Project Update WCCC February 2018 TERRAMIN AUSTRALIA LIMITED SLIDE - - PowerPoint PPT Presentation

project update wccc february 2018
SMART_READER_LITE
LIVE PREVIEW

Project Update WCCC February 2018 TERRAMIN AUSTRALIA LIMITED SLIDE - - PowerPoint PPT Presentation

Project Update WCCC February 2018 TERRAMIN AUSTRALIA LIMITED SLIDE No. 1 Project Update EPBC Act Referral Federal government assessed and determined Not a controlled action Not conditional Received 7 th February 2018


slide-1
SLIDE 1

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 1

Project Update – WCCC February 2018

slide-2
SLIDE 2

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 2

Project Update

 EPBC Act Referral – Federal government assessed and determined “Not a controlled action’’

  • Not conditional
  • Received 7th February 2018
  • Endangered orchids and listed ecosystems within the proposed ML not

impacted by mining operations – aspects such as groundwater, dust, etc assessed  CSIRO – confirmed will continue through 2018 – Phase 2

  • No final report yet but Kieren to present results (April 2018)
slide-3
SLIDE 3

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 3

Community participation: Anchor to Pulse 4 (ALL)

Responded

294

Invited

444

Response Rate

66%

Completed all 4 surveys

211

  • Strong engagement in the 2017

CSIRO Reflexivity process – 211 people completed all five surveys across 12 months+

slide-4
SLIDE 4

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 4

Mining Lease Proposal (MLP)

 No feedback from Government regarding Managed Aquifer Recharge  This has impacted our targeted timeframe  We will update WCCC on targeted timeframe when we receive advice from the Government  Terramin will release draft sections of the Mining Lease Proposal to the WCCC when confirmation from Government that Chapter conforms with the Ministerial Determination and applicable legislation  Our aim has been in the interim is to have the WCCC informed of the proposed MLP contents

slide-5
SLIDE 5

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 5

Outcomes and Measurable Criteria

 Outcomes and Outcome Measurable Criteria

  • So far WCCC has received
  • Groundwater
  • Surface water
  • Noise
  • Vibration
  • Air Overpressure
  • Traffic
  • Fire
  • Air Quality
  • Outcomes are set at Mining Lease Proposal (MLP) stage
  • Measurable criteria developed from now and over the Programme for Environmental

Protection and Rehabilitation (PEPR) phase, - AFTER the MLP (if approved)

  • Government guidelines on how to propose outcome measurable criteria – link in

meeting minutes

  • Proposed outcomes will form basis of Lease Conditions
slide-6
SLIDE 6

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 6

Outcomes and Lease Conditions – AZM Example how the conditions developed

ML PROPOSED OUTCOME “Stabilise disturbed areas and prevent sediment from leaving the site” ML LEASE CONDITION “The Lessee must, in constructing and operating the lease and post mine closure, stabilise disturbed areas and prevent sediment from leaving the site” Measureable Criteria developed to demonstrate compliance with ML Outcome and Lease condition

slide-7
SLIDE 7

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 7

Outcome – proposed and finalised at Mining Lease Proposal Measureable Criteria – draft now but finalised through PEPR stage

slide-8
SLIDE 8

TERRAMIN AUSTRALIA LIMITED

Air Quality – Dust Control

slide-9
SLIDE 9

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 9

Types of Dust

slide-10
SLIDE 10

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 10

Baseline Monitoring at BIHGP

 What we measured for

  • Total Suspended Particulates (TSP) - <50 micron
  • PM10 - <10 micron
  • Deposited Dust (Total Insoluble Matter) – any size
  • Background metals
slide-11
SLIDE 11

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 11

Dust - compliance

 Dust is a recognised nuisance  Environmental Protection (Air Quality) Policy (EP Act) sets the standards for airborne dust  No Total Suspended Particulates / Dust deposition standards for SA

