Professor Ewan McKendrick University of Oxford SETTING THE SCENE - - PowerPoint PPT Presentation

professor ewan mckendrick university of oxford setting
SMART_READER_LITE
LIVE PREVIEW

Professor Ewan McKendrick University of Oxford SETTING THE SCENE - - PowerPoint PPT Presentation

THE IMPACT OF COVID-19: FRUSTRATION, FORCE MAJEURE, HARDSHIP AND DEALING WITH UNCERTAINTY Professor Ewan McKendrick University of Oxford SETTING THE SCENE Contracts entered into in 2019 Contracts entered into in January or February


slide-1
SLIDE 1

THE IMPACT OF COVID-19: FRUSTRATION, FORCE MAJEURE, HARDSHIP AND DEALING WITH UNCERTAINTY

Professor Ewan McKendrick University of Oxford

slide-2
SLIDE 2

SETTING THE SCENE

  • Contracts entered into in 2019
  • Contracts entered into in January or February

2020

  • Contracts entered into in March 2020 or

thereafter

  • The response of the Chinese authorities –

issuing force majeure notices

  • The Cabinet Office response – encouraging co-
  • peration
slide-3
SLIDE 3
  • A doctrine which operates within narrow limits
  • Contract not frustrated if provision made for event in the

contract itself

  • Subsequent impossibility
  • Subsequent illegality
  • Performance radically different from that which was in

the contemplation of the parties at the time of entry into the contract

  • Not an escape route from a bad bargain
  • Drastic consequences of its invocation
  • Doctrine only open to review by the Supreme Court

FRUSTRATION: INTRODUCTION

slide-4
SLIDE 4

SUBSEQUENT ILLEGALITY

  • Focus here is on what the law requires, not on

government guidance which does not have the force of law

  • Illegality as a matter of English law, not foreign law
  • Which has had the effect of removing all or substantially

all of the benefit that one party receives from the performance of the contract

  • Fact that illegality is foreseeable is irrelevant
  • Cannot make express provision for subsequent illegality
  • Heavy public policy influence
  • Contrast discretionary approach in Patel v Mirza
slide-5
SLIDE 5
  • Impossibility, not impracticality
  • Not sufficient that performance has become

prohibitively expensive

  • A partial failure of supplies will not suffice –

failure must be total so that performance is impossible: Super Servant II

  • Impossibility must not be attributable to fault of

either party

  • Must not have been foreseeable

IMPOSSIBILITY

slide-6
SLIDE 6

DELAY

  • Delay must be abnormal
  • Outside what the parties could have

reasonably contemplated at the time of entry into the contract

  • Prospective not retrospective
  • Compare length of delay to duration of

contract

slide-7
SLIDE 7

EFFECTS OF FRUSTRATION

  • Automatic discharge of the contract
  • Discharge prospective, not retrospective
  • Law Reform (Frustrated Contracts) Act 1943
  • Reverse unjust enrichments but not loss

apportionment

  • Sums paid before discharge recoverable, sums

due cease to be payable - allowance for expenses

  • Non monetary benefits – if there is a valuable

benefit may be required to pay a just sum

slide-8
SLIDE 8

FORCE MAJEURE CLAUSES INTRODUCTION

  • Force majeure not a legal doctrine in

English law – compare French law

  • A contract term
  • Important to examine the content of the

term – be careful with ‘boilerplate’ clauses

  • The function of the clause (i) shield from

liability in damages, (ii) suspension of the contract, (iii) termination of the contract

slide-9
SLIDE 9

INTERPRETATION OF FORCE MAJEURE CLAUSES

  • Approach to construction – need for clear words
  • Contra proferentem rule – unlikely to apply
  • Burden of proof
  • Must the event be unforseeable?
  • The specific events – pandemic or epidemic –

government action - embargo

  • What is the value of the list?
  • Examine the nature of the events – is there a

link between them?

slide-10
SLIDE 10

THE ‘WRAP UP’ PROVISION

  • The general wrap-up provision (‘similar

events which reasonably may impede, prevent or delay the performance of this contract’)

  • Does the ejusdem generis rule apply?
  • If it does, can it be excluded?
  • Why insert a ‘wrap up’ provision of this

type?

slide-11
SLIDE 11

BEYOND THE (REASONABLE) CONTROL OF THE PARTIES

  • Must the event be beyond the control of

the parties?

  • As a matter of implication
  • As a result of an express term of the

contract

  • Is there a difference between ‘control’ and

‘reasonable control’?

slide-12
SLIDE 12

CHANGE IN ECONOMIC CIRCUMSTANCES

  • Can a party for whom performance has become

significantly more expensive rely on a force majeure clause?

  • Depends on the wording
  • ‘If either party is by reason of force majeure

rendered unable wholly or in part to carry out its

  • bligations under this agreement then…
  • ‘prevent’ ‘hinder’ or ‘impede’ performance
slide-13
SLIDE 13

THE CAUSAL LINK

  • Generally the force majeure event must be the

cause of the non-performance

  • But what of the case where the party seeking to

rely on the clause would not have been able to perform in any event?

  • May be irrelevant where the party is relying on

the clause solely to bring about its prospective discharge

  • But may be very relevant where reliance is

placed on the clause in order to shield a party from liability in damages

slide-14
SLIDE 14

NOTIFICATION OBLIGATIONS

  • Is there a contractual requirement to give

notice of the occurrence of a force majeure event?

  • Is the giving of notice a condition

precedent to reliance upon the clause?

  • Remedies for non-compliance?
  • When must notice be given?
  • What form must the notice take?
slide-15
SLIDE 15

THE EFFECT OF THE CLAUSE

  • Shield the party relying on the clause from

liability in damages

  • Enable a party to suspend performance of the

contract for the duration of the force majeure event

  • Entitle the party relying on the clause to

terminate the contract

  • Bring about the automatic termination of the

contract

  • Depends on the drafting of the contract
slide-16
SLIDE 16
  • What amounts to ‘hardship’
  • Is the clause enforceable or is it an agreement to agree?
  • Likely to be used where wish to be able to adapt the

contract because of changed circumstances

  • Can the parties be required to re-negotiate the terms of

their contract to restore the equilibrium of the contract?

  • If the parties refuse to do so or the renegotiation is

unsuccessful, what remedies are available?

  • Will the court adapt the contract or is the only remedy
  • ne in damages?
  • Is there a difference between litigation and arbitration?

HARDSHIP CLAUSES

slide-17
SLIDE 17

MATERIAL ADVERSE CHANGE CLAUSES

  • Loan agreements and financial contracts
  • What is a ‘material’ adverse change?
  • What are the consequences of reliance

upon the clause?

  • Why rely on such a clause?
  • When will it be used in preference to a

force majeure clause?

slide-18
SLIDE 18

DEALING WITH UNCERTAINTY

  • What provision can you make for the impact of

COVID-19 on you or your clients’ contractual

  • bligations?
  • Is the aim to shield from liability in damages?
  • Is the aim to adapt the contract to changed

circumstances

  • Is termination the preferred option? If so, can

the termination event be identified with sufficient precision?

slide-19
SLIDE 19

DEALING WITH UNCERTAINTY

  • The problem of long term contracts
  • Move towards short term contracts?
  • Preserving flexibility
  • But avoid drafting agreements to agree

which are unenforceable