Project Overview History Problem Error in Original Flood - - PowerPoint PPT Presentation
Project Overview History Problem Error in Original Flood - - PowerPoint PPT Presentation
Project Overview History Problem Error in Original Flood Insurance Study 100 Year Flood Elevation Shown 5 Feet Lower Than Actual Affected Areas Cranford Drive Bush Court & Cragmere Oval Cypress Street History
History
Problem
Error in Original Flood
Insurance Study
100 Year Flood Elevation Shown
5 Feet Lower Than Actual
Affected Areas
Cranford Drive Bush Court & Cragmere Oval Cypress Street
History
1st Proposed Project
2150 feet of realignment of Demarest Kill, between Old
Route 304 and Cranford Drive
1600 feet of realignment of its tributary Limited gabion construction
Permits Issued to Project
NYSDEC - 01/26/1998 Army Corps - 06/23/2000 Rockland Co Drainage Agency - 04/07/1998
Project Scope Revised Due to Opposition
Public Input and Outreach
September, 2011 Resident Meeting October, 2011 Site Meetings 2011 Resident Survey
135 Surveys Mailed 68 Responses Received
Multiple Responses Discounted
52 Responses Used
Return to Larger Scope Project New Permit Applications Required
Public Input and Outreach
New Permit Applications
Army Corps of Engineers
June 2013
NYSDEC
June 2013
RCDA
August 2013
Public Notice and Comment – Town Mailing Additional Information Meetings
February 2013
April 2014 February 2015
Additional Project Review
NY Rising Community Reconstruction Plan - 2014 Governor’s Office of Storm Recovery
Environmental and Plan Peer Reviews – 2015-2017
- Detention Pond Construction
South End of
Cypress Street
Capacity 1.8 Ac-Ft
586,492 Gallons
Interim Measures
Old Project Plan
New Project Plan – Stream Elements
New Project Plan – Stream Planting
Old Project Cross Section
Insert project section
New Project Cross Section
New Project Cross Section
New Project Cross Section
Old Project Retaining Walls
New Project Retaining Walls
Project Funding
Estimated Cost - $3.5 Million Town Funding - NONE County Has Agreed to Contribute
Will Reimburse $1 Million of Project Cost Inter-municipal Agreement has been Executed
FEMA
Hazard Mitigation Program Post Irene – Not approved
NY Rising / GOSR
$2.5 Million Committed to this Project
Continuing Interim Measures
Stream Cleaning
Town Forces Continuing to Identify and Remove