  • Standard practice - NSW Approved Methods for Modelling and

Assessment of Air Pollutants

Ind ndic icator Pro Projec ect t Ob Objec ectiv ive Aver eraging Per Perio iod Envir ironmental l Valu lue TSP 90 µg/m³ 24-hour Amenity PM10 50 µg/m³ 24-hour Health PM2.5 25 µg/m³ 24-hour Health 8 µg/m³ Annual Dust deposition (Total Insoluble Matter) 4 g/m²/month (maximum total deposited dust level) Annual Nuisance/ Ecological 2 g/m2/month (maximum increase in deposited dust level )

slide-12
SLIDE 12

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 12

slide-13
SLIDE 13

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 13

Baseline

 Updated Baseline Reports in 2017  PM10 more variable than expected baseline results for 2017

  • Strathalbyn range 0.2 – 30.6 µg/m³
  • Woodside range 10.7 – 78.9 µg/m³
  • EPA 2006 Woodside 6 - 90 µg/m³

 Total Suspended Particulates variable with seasonal activities  Total Dust Deposition similar to other agricultural areas

  • 4 grams/m2/month is proposed for total

maximum including background (from

  • ther operations)
slide-14
SLIDE 14

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 14

Sources of Potential Dust

 Dump trucks on surface – Mullock and Ore  Integrated Mullock Landform  Disturbed and cleared land  Construction sites  Vehicle emissions  Ventilation fans

slide-15
SLIDE 15

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 15

Management of Potential Dust

 Enclosing, vegetation, spraying, all examples of how to control

slide-16
SLIDE 16

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 16

Site Design – increase vegetation moisture

 Irrigation systems  Perennial vegetation – green all year  Significant reduction of grasses with high fuel loads – phalaris  Native C3 and C4 grasses

slide-17
SLIDE 17

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 17

Monitoring of Potential Dust

 Beta Attenuation Particulate Monitors – “BAM Units”

  • Live
  • Link to weather station
  • Can have alert systems in place
  • Example – wind direction, wind speed and increased dust can set
  • ff early warning alarms to change activities
  • Options – more mitigation or alter/stop “source” activity

 High Volume dust samplers – filters to go laboratory  Dust Deposition Gauges – monitor total dust over monthly average

slide-18
SLIDE 18

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 18

Example – Olympic Dam

 OUTCOME: No adverse impacts to public health as a result of fugitive particulate emissions from BHP Billiton’s expansion activities at Olympic Dam  Real time monitoring with weather station – rapid response  Trigger Action Response Plan  1. Relocating activities – more distance to sensitive receptor  2. Redirecting mine rock haulage activities  3. Increasing frequency of dust suppression activities  4. Cessation of operations

slide-19
SLIDE 19

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 19

Bird in Hand – Air Quality Strategies

 Water carts, sprinklers on exposed and disturbed soils (inc. IML)  Vegetate exposed soils as soon as practical, hydromulching, cover all soil bunds with vegetation (reduces air velocity on soil)  Ore – enclosed in silo rather than on ground  Tip points fully enclosed  Maintenance of haul roads with regular application of dust suppressant spray  Asphalted roads  Transfer of dry materials must be covered – silo, covered trucks to Strathalbyn, etc.

slide-20
SLIDE 20

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 20

Proposed outcomes

  • 1. No nuisance impacts to local residents from dust generated by construction, mining or closure activities.
  • 2. No public health impacts to local residents from dust generated by construction, mining or closure activities.
  • 3. No loss of productivity on properties surrounding the mining lease from dust generated by construction, mining or

closure activities.

  • 4. No permanent loss of abundance, condition or diversity of native vegetation (as defined by Native Vegetation Act

1991) on or off the lease during construction, operation and post mine completion through;

  • clearance,
  • dust/contaminant deposition,
  • fire,
  • reduction in water supply, or
  • ther damage,

unless prior approval under Native Vegetation Act 1991 and Native Vegetation Regulations 2017 is obtained.

slide-21
SLIDE 21

TERRAMIN AUSTRALIA LIMITED

Traffic Management of Heavy Vehicles

slide-22
SLIDE 22

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 22

Tonkin Consulting  Type of road haul truck  Analysis of road haul truck movements  Analysis of haulage routes

  • Suitability
  • Safety
  • Existing conditions

 Haulage Exclusions - understanding

  • Peak traffic periods
  • Overnight exclusion
  • Disaster plan – bushfire, accident, flood, etc.
  • Community events and other restrictions

