program
play

Program Roadways and Infrastructure June 20, 2019 Roadways and - PowerPoint PPT Presentation

2019 Bond Program Roadways and Infrastructure June 20, 2019 Roadways and Infrastructure Needs Address existing transportation infrastructure deficiencies such as: Capacity Congestion Safety Address future capacity needs based


  1. 2019 Bond Program Roadways and Infrastructure June 20, 2019

  2. Roadways and Infrastructure Needs • Address existing transportation infrastructure deficiencies such as: • Capacity • Congestion • Safety • Address future capacity needs based on projected growth • Funding future phases of ongoing projects • Continue Street Reconstruction OCI Improvement June 13, 2019 ID 19-449 2

  3. Proposed Proposition 2 – Staff Prioritization Program Funding Staff Recommended Project Total Project Cost Staff is in City Bond Funding Proposition 2: Roadways and Infrastructure discussion with Bonnie Brae (V, VI, VII) $111.5M $27M multiple agencies Hickory Creek $160M $34M to leverage the Street Rehab Program $35M $35M City’s bond Sidewalks $12M $12M Robinson Road $12.3M $12.3M funding to Ryan Road $47.66M $44.26M achieve 3x the Jim Christal $16.8M $1.65M value in capital FM 428 $44M - Other Proposition Requests projects. Street Lighting $5M - $15M $0 Total $444M - $454M $166.21M 3

  4. Arterial Projects Area 2 PROJECT SELECTION: • Demand in high growth areas • Historically unsafe roadways Area 3 • Regional connectivity • Capacity improvements • Funding opportunities • Improve safety in adjacent neighborhoods Area 1 June 13, 2019 ID 19-449 4

  5. Area 1 – Upcoming Developments June 13, 2019 ID 19-449 5

  6. Area 2 – Upcoming Developments June 13, 2019 ID 19-449 6

  7. Area 3 – Upcoming Developments June 13, 2019 ID 19-449 7

  8. Project Cost Information • The total cost to complete the all elements of the project is estimated. • The total cost is the sum of: • Design • Right-of-Way Acquisition • Construction • Contingency • Inflation • Staff Time • Contract Incentives/Disincentives • For each project, the total project cost and the City’s projected cost have been estimated. June 13, 2019 ID 19-449 8

  9. Bonnie Brae Street Phases V, VI, & VII Limits: Scripture Street to Loop 288 • Scope: Widen approximately 3 miles • to 4-lane divided Characteristics/LOS: • Existing - Peak hour LOS D or • worse Proposed – LOS A or B • Total Cost: $111.5M • City Cost: $27M • June 13, 2019 ID 19-449 9

  10. Hickory Creek Road • Limits: I-35 W To FM 2499 (5.75 miles) • Scope: Construct/Widen to a 6-lane divided facility • Characteristics/LOS: • Current - LOS D or worse • Proposed – LOS A or B • Total Cost: $160M City Cost: $34M June 13, 2019 ID 19-449 10

  11. Neighborhood Streets Rehabilitation June 13, 2019 ID 19-449 11

  12. Overall Condition Index (OCI) • Numerical score ranging from 0 (worst) to 100 (best) • OCI Consist of the following • 80 % PCI (Pavement Condition Index) • 20% RI (Ride Index) • Typically performed by a pavement management consultant using specialized equipment • OCI scores are used in conjunction with a pavement management software program to develop preventative maintenance plans to help manage street assets

  13. Pavement Life Cycle Curve Maintenance Impacts on Pavement Life Cycle Typical Pavement Life Cycle 40% of pavement life Excellent has a 15% drop in quality Very Good 15% of pavement life Pavement Quality $1 spent now Good has a 40% drop in quality Fair Poor Costs $8 if delayed Very Poor Time

  14. Neighborhood • City wide average OCI is 64 Streets OCI Range Description Relative Remaining Life Definition Like new condition – little to no maintenance required; routine 85 – 100 Excellent 15 to 25 Years maintenance such as crack and joint sealing. Routine maintenance such as patching and crack sealing with surface 75 – 85 Very Good 12 to 20 Years treatments such as seal coats or slurries. Heavier surface treatments and thin overlays. Localized panel 65 – 75 Good 10 to 15 Years replacements. Heavy surface-based inlays or overlays with localized repairs. Moderate 45 – 65 Fair to Marginal 7 to 12 Years to extensive panel replacements. Sections will require very thick overlays, surface replacement, base 30 – 45 Poor 5 to 10 Years reconstruction, and possible subgrade stabilization. 0 – 30 Very Poor 0 to 5 Years High percentage of full reconstruction. June 13, 2019 ID 19-449 14

  15. Project Selection OPTIONS: • Option 1: Lowest OCI First • Option 2: Low OCI grouped • Option 3: Hybrid June 13, 2019 ID 19-449 15

