Project Overview History Problem Error in Original Flood - - PowerPoint PPT Presentation

project overview history
SMART_READER_LITE
LIVE PREVIEW

Project Overview History Problem Error in Original Flood - - PowerPoint PPT Presentation

Project Overview History Problem Error in Original Flood Insurance Study 100 Year Flood Elevation Shown 5 Feet Lower Than Actual Affected Areas Cranford Drive Bush Court & Cragmere Oval Cypress Street History


slide-1
SLIDE 1

Project Overview

slide-2
SLIDE 2

History

 Problem

 Error in Original Flood

Insurance Study

 100 Year Flood Elevation Shown

5 Feet Lower Than Actual

 Affected Areas

 Cranford Drive  Bush Court & Cragmere Oval  Cypress Street

slide-3
SLIDE 3

History

 1st Proposed Project

 2150 feet of realignment of Demarest Kill, between Old

Route 304 and Cranford Drive

 1600 feet of realignment of its tributary  Limited gabion construction

 Permits Issued to Project

 NYSDEC - 01/26/1998  Army Corps - 06/23/2000  Rockland Co Drainage Agency - 04/07/1998

 Project Scope Revised Due to Opposition

slide-4
SLIDE 4
slide-5
SLIDE 5
slide-6
SLIDE 6

Public Input and Outreach

 September, 2011 Resident Meeting  October, 2011 Site Meetings  2011 Resident Survey

 135 Surveys Mailed  68 Responses Received

 Multiple Responses Discounted

 52 Responses Used

 Return to Larger Scope Project  New Permit Applications Required

slide-7
SLIDE 7

Public Input and Outreach

 New Permit Applications

 Army Corps of Engineers

June 2013

 NYSDEC

June 2013

 RCDA

August 2013

 Public Notice and Comment – Town Mailing  Additional Information Meetings

 February 2013

April 2014 February 2015

 Additional Project Review

 NY Rising Community Reconstruction Plan - 2014  Governor’s Office of Storm Recovery

 Environmental and Plan Peer Reviews – 2015-2017

slide-8
SLIDE 8
  • Detention Pond Construction

 South End of

Cypress Street

 Capacity 1.8 Ac-Ft

586,492 Gallons

Interim Measures

slide-9
SLIDE 9

Old Project Plan

slide-10
SLIDE 10

New Project Plan – Stream Elements

slide-11
SLIDE 11

New Project Plan – Stream Planting

slide-12
SLIDE 12

Old Project Cross Section

Insert project section

slide-13
SLIDE 13

New Project Cross Section

slide-14
SLIDE 14

New Project Cross Section

slide-15
SLIDE 15

New Project Cross Section

slide-16
SLIDE 16

Old Project Retaining Walls

slide-17
SLIDE 17

New Project Retaining Walls

slide-18
SLIDE 18

Project Funding

 Estimated Cost - $3.5 Million  Town Funding - NONE  County Has Agreed to Contribute

 Will Reimburse $1 Million of Project Cost  Inter-municipal Agreement has been Executed

 FEMA

 Hazard Mitigation Program Post Irene – Not approved

 NY Rising / GOSR

 $2.5 Million Committed to this Project

slide-19
SLIDE 19

Continuing Interim Measures

 Stream Cleaning

 Town Forces Continuing to Identify and Remove

Blockages

 Coordination with County Highway Dept.