Project Launch Tuesday, May 5, 2015 Consultant Team Members PRISM - - PowerPoint PPT Presentation

project launch tuesday may 5 2015 consultant team members
SMART_READER_LITE
LIVE PREVIEW

Project Launch Tuesday, May 5, 2015 Consultant Team Members PRISM - - PowerPoint PPT Presentation

Project Launch Tuesday, May 5, 2015 Consultant Team Members PRISM Partners Inc. (PRISM) Susan Conner - Consultant Team Lead - MOHLTC Capital Planning Specialist - Business Case + Local Share Specialist Bessant Pelech Associates


slide-1
SLIDE 1

Project Launch Tuesday, May 5, 2015

slide-2
SLIDE 2

PRISM Partners Inc. (“PRISM”) Susan Conner - Consultant Team Lead

  • MOHLTC Capital Planning Specialist
  • Business Case + Local Share Specialist

Bessant Pelech Associates (“BPA”) Julie Bessant Pelech - Master Programmer

  • Service Delivery Model Report
  • Part A Components Lead

Two Row Architect (“Two Row”) Brian Porter - Master Planner

  • Facility Planner
  • Part B Components Lead

Hanscomb Ltd. (“Hanscomb”)

  • Cost Consultant

1

Consultant Team Members

slide-3
SLIDE 3

Close se Early Planning Planning Implementation

Stage 1: Pre-Capital Stage 1: Proposal Development Stage 2: Functional Program Stage 3.1: Preliminary Design Part 1 Stage 3.2: Preliminary Design Part 2 Stage 4.1: Working Drawings Stage 4.2: Award of Contract Stage 5.1: Construction Stage 5.2: Settlement

Details of processes can be found in MOHLTC/LHIN Joint Review Framework for Early Capital Planning Stages:

Details of processes can be found in Capital Planning Manual 1996

Details provided in letter to CHC’s in 2010-11 Ministry Planning Review Checkpoints LHIN Support Checkpoints Potential Ministry Grant Funding/Adjustment Checkpoints Ministry Funding Management Proposal/Planning and Design (P&D) Grant Implementation Grant Potential Grant Types Full Grant

Close

Overview of MOHLTC Capital Planning Stages

2

slide-4
SLIDE 4

MOHLTC Guidelines and Checklists

3

slide-5
SLIDE 5

Early Planning

Pre- Capital Stage 1: Proposal Stage 2: Functional Program Physical Infrastructure Deficiencies Related to Program and Service Needs Service Delivery Model Report + Master Planning Define and Justify Scope of Capital Project (Future Function, Form and Space) Compelling Case to MOHLTC MOHLTC Focus on Physical and Cost Element O MOHLTC Approval of Project

4

slide-6
SLIDE 6

1.

Articulation of Planning Objectives

2.

Vision Setting

3.

Current and Future State Assessment

4.

Internal Engagement with 6 Program Teams

5.

External Engagement with Partner Organizations

6.

Community Engagement

7.

Utilization Profiles (MOHLTC only allows for 5% growth)

Part A: Master Program, Service Delivery Model Report and Functional Program

5

slide-7
SLIDE 7

8.

Functional and Operational Parameters based on Best Practice

9.

Space Projections/ Space Tables

10.

Human Resources Plan

11.

Preliminary Operating Cost Estimate

12.

Preliminary Furniture and Equipment List

13.

A Local Share Plan

14.

Completed Checklists for Submission to MOHLTC

Part A: Master Program, Service Delivery Model Report and Functional Program

6

slide-8
SLIDE 8

1.

Technical Building Assessments

2.

Current and Future Space Requirements

3.

Identify Infrastructure Deficiencies

4.

Options to Solve Deficiencies

i.

Renovate/Retrofit /Refurbish existing

ii.

Acquire Land /Build Special-Purpose Facility

iii.

Acquire Land/Retrofit Buildings

iv.

Lease Building/ Leasehold Improvements

Part B: Master Planning and Facility Development Plan

7

slide-9
SLIDE 9

5.

High-Level Project Cost Estimate

6.

Facility Development Plan

7.

High-Level Funding Plan

8.

Project Schedule

9.

Phasing Plan

10.

Completed Checklists for Submission to MOHLTC

Part B: Master Planning and Facility Development Plan

8

slide-10
SLIDE 10

9

Culture

slide-11
SLIDE 11

10

Connection to Outdoors

slide-12
SLIDE 12

11

Less Institutional

slide-13
SLIDE 13

Pre-Capital Critical Path (Preliminary)

Task/Deliverables 2015 May June July

4 11 18 25 1 8 15 22 29 6 13 20 27 1 Project Launch 2 Due Diligence and Document Review 3 Establish Program/ User Teams 4 Program Team Engagement (Round 1) 5 Current State and Future State 6 Program Team Engagement (Round 2) 7 Partner Engagement 8 Finalize Space Requirements 9 Community Engagement Session (both sites) 10 Technical Assessment

12

May 5th (Week of May 18th) (Week of June 8th) (Week of June 22nd )

slide-14
SLIDE 14

Task/Deliverables 2015 May June July

4 11 18 25 1 8 15 22 29 6 13 20 27 11 Report on Infrastructure Deficiencies 12 Identify Infrastructure Solutions 13 Range of Project Cost Estimates for Options 14 Internal Engagement re. Preferred Option(s) 15 Presentation to Capital Planning Committee 16 Finalize Components of Pre-Capital Submission 17 Draft Pre-Capital Submission to Executive Director 18 Finalize Submission 19 Presentation to Board for Approval

Pre-Capital Critical Path (Preliminary)

13

(Week of June 29th ) July 24th

slide-15
SLIDE 15

1.

Validate Pre-Capital Critical Path with Executive Director and Management Team

2.

Determine Process for Vision Setting

3.

Establish Program/User Teams (with Terms of Reference)

4.

Set Dates for Program Team Meetings (2 rounds)

5.

Determine Engagement Plan for DAHC’s Partners

6.

Set Date for Community Engagement Session (both Brantford and Hamilton)

7.

Prepare Pre-User Team Meeting Materials

Next Steps

14