  16. Neighborhood Streets Advantages: Addresses the “very poor” streets • that have an expected remaining life of 5-years or less. Disadvantages: Potential to increase construction • cost Does not include connecting streets • Adds to construction fatigue • OCI Segments Lane Miles Project Cost 0 – 5 3 1 $1 M 0 – 10 15 5 $5 M 0 – 15 61 20 $20 M 0 – 20 135 42 $35 M 0 – 25 230 72 $60 M 0 – 30 362 115 $95 M June 13, 2019 ID 19-449 16

  17. Neighborhood Streets Area 2 Advantages: Most efficient with respect to costs • Includes connecting streets • Improves all infrastructure in neighborhood • Shortens construction fatigue experience • Disadvantages: Area 3 Does not address all “very poor” streets • Segments Lane Miles Project Cost Section 1 49 12.88 $10.8 M Section 2 49 13.24 $11.1 M Section 3 73 21.32 $17.9 M Section 4 51 12.78 $10.7 M Section 5 24 11.38 $9.5 M Section 6 20 6.91 $5.8 M Section 7 20 4.98 $4.2 M Area 1 TOTAL 286 83.49 $70.0 M June 13, 2019 ID 19-449 17

  18. Neighborhood Streets Section • 12.8 Lane Miles • Total Cost: $10.7M • Average OCI – 27.7 • Projected OCI – 75* June 13, 2019 ID 19-449 18

  19. Staff Recommended Option Neighborhoods Staff recommends a combination of the Neighborhoods and Lowest OCI Options. Segments Lane Miles Project Cost Advantages: Section 1 49 12.88 $10.8 M Section 2 49 13.24 $11.1 M Addresses more of the “very poor” streets • Section 3 73 21.32 $17.9 M Gains more efficiency with respect to costs • Section 4 51 12.78 $10.7 M Section 5 24 11.38 $9.5 M Includes connecting streets • Section 6 20 6.91 $5.8 M Improves all infrastructure in selected neighborhoods • Section 7 20 4.98 $4.2 M TOTAL 286 83.49 $70.0 M Shortens construction fatigue experience • Disadvantages: Does not address all “very poor” streets • Lowest OCI Does not minimize construction fatigue • OCI Segments Lane Miles Project Cost Still has some remaining disconnected segments • 0 – 5 2 0.8 $0.8 M 0 – 10 13 4.8 $4.8 M 0 – 15 48 16.9 $18.2 M Recommended Option Cost: $70M 0 – 20 102 32.3 $30 M 0 – 25 230 72 $60 M 0 – 30 362 115 $95 M June 13, 2019 ID 19-449 19

  20. Sidewalks June 13, 2019 ID 19-449 20

  21. Project Selection Complete construction of unfunded sidewalks in 2018 and 2019 sidewalk bundles. • 2018 Sidewalks – $1M, 2 miles • 2019 Sidewalks - $2.2M, 3.25 miles June 13, 2019 ID 19-449 21

  22. Project Selection BASED ON PROXIMITY TO SCHOOLS • Within ¼ mile of a School ($18.7 M), 28.4 miles • Within ½ mile of a School ($130.8M), 198.3miles • Within 1 mile of a School ($276.3M), 418.6miles June 13, 2019 ID 19-449 22

  23. Example: Evers/Strickland • 3 Miles of sidewalk to be added. • Total Cost: $2M June 13, 2019 ID 19-449 23

  24. Plan • Design and acquire right-of-way or easements for sidewalks for the following year • Construct sidewalks designed in previous year • Leverage City funds to get Federal and State funds. SRTS funding typical City match is 20% June 13, 2019 ID 19-449 24

  25. Robinson Road Limits: FM 2499 to Teasley Lane • Scope: Widen approximately • 3,700 feet (0.7 miles) from 2 lanes to 4-lane divided Characteristics/LOS: • Current LOS E • Project LOS A • Total Cost: $12.3M • City Cost: $12.3M • June 13, 2019 ID 19-449 25

  26. Ryan Road Limits : Teasley Lane to Country Club • Road Scope: Widen approximately 2 miles • from 2 lanes to 4 lanes divided Characteristics/LOS: • Current LOS D or worse • Proposed LOS A • Total Cost: $47.66M • City Cost: $44.26M • June 13, 2019 ID 19-449 26

  27. Ryan Road Limits : Teasley Lane to Country Club • Road Scope: Area study shows future need • is for a 2-lane road with intersection improvements at FM2181 and FM1830. Characteristics/LOS: • Currently LOS D or worse • Project LOS A • Total Cost: $10M to $25M • City Cost: $4M to $19M • June 13, 2019 ID 19-449 27

  28. Jim Christal Road • Limits: I-35 to Western Boulevard • Scope: Widen approximately 1 mile from 2 lanes to 4-lane divided • Characteristics: Heavy Truck Traffic • Total Cost: $16.8M • City Cost: $1.65M June 13, 2019 ID 19-449 28

  29. Sherman Drive (FM 428) Limits: Loop 288 to Clear Creek (2 miles) • Scope: Widen 2 lanes to 6-lane divided • (ultimate) TxDOT managed and funded Total Cost: $44M • City Cost: $0 • June 13, 2019 ID 19-449 29

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend