I-69 F 69 Finish Li Line Project Update
October 2019 Sarah Rubin, INDOT, Project Manager
1
Project Update October 2019 Sarah Rubin, INDOT, Project Manager 1 - - PowerPoint PPT Presentation
I-69 F 69 Finish Li Line Project Update October 2019 Sarah Rubin, INDOT, Project Manager 1 I-69 Finish Line Project Update Project overview Construction schedule Refinements (changes since the FEIS in Feb. 2018) Aesthetics
October 2019 Sarah Rubin, INDOT, Project Manager
1
2
3
4
Finish Line
information
project updates
pages
5
including I-465
three years early
connection between Evansville and Indianapolis
6
7
safety and reduce travel time
result in 1,300 fewer regional crashes each year
savings from Martinsville to Indianapolis
8
highway
roads
9
constructed
established
10
Martinsville
parcels in process
11
maintenance-of-traffic
12
13
14
2022
15
County
16
Fairview Rd.
2023 and 2024
17
from I-70 to I-65
and 2024
18
19
20
21
22
23
24
25
26
27
Henderson Ford Rd
28
Henderson Ford Rd
29
Henderson Ford Rd
landlocked parcels
project development costs
agricultural land
30
31
32
roundabouts to eliminate signalized intersection at Old SR 37
flow
33
34
35
northeast quadrant
36
37
Fullonia Gardenia
Henderson Ford Rd. Lighting Options
38
39
40
Lighting Options
41
42
43
44
barriers
businesses in the area
barrier station
45
46
47
48