Enloe Hydroelectric Project
Project Implementation
November 5, 2013
Public Utility District No. 1 of Okanogan County
Project Implementation November 5, 2013 Project Location Enloe Site - - PowerPoint PPT Presentation
Public Utility District No. 1 of Okanogan County Enloe Hydroelectric Project Project Implementation November 5, 2013 Project Location Enloe Site Installation of Second Penstock Dam Operation with Flashboards FERC License Project Concept Typical
Public Utility District No. 1 of Okanogan County
Planning Feasibility assessment Site Investigation Permitting Compliance – Dam Safety, PM&Es Design Procure equipment Construction Commissioning Operation
Design-Bid-Build Schedule
2013 2014 2015 2016 2017 ACTIVITY J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D ENGINEERING Design Supplemental Site Investigations Prepare Bid Documents Bid Equipment Packages Bid Construction Construction Management PROCUREMENT Turbine/Generator Package Gates, Trashracks and Hoists Crest Gates Penstock Transformers/Switchgear CONSTRUCTION Mobilization Access road improvements Temporary Cofferdam Training Wall Site excavation Intake Channel Penstock Intake Penstock Tailrace channel Instream Flow Facilities Powerhouse Foundation Excavation Concrete Substructure Turbine/Generator embedded parts Powerhouse Structure Turbine/Generator Installation Electrical/mechanical services Substation/transmission Commissioning Commence Operation Install Crest Gates
Develop concept/preliminary design Acquire development rights/permits/approvals Establish performance criteria Establish construction standards Develop RFP and construction contract Project oversight
Design acceptance/approval Construction Acceptance (quality assurance)
Regulatory compliance Dam safety Project finance Project administration
FERC License – 97 Pages
Issued - July 9, 2013 Effective - July 1, 2013 Expires - June 30, 2062
Terms and Conditions – Called Articles
202-206
Finalize Exhibits F & G, Headwater benefits, Land Rights,
Financing
301-307
Construction, Dam Safety, Public Safety Plans etc.
400-416
Update Ecology Plans, Spoils plans, Revegetation, Recreation
plans, Fire , Aesthetics Plans, Programmatic Agreement etc.
Form L-2 General Articles 1 – 32 Appendix A – 401 Water Quality Certificate Conditions Appendix B – NOAA Fisheries Terms and Conditions
The FERC license contains 61 Articles
Currently we have identified approximately 350 tasks for the life of the project (50 years).
Approximately 120 tasks have been identified that have compliance deadlines between July 2013 and July 2015.
The 350 and 120 tasks identified above do not include tasks associated with the BLM R/W, 401 rulings, ACOE 404 conditions, HPA conditions or any pre, during or post Engineering or Operations assignments.
We anticipate that there will be between 500 and 1000 tasks once all the conditions are analyzed.
Article 202, Exhi
hibi bit t F F Drawing ngs. . Withi hin n 45 5 days s of f the he da date e of f issu ssuance e of f the e license, , the e licensee e shall l file e the e approved d exhibit t F F dr drawings s in n aperture e card d and d electronic c file e formats…… …
Article 203, Exhi
hibi bit t G G Drawing ngs. . Withi hin n 90 0 days s of f the he effective e da date e
f the e license, , the e licensee e shall l file, , for r Commission n approval, , revised d Exhi hibi bit t G G drawing ngs s enc nclosing ng withi hin n the he pr project t bo bound ndary y all l pr princ ncipa pal l project t works s necessary y for r operation n and d maintenance e of f the e project, , includi ding g the e proposed d side de channel l enhancement t site; ; the e entire e leng ngth h of f the he ODIT IT Ditch R h Road f from m the he Loomis-Orov
e Roa
to
e En Enloe e Dam m Recreation n Area, , the e entire e length h of f the e En Enloe e Dam m Road; d; and d a a river a access s take-out t at t the e Miners s Flat t site……. .
Article 306, Owner’s
s Dam am Saf afety y Program.
ithin in 90 da days ys f from m the e is issu suance ce da date o e of t the e licen icense, se, the e licen icensee see shall l submit it to t the C e Commis issio ion’s s Div ivisio ision n of f Dam m Safet ety a y and d Inspect ectio ions s (D2SI)–Portland nd Regiona nal E Eng ngine neer, , an O n Owne ner’s s Dam m Safety y Program m which h among o
items d demonstrates s a a clear r acknowledgement t of t the e dam m
s responsibility y for r the s safety y of t the e project, a an o
e of f the r roles a and d resp esponsib sibil ilit ities es of f it its da dam s safet ety y staff, , and d access ccess of it its da dam s safet ety y officia icial t l to
its C s Chief ief Executive e Officer. F For g guidance e on t the e Owner’s s Dam m Safety y Programs, , the l licensee e should d reference e information n posted d on t the F FERC C website. .
Article 307, Public
c Safety y Plan. . Wit
ithin in 90 0 da days ys f from t the e is issu suance ce of t this o is order der, , the l e licen icensee ee sh shall l submit it one e co copy y to t the e Commiss issio ion’s s Div ivis isio ion n of D Dam S Safet ety a y and d Ins nspe pections ns ( (D2SI)-Portland d Reg egio ional l Engin ineer eer and t d two co copies ies to
e Commis issio ion n (one e
f these e copies s shall b be e a c courtesy y copy y to t the e Commission’s s Director, , D2SI) o
f a P Public c Safety P Plan. . The e plan s shall l include e an e evaluation n of p public c safety c concerns s at t the p project t sit ite, e, in incl cludin ding g desig designated ed recr ecrea eatio ion n area eas, , and d asses ess t s the n e need eed for t the e in inst stallatio ion o
f safet ety y dev devices ices or r other er s safet ety m y mea easures.