Proof of Traffic concepts

slide-23
SLIDE 23

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 23

Exi Existin ing Traffic ic Volu

  • lumes on

n Pf Pfeif iffer Roa

  • ad

Apr pril il 2014 2014 Nov Nov 14 14 Fe Feb 20 2015 15 Nov Nov-Dec 2017 2017 24 Hours 1036 953 955 944 Cars 867 762 857 879 Heavy vehicles 170 190 99 64 AM Peak (hour) 86 72 68 78 PM Peak (hour) 92 90 79 94

Existing Pfeiffer Road Traffic

 Traffic volumes are highly variable  Always activities on Pfeiffer Road

  • Vintage + bottling
  • Expansions of current

businesses

  • New owners and

developments

  • Hay and cattle
  • Strawberries and apples
  • Crush, Winter Reds, events
  • Polo tournaments
slide-24
SLIDE 24

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 24

What type & how many vehicles?

 Ore haulage vehicles – 19m Rigid Truck and Dog;

12 loads = 24 movements per day

 Other supply trucks – Rigid Trucks thru’ to Semi-Trailers

2 loads = 4 movements per day

 Company vehicles - Utes/SUV’s

5 vehicles = 10 movements per day

 Employee vehicles – Cars

15 cars per shift (2 shifts per day) = 60 movements per day

 Visitors – Cars

3 cars = 6 movements per day

TOTAL movements per day = 104

slide-25
SLIDE 25

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 25

19m Truck and Dog – General Access Vehicle

slide-26
SLIDE 26

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 26

Management

 Safety is top priority  Dedicated access to site on Pfeiffer Road –

  • Wide enough with good sightlines
  • Dpt. Planning, Transport and Infrastructure approved design

 Exclusion times – no ore haulage between BIH and Angas

  • 10pm – 6am (excludes night)
  • 6am – 9am (excludes commuter traffic and school drop off)
  • 3pm – 4.30pm (excludes school pick up and buses)

 Reduced speed limit for Terramin trucks on Pfeiffer Road – 60km/hr  Dash cams and GPS  All other strategies listed on Issues paper

slide-27
SLIDE 27

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 27

slide-28
SLIDE 28

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 28

Potential Routes

Woodside to Strathalbyn - 3 possible routes:

 Route 1 – via Nairne Road, Old Princes Hwy, Bald Hills Rd, Hartman Rd, Paech Rd, Wellington Rd & Callington Rd (35 mins)  Route 2 – via Nairne Rd, South Eastern Freeway and Callington Rd (40 mins) – preferred

  • Opportunity to upgrade Nairne/Pfeiffer Rd intersection with
  • ther stakeholders

 Route 3 – via Nairne Rd, Nairne Township, Old Princes Hwy and Callington Rd (45 mins)

slide-29
SLIDE 29

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 29

slide-30
SLIDE 30

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 30

Proposed outcome No unauthorised damage to public infrastructure as a result of mining operations No traffic accidents occur involving the public and mine traffic that could have been reasonably prevented

slide-31
SLIDE 31

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 31

Monitoring – Draft Outcome Measurable Criteria

 Independent investigation of all traffic accidents demonstrates that the mine

  • perator could not have reasonably prevented the accident from occurring.

 Investigation of all public infrastructure related complaints demonstrates that the Mine Operator did not cause or could not reasonably have prevented the incident from occurring;  All public infrastructure related complaints were acknowledged within 48 hours and closed out within 14 days to the satisfaction of the complainant or as agreed with the Chief Inspector of Mines.  Truck driver check sheets will be completed for all ore trucks leaving site to demonstrate loads are covered and in compliance with agreed hours of operation.  Daily inspection of entry/exit points demonstrates no build-up of dragout material at the site entrance on Pfeiffer Road is occurring.

slide-32
SLIDE 32

TERRAMIN AUSTRALIA LIMITED

Bushfire Prevention and Emergency Response Planning

slide-33
SLIDE 33

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 33

Bushfire Prevention - Currently

 Rotational grazing – 5 paddocks  Slashing of other fencelines/paddocks  Gradual replacement of introduced pasture grasses with native C3 and C4 perennial to reduce fire fuel loading

