping in the raised medians and possibly large curb extensions
  • Paving the section needed for widening
  • Install new pavement markings and signage
  • Replacing cracked sections of sidewalk
slide-6
SLIDE 6
slide-7
SLIDE 7
slide-8
SLIDE 8
slide-9
SLIDE 9
slide-10
SLIDE 10

Critical Easements

  • 12 Temporary Construction
  • Working with Engineering and Real Estate
  • Will be notifying and speaking with property owners very soon
slide-11
SLIDE 11

Other Adjacent Projects

  • Separate from S. Walter Reed Complete Street Project
  • Bikeshare station in front of Patrick Henry at 8th Street
  • Bioretention at 5th Street (NW) and 9th Street (SE)
  • Traffic signal at 7th Street
  • Traffic signal at 9th Street
slide-12
SLIDE 12

Next Steps & Milestones –

  • Civic engagement of 60% plans – March 2016
  • Utility relocation coordination – ongoing. throughout 2016
  • Easement acquisition – ongoing. throughout 2016
  • 90% design plans – August 2016
  • Informational presentation of 90% plans – September 2016
  • 100% design plans – November 2016
  • County construction permits – January 2017
  • Procurement & Advertisement – December to March 2017
  • Construction award – May 2017
  • Construction completion – June 2017 to March 2018
slide-13
SLIDE 13

Questions or Comments?