Project History Original Funding appropriated by the State in 1998 - - PowerPoint PPT Presentation

project history
SMART_READER_LITE
LIVE PREVIEW

Project History Original Funding appropriated by the State in 1998 - - PowerPoint PPT Presentation

Project History Original Funding appropriated by the State in 1998 Site acquired through Eminent Domain in Sept 28,2000 Skidmore, Owings and Merrill selected as architects in 2000 Programming and Design started January 2003


slide-1
SLIDE 1

Project History

  • Original Funding appropriated by the State in 1998
  • Site acquired through Eminent Domain in Sept 28,2000
  • Skidmore, Owings and Merrill selected as architects in

2000

  • Programming and Design started January 2003
  • Approved by City Planning Commission‐January 5,

2005

  • Groundbreaking –October 23, 2007
  • Construction begins‐ February 1, 2007
slide-2
SLIDE 2

Project Team

  • CUNY ‐ Manages project from inception through the Design

Development Phase. Final decisions on design/program elements and in maintaining the project budget.

  • DASNY‐ Acts as the construction administrator for the project.

Administers all contracts for construction, project finances and holds property deed.

  • SOM‐ Architect in charge of programming, designing and will

follow the project’s development through completion and

  • ccupancy.
  • Turner Construction‐ Construction Manager for the new building.

This joint venture with SOM was formed to monitor the costs at each of the milestones

  • f the project.
slide-3
SLIDE 3

Scope

  • 629,000 square feet
  • 13 stories
  • Essentially designed to replace North Hall
  • Consolidates most of the campus one full city block
  • Campus gross sq.ft. will increase from 730,856 sq.ft. to

1,130,634 sq.ft. (Not including North Hall)

  • Gross sq. ft for John Jay increases from 44 sq. ft. to 59 sq.
  • ft. per F.T.E. (Full Time Equivalent)
  • Mixed use building consisting of classrooms, computer

and science facilities, academic departments and offices, academic support services, student services and activities.

  • Largest CUNY capital project‐ over ½ Billion Dollars
  • Building expansion capabilities
slide-4
SLIDE 4

Building Organization

  • Concourse : 1st ‐4th floors ‐ Student Services
  • Tower section: 6th ‐13th floors‐ Academic Departments
  • Cascade: Central corridor extending from 59th Street entrance up to

the 5th floor Dining facilities and connection to Haaren Hall

  • Building systems: ‐State of the art smart classrooms

‐100% Wireless Facility ‐Technologically advanced H.V.A.C. (Heating, Ventilation, Air Conditioning) system design and equipment ‐Excellent fire protection systems ‐ Emergency/Panic systems in all public restrooms

  • Vertical Transportation: 8 New passenger elevators

2 Freight elevators 1 Accessible elevator 12 Escalators from 11th Avenue to 7th fl

slide-5
SLIDE 5
slide-6
SLIDE 6

Major Features

  • Main entrances on 59th Street and 11th Avenue
  • Outdoor rooftop commons (The “Jay Walk”)‐ 60,000 sq.ft
  • Connected to Haaren Hall at 3 levels
  • 250 seat auditorium
  • Consolidated student services on entrance floor
  • Black Box Theater
  • Moot Court
  • New & Expanded Science Facilities on 3 floors
  • Wireless throughout ‐ additional computer stations
slide-7
SLIDE 7

Major Features

Main entrance on 59th Street

slide-8
SLIDE 8

Major entrance on 11th Avenue

slide-9
SLIDE 9

Lobby on 59th Street

slide-10
SLIDE 10

Outdoor rooftop commons (The “Jay Walk”)

From 11th Fl. looking East

slide-11
SLIDE 11

The “Jay Walk”

From 6th Fl. looking East

slide-12
SLIDE 12

The “Jay Walk”

From Lower Roof –Haaren Hall looking West

slide-13
SLIDE 13

250 Seat Auditorium

slide-14
SLIDE 14

Moot Court

slide-15
SLIDE 15

Computer Center :2nd fl.

slide-16
SLIDE 16

Major Features

  • 400 seat student cafeteria
  • Outdoor dining
  • Indoor pedestrian cascade with large meeting areas

and food service facilities

  • Café and gallery/events space on 11th Avenue
  • Emergency Management and High Rise Simulator

Labs

  • All smart classrooms – additional 5 classrooms and

150 additional seats to the Campus

  • New Theater Lobby and conference rooms
  • World Trade Center Memorial
slide-17
SLIDE 17

400 seat student cafeteria

slide-18
SLIDE 18

Cafeteria: Servery

slide-19
SLIDE 19

The Cascade

From 3rd Fl. looking West

slide-20
SLIDE 20

The Cascade

4th Fl. looking West

slide-21
SLIDE 21

Smart Classrooms : 2‐ 120 Seat Lecture Halls

slide-22
SLIDE 22

Conference room :12th Floor

slide-23
SLIDE 23
  • World Trade Center Memorial

Location for World Trade Center Steel Memorial Dedication for 10th Anniversary of the attack

slide-24
SLIDE 24
  • World Trade Center Steel

‐ Overall dimensions: 3’‐6” H x 8’‐4” L x 5’‐0” W 0.25” Thick ‐ Weight : ± 2,000 pounds

slide-25
SLIDE 25

Progress to Date

  • Excavation, Foundation, Structural Steel, Superstructure

Concrete, Masonry, Spray on Fireproofing ‐‐ Completed

  • Roofing System ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐current finish 12/23/10
  • Hoisting and Sidewalk Bridge ‐‐‐‐‐‐ current finish 1/20/11
  • Building enclosed ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐current finish 03/01/11
  • Vertical Transportation ‐‐‐‐‐‐‐‐‐‐‐‐‐‐ current finish 6/08/11
  • Acoustical Ceiling System‐‐‐‐‐‐‐‐‐‐‐‐ current finish 6/29/11
  • General Construction, Electrical, Plumbing,

Mechanical & Fire Protection and Integrated Control Systems ‐‐‐‐‐‐‐‐‐current finish 11/03/11

slide-26
SLIDE 26

Tentative Schedule for Completion

  • Lower four floors to be completed , Summer June

20, 2011

  • Tower Project completion and owner occupancy

starts by November 22, 2011.

  • Temporary Certificates of Occupancies will be

issued: Concourse : floors 1‐4 ‐‐‐‐ June 22, 2011 Tower : floors 5‐13‐‐‐‐ August 19, 2011 Owner occupancy ‐‐‐‐‐November 22, 2011

slide-27
SLIDE 27

New Building Art

  • An art committe was organized to select artists for the

new building .

  • Budget ‐ $ 800,000.00 (Includes all expenses)
  • 3 Artists Selected ‐ Alfredo Jaar for 59th Street entrance

‐ Ralph Helmick for new computer hub ‐ Nobuho Nagasawa for 11th Avenue entrance hall (By Black Box Theater)

  • Student Art will also be displayed throughout the new

building spaces such as The Cascade

slide-28
SLIDE 28

Other

  • Grand Opening in October 2011. Date, time and

location to be determinated. Committee will be established to develop the opening celebration.

  • Continued use of North Hall‐ Several Academic

Departments will need to remain in North Hall until their spaces are ready to occupy in Haaren and BMW buildings

  • 6th floor in BMW and spaces in several floors of

Haaren Hall will need to be renovated to accommodate Academic Departments that do not fit in the new building

slide-29
SLIDE 29

Tentative New Building Move Schedule

  • Move consultant has been retained by DASNY
  • Professional moving companies will be hired for the

new building move

  • Move policies being developed by John Jay
  • Boxes will be provided to everyone and anyone with

special needs will be receive assistance for packing

  • Phase I of move ‐ Summer 2011 will include:

‐ Department of Public Safety ‐ DOIT ‐ Facilities Management Dept. Offices + Shops ‐ Children’s Center ‐ C.E.L.S

slide-30
SLIDE 30

‐ Central Receiving & Mailroom ‐ Emergency & Security Management Lab / High‐rise Simulator ‐ I.T.S.S & Computer Labs ‐ Judicial Board ‐ Reflection Room ‐ Office of Student Life ‐ Student Clubs & Organizations ‐ Student Government ‐ Office of Accessibility Services ‐ Academic Advisement Center ‐ Bursar’s Office

slide-31
SLIDE 31

‐ Center for Career and Professional Development Community Outreach and Service Learning ‐ Department of Counseling Counseling Services Center ‐ Enrollment Management & Testing Offices ‐ Graduate Admissions ‐ Health Office ‐ John Jay Express Services Center ‐ PDP Lab ‐ Testing Labs ‐ Undergraduate Admissions ‐ Office of the V.P for Student Development and Dean of Students ‐ Women’s Center ‐ Math & Science Resource Center ‐ Writing Center

slide-32
SLIDE 32
  • Phase II of move – Winter 2011‐2012

‐ Gender Studies ‐ Interdisciplinary Studies ‐ Math Dept. ‐ English Dept. ‐ Foreign Language Dept. ‐ History Dept. ‐ Honors Program ‐ Latin American & Latino/a Studies ‐ Mc Nair Program ‐ Philosophy Dept. ‐ Undergraduate Research ‐ Anthropology Dept. ‐ Office of Finance and Administration

slide-33
SLIDE 33

‐ Political Science Dept. ‐ Protection Management Dept. ‐ Development through the life cycle ‐ P.H.D. Forensic Psychology ‐ Psychology Dept.

  • Phase III of move : Summer 2012

‐ Science Dept. – Teaching and Research Labs.

For additional information details regarding office locations ,please visit our website: www.jjay.cuny.edu