  • Exotic grasses (phalaris &

cocksfoot) 17-27 t/Ha

  • Native grasses (C3/C4) 1.5-8 t/Ha.
  • From Upper Torrens catchment group

 Irrigation system in summer increases soil and plant moisture  Water truck onsite

slide-34
SLIDE 34

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 34

Bushfire Prevention - Currently

 Rotational grazing – 5 paddocks  Slashing of other fencelines/paddocks  Gradual replacement of introduced pasture grasses with native C3 and C4 perennial to reduce fire fuel loading

  • Exotic grasses (phalaris &

cocksfoot) 17-27 t/Ha

  • Native grasses (C3/C4) 1.5-8 t/Ha.
  • From Upper Torrens catchment group

 Irrigation system in summer increases soil and plant moisture  Water truck onsite

slide-35
SLIDE 35

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 35

Bushfire Prevention - Currently

 Rotational grazing – 5 paddocks  Slashing of other fencelines/paddocks  Gradual replacement of introduced pasture grasses with native C3 and C4 perennial to reduce fire fuel loading

  • Exotic grasses (phalaris &

cocksfoot) 17-27 t/Ha

  • Native grasses (C3/C4) 1.5-8 t/Ha.
  • From Upper Torrens catchment group

 Irrigation system in summer increases soil and plant moisture  Water truck onsite

slide-36
SLIDE 36

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 36

Bushfire Prevention – during mining operations

 “Hot works” permits for all activities which have risk of sparks – e.g. angle grinding, welding  Fire hydrants and extinguishers located onsite  Reticulated irrigation systems can be used for fire prevention  More water access points across site  Annual safety review of all systems – external receptors  Emergency Response Teams trained and equipped onsite

slide-37
SLIDE 37

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 37

Emergency Response Management

 Emergency response management plan – required under SA Work Health and Safety Regulations 2012  Based on a risk assessment process

  • Reviewed at least annually
  • Regular drills and mock scenarios

 Like any other location – 000 services are available and would be called in an emergency, e.g. bushfire or car accident  HOWEVER - Terramin Emergency Response Teams (ERT) provide first response – for an underground incident ERT responds

slide-38
SLIDE 38

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 38

Regulations

 SA Work Health and Safety Regulations 2012 – 1.7.2016

 43—Duty to prepare, maintain and implement emergency plan  A person conducting a business or undertaking at a workplace must ensure that an emergency plan is prepared for the workplace, that provides for the following:

  • (a) emergency procedures, including—

– (i) an effective response to an emergency; and – (ii) evacuation procedures; and – (iii) notifying emergency service organisations at the earliest opportunity; and – (iv) medical treatment and assistance; and – (v) effective communication between the person authorised by the person conducting the business or undertaking to coordinate the emergency response and all persons at the workplace;

  • (b) testing of the emergency procedures, including the

frequency of testing;

  • (c) information, training and instruction to relevant workers in

relation to implementing the emergency procedures.

slide-39
SLIDE 39

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 39

Emergency incidents

 Fire  Hazchem Response  Vehicle extraction  Search and Rescue  First Aid

slide-40
SLIDE 40

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 40

ERT Teams

 Nationally accredited training programs and qualifications  State, National and International competitions held between mine sites.  Opportunities to combine training and resources with other emergency services

  • rganisations

 Can provide additional support to community incidents

slide-41
SLIDE 41

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 41

ERT organisation

 Typical arrangement one team per shift made up of personnel

  • n site

 6-8 persons per shift  First responders to incidents on site  Ongoing training

  • Accredited courses
  • On site mock emergencies
  • Opportunities for local

services to be involved

slide-42
SLIDE 42

TERRAMIN AUSTRALIA LIMITED

SLIDE No. 42

Proposed outcome

  • 1. No public injuries or deaths as a result of fires originating in the proposed mining lease that could have

been reasonably prevented.

  • 2. No unplanned fires on site and ensure control measures are in place to manage potential offsite impacts.
  • 3. No permanent loss of abundance, condition or diversity of native vegetation (as defined by Native

Vegetation Act 1991) on or off the lease during construction, operation and post mine completion through;

  • clearance,
  • dust/contaminant deposition,
  • fire,
  • reduction in water supply, or
  • ther damage,

unless prior approval under Native Vegetation Act 1991 and Native Vegetation Regulations 2017 is obtained.