Project C/CAG TAC Meeting November 21, 2019 Project Scope - PowerPoint PPT Presentation

SamTrans Traffic Signal Priority Project C/CAG TAC Meeting November 21, 2019 Project Scope Implement Traffic Signal Priority (TSP) for SamTrans buses along El Camino Real in San Mateo County 26 miles corridor between Daly City and Menlo


  1. SamTrans Traffic Signal Priority Project C/CAG TAC Meeting November 21, 2019

  2. Project Scope Implement Traffic Signal Priority (TSP) for SamTrans buses along El Camino Real in San Mateo County  26 miles corridor between Daly City and Menlo Park  161 SamTrans buses will be equipped  125 Intersections will be equipped 2

  3. Concept of Operations 1. GPS based vehicle location 2. Bus issues a Priority Request 3. Traffic Signal Controller grants or denies request a) lower priority than Emergency Vehicle Preemption b) does not cancel a pedestrian cycle c) extends the green interval d) shorten the red cycle for early green 3

  4. Concept of Operations 4

  5. Project Benefits 1. Reduce delays at intersections 2. Better on-time performance 3. Increase ridership 5

  6. Project Status 1. Executed a contract with ACT Traffic Solutions on May 1, 2019.  ACT will implement the EMTRAC system on the buses and intersections. 2. Performed 5 pilot installations on 5 different bus models in October 2019. 3. Begin pilot installations in the City of San Mateo on the first week of December 2019.  Hillsdale Blvd 27 th Ave  37 th Ave  41 st Ave  42 nd Ave  6

  7. Bus Equipment Installation 7

  8. Bus Equipment Installation 8

  9. Intersection Equipment Installation EMTRAC Priority Detector 9

  10. Intersection Equipment Installation Traffic Controller Cabinet 10

  11. Project Schedule 1. Begin Installation – 2019 Q4  First installations in the city of San Mateo  City by city installation and testing, north to south a) Daly City b) Colma c) South San Francisco d) San Bruno e) Millbrae f) Burlingame g) Belmont h) San Carlos i) Redwood City j) Atherton k) Menlo Park 11

  12. Project Schedule 2. Complete Installation – 2020 Q4 3. Final Acceptance – 2021 Q3 12

  13. Questions? 13

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.