SLIDE 1 Project History
- Original Funding appropriated by the State in 1998
- Site acquired through Eminent Domain in Sept 28,2000
- Skidmore, Owings and Merrill selected as architects in
2000
- Programming and Design started January 2003
- Approved by City Planning Commission‐January 5,
2005
- Groundbreaking –October 23, 2007
- Construction begins‐ February 1, 2007
SLIDE 2 Project Team
- CUNY ‐ Manages project from inception through the Design
Development Phase. Final decisions on design/program elements and in maintaining the project budget.
- DASNY‐ Acts as the construction administrator for the project.
Administers all contracts for construction, project finances and holds property deed.
- SOM‐ Architect in charge of programming, designing and will
follow the project’s development through completion and
- ccupancy.
- Turner Construction‐ Construction Manager for the new building.
This joint venture with SOM was formed to monitor the costs at each of the milestones
SLIDE 3 Scope
- 629,000 square feet
- 13 stories
- Essentially designed to replace North Hall
- Consolidates most of the campus one full city block
- Campus gross sq.ft. will increase from 730,856 sq.ft. to
1,130,634 sq.ft. (Not including North Hall)
- Gross sq. ft for John Jay increases from 44 sq. ft. to 59 sq.
- ft. per F.T.E. (Full Time Equivalent)
- Mixed use building consisting of classrooms, computer
and science facilities, academic departments and offices, academic support services, student services and activities.
- Largest CUNY capital project‐ over ½ Billion Dollars
- Building expansion capabilities
SLIDE 4 Building Organization
- Concourse : 1st ‐4th floors ‐ Student Services
- Tower section: 6th ‐13th floors‐ Academic Departments
- Cascade: Central corridor extending from 59th Street entrance up to
the 5th floor Dining facilities and connection to Haaren Hall
- Building systems: ‐State of the art smart classrooms
‐100% Wireless Facility ‐Technologically advanced H.V.A.C. (Heating, Ventilation, Air Conditioning) system design and equipment ‐Excellent fire protection systems ‐ Emergency/Panic systems in all public restrooms
- Vertical Transportation: 8 New passenger elevators
2 Freight elevators 1 Accessible elevator 12 Escalators from 11th Avenue to 7th fl
SLIDE 5
SLIDE 6 Major Features
- Main entrances on 59th Street and 11th Avenue
- Outdoor rooftop commons (The “Jay Walk”)‐ 60,000 sq.ft
- Connected to Haaren Hall at 3 levels
- 250 seat auditorium
- Consolidated student services on entrance floor
- Black Box Theater
- Moot Court
- New & Expanded Science Facilities on 3 floors
- Wireless throughout ‐ additional computer stations
SLIDE 7
Major Features
Main entrance on 59th Street
SLIDE 8
Major entrance on 11th Avenue
SLIDE 9
Lobby on 59th Street
SLIDE 10 Outdoor rooftop commons (The “Jay Walk”)
From 11th Fl. looking East
SLIDE 11 The “Jay Walk”
From 6th Fl. looking East
SLIDE 12 The “Jay Walk”
From Lower Roof –Haaren Hall looking West
SLIDE 13
250 Seat Auditorium
SLIDE 14
Moot Court
SLIDE 15
Computer Center :2nd fl.
SLIDE 16 Major Features
- 400 seat student cafeteria
- Outdoor dining
- Indoor pedestrian cascade with large meeting areas
and food service facilities
- Café and gallery/events space on 11th Avenue
- Emergency Management and High Rise Simulator
Labs
- All smart classrooms – additional 5 classrooms and
150 additional seats to the Campus
- New Theater Lobby and conference rooms
- World Trade Center Memorial
SLIDE 17
400 seat student cafeteria
SLIDE 18
Cafeteria: Servery
SLIDE 19 The Cascade
From 3rd Fl. looking West
SLIDE 20 The Cascade
4th Fl. looking West
SLIDE 21
Smart Classrooms : 2‐ 120 Seat Lecture Halls
SLIDE 22
Conference room :12th Floor
SLIDE 23
- World Trade Center Memorial
Location for World Trade Center Steel Memorial Dedication for 10th Anniversary of the attack
SLIDE 24
‐ Overall dimensions: 3’‐6” H x 8’‐4” L x 5’‐0” W 0.25” Thick ‐ Weight : ± 2,000 pounds
SLIDE 25 Progress to Date
- Excavation, Foundation, Structural Steel, Superstructure
Concrete, Masonry, Spray on Fireproofing ‐‐ Completed
- Roofing System ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐current finish 12/23/10
- Hoisting and Sidewalk Bridge ‐‐‐‐‐‐ current finish 1/20/11
- Building enclosed ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐current finish 03/01/11
- Vertical Transportation ‐‐‐‐‐‐‐‐‐‐‐‐‐‐ current finish 6/08/11
- Acoustical Ceiling System‐‐‐‐‐‐‐‐‐‐‐‐ current finish 6/29/11
- General Construction, Electrical, Plumbing,
Mechanical & Fire Protection and Integrated Control Systems ‐‐‐‐‐‐‐‐‐current finish 11/03/11
SLIDE 26 Tentative Schedule for Completion
- Lower four floors to be completed , Summer June
20, 2011
- Tower Project completion and owner occupancy
starts by November 22, 2011.
- Temporary Certificates of Occupancies will be
issued: Concourse : floors 1‐4 ‐‐‐‐ June 22, 2011 Tower : floors 5‐13‐‐‐‐ August 19, 2011 Owner occupancy ‐‐‐‐‐November 22, 2011
SLIDE 27 New Building Art
- An art committe was organized to select artists for the
new building .
- Budget ‐ $ 800,000.00 (Includes all expenses)
- 3 Artists Selected ‐ Alfredo Jaar for 59th Street entrance
‐ Ralph Helmick for new computer hub ‐ Nobuho Nagasawa for 11th Avenue entrance hall (By Black Box Theater)
- Student Art will also be displayed throughout the new
building spaces such as The Cascade
SLIDE 28 Other
- Grand Opening in October 2011. Date, time and
location to be determinated. Committee will be established to develop the opening celebration.
- Continued use of North Hall‐ Several Academic
Departments will need to remain in North Hall until their spaces are ready to occupy in Haaren and BMW buildings
- 6th floor in BMW and spaces in several floors of
Haaren Hall will need to be renovated to accommodate Academic Departments that do not fit in the new building
SLIDE 29 Tentative New Building Move Schedule
- Move consultant has been retained by DASNY
- Professional moving companies will be hired for the
new building move
- Move policies being developed by John Jay
- Boxes will be provided to everyone and anyone with
special needs will be receive assistance for packing
- Phase I of move ‐ Summer 2011 will include:
‐ Department of Public Safety ‐ DOIT ‐ Facilities Management Dept. Offices + Shops ‐ Children’s Center ‐ C.E.L.S
SLIDE 30
‐ Central Receiving & Mailroom ‐ Emergency & Security Management Lab / High‐rise Simulator ‐ I.T.S.S & Computer Labs ‐ Judicial Board ‐ Reflection Room ‐ Office of Student Life ‐ Student Clubs & Organizations ‐ Student Government ‐ Office of Accessibility Services ‐ Academic Advisement Center ‐ Bursar’s Office
SLIDE 31
‐ Center for Career and Professional Development Community Outreach and Service Learning ‐ Department of Counseling Counseling Services Center ‐ Enrollment Management & Testing Offices ‐ Graduate Admissions ‐ Health Office ‐ John Jay Express Services Center ‐ PDP Lab ‐ Testing Labs ‐ Undergraduate Admissions ‐ Office of the V.P for Student Development and Dean of Students ‐ Women’s Center ‐ Math & Science Resource Center ‐ Writing Center
SLIDE 32
- Phase II of move – Winter 2011‐2012
‐ Gender Studies ‐ Interdisciplinary Studies ‐ Math Dept. ‐ English Dept. ‐ Foreign Language Dept. ‐ History Dept. ‐ Honors Program ‐ Latin American & Latino/a Studies ‐ Mc Nair Program ‐ Philosophy Dept. ‐ Undergraduate Research ‐ Anthropology Dept. ‐ Office of Finance and Administration
SLIDE 33 ‐ Political Science Dept. ‐ Protection Management Dept. ‐ Development through the life cycle ‐ P.H.D. Forensic Psychology ‐ Psychology Dept.
- Phase III of move : Summer 2012
‐ Science Dept. – Teaching and Research Labs.
For additional information details regarding office locations ,please visit our website: www.jjay.cuny.edu