The s e submit itted ed plan sh shall l in incl clude de a a des descr crip iptio ion n of f all l public ic safet ety y dev devices ices and d sig signage, e, as w wel ell a as a a m map p showin ing g the e loca catio ion n of f all l public ic safety m measures. . For r guidance e on n preparing g public c safety p plans, t the l licensee e can r review w the G Guidelines s for r Public c Safety a at t Hydropower r Projects o
n the F FERC C website………… …
Compliance Document Engineering Component Required? Task Task Management Area Oversight Group(s) Consultation Requirement Due Date (for Initial Occurrence) Pre-Construction, Construction, or Operation Periodicity Reference Information License No The PUD shall develop an Operational Compliance Monitoring Plan and submit it to FERC for approval. Engineering FERC; Ecology; WDFW; FWS; NMFS; BLM; Colville Tribes Consultation and Approval Within one year of license issuance. Pre Construction One time License, Article 403 License No The PUD shall develop a Recreation Management Plan and submit it to FERC for approval. Recreation FERC; BLM; NPS; Ecology; Rec and Conservation; SHPO; Colville Tribes Consultation and Approval Within one year of license issuance. Pre Construction One time License, Article 410 License No The PUD shall develop a Fire Suppression Plan and submit it to FERC for approval. Engineering FERC; BLM; DNR Consultation and Approval Within one year of license issuance. Pre Construction One time License, Article 412 License No The PUD shall submit the final HPMP to FERC for approval. Cultural NA NA Within one year of license issuance. Pre Construction One time License, Article 415 License Yes The PUD shall consult with the appropriate State and Federal agencies and, within one year of the license issuance, submit for FERC approval a plan for clearing the reservoir area. Engineering FERC; State and federal agencies Consultation and Approval Within one year of license issuance Construction One time License, Article 20 Recreation Management Plan No The PUD shall coordinate with BLM and other landowners, as appropriate, to identify options for preventing public access to the old powerhouse. Safety BLM; landowners Consultation The RMP implementation schedule (Figure 4 of the RMP) must be adapted for the actual license issuance date. Pre Construction and Construction One time RMP, 20 401 Yes The PUD shall obtain a Hydraulic Project Approval prior to in stream work. Engineering Ecology Approval Prior to construction Pre Construction One time 401, Page 16 Aquatic Invasive Species Management Plan No The PUD shall conduct a walking survey of the perimeter of the project boundary to inspect the shoreline and adjacent shallow water areas for all AIS presence. Fish and Aquatics NA NA Prior to construction Pre Construction Annually AISMCP, 15 Blasting Plan Yes The PUD shall develop and implement a Final Blasting Plan. Safety/Engineering NA NA Prior to construction Pre Construction One time Blasting, 1 HPMP No The PUD shall coordinate with the DAHP, THPOs, and other consulting parties, as appropriate, during implementation of the HPMP to ensure compliance with Section 106 requirements. Cultural DAHP; THPOs; Consulting parties NA Prior to construction Pre Construction Ongoing HPMP, 30 License No The PUD shall develop a Wildlife Management Plan and submit it to FERC for approval. Wildlife and Botanical FERC; FWS; BLM; WDFW Consultation and Approval At least 90 days before starting construction. Pre Construction One time License, Article 409 401 No The PUD shall distribute draft plans and reports to all of the FW members for review and comments. Fish and Aquatics FW Consultation Upon finalization of FW membership Entire License Period Ongoing 401, Page 14 Stormwater Pollution Prevention Plan Yes The PUD shall implement the Stormwater Pollution Prevention Plan. Water Quality NA NA Prior to construction Pre construction or Construction Ongoing xx NMFS Biological Opinion No The PUD shall establish a Biological Resources Program, Technical Review Group (TRG). Fish and Aquatics NA NA Prior to construction Pre Construction One time BiOP, 14
Performance criteria & engineering standards Transmission Interconnection Transmission line Protection Control system interface SCADA Schedule Budget Cost Control Quality Assurance Contract Administration Dam Safety
FERC Uniform System of Accounts
FERC Financial reporting Annual FERC Charges Payment of resource agency participants Privilege taxes Grant management – if applicable Article 7 of License – FERC will determine
401 WQ Permit Appeal and Rehearing
Completed October 2013
FERC License Rehearing and Appeals
FERC commission rejects all appellants except American Whitewater September 4, 2013
FERC ruling/order on environmental groups’ rehearing request?
PUD seeks rehearing 30 days after order/rehearing? (if FERC grants rehearing)
Environmental groups appeal decision 60 days after order/rehearing?
Next step for parties, appeal to Federal Court of Appeals
Water Rights ROE’s Appeal
WR Appeal to PCHB (30 days after issuance)
Hearing August 6 & 7, 2014, all same processes followed in 401.
Dam facilities inspections and reports Agencies participation & cost recovery agreements Historical structures monitoring Emergency Action Plan updates Environmental & Permitting Consultants Engineering Consultants Legal PM&E Implementation Additional agency requests
Elwha
Project Acquisition $29.9M, 9.20% Dam and Transmission Line Removal $26.9M, 8.30% Water Quality Protection ( treatment plants) $106.6M,
Flood Protection (Levees) $23.3M, 7.20% Fish hatchery $16.4M, 5.00% Ecosystem Restoration $15.9M, 4.90% Other contract and non-contract costs $106M, 32.60%
Total Budget $325 Million 100%
Co
Milltown
The p
Preliminary removal costs include both direct (dam
Entrainment range in Millions $27 - $67 Full removal range in Millions $375 